Dolben v. Duncan Construction Co.

177 N.E. 105, 276 Mass. 242, 1931 Mass. LEXIS 1014
CourtMassachusetts Supreme Judicial Court
DecidedJune 26, 1931
StatusPublished
Cited by14 cases

This text of 177 N.E. 105 (Dolben v. Duncan Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dolben v. Duncan Construction Co., 177 N.E. 105, 276 Mass. 242, 1931 Mass. LEXIS 1014 (Mass. 1931).

Opinion

Sanderson, J.

The plaintiff brought this bill against the Duncan Construction Company, the city of Medford, and the New Amsterdam Casualty Company, hereinafter referred to, respectively, as the contractor, the city, and the surety, alleging that the contractor entered into a contract with the city for the construction of a school building and defaulted in performance of the contract. The plain[247]*247tiff is a subcontractor and the bill is brought both in his own behalf and in behalf of all subcontractors who may join therein to obtain satisfaction for their claims from the money retained by the city under the contract and from the bond of the surety, the money and bond being alleged to be the security obtained under G. L. c. 149, § 29. Twenty-nine subcontractors and the Manufacturers National Bank of Lynn intervened, the latter alleging that it held an assignment from the contractor dated August 21, 1926, of the moneys due and to become due from the city. The surety filed a cross bill against the city, alleging that it held an assignment from the contractor dated on or about June 15, 1926, of all moneys due and to become due from the city. The case was referred to a master and the interlocutory and final decrees were based upon his report, certain exhibits and an agreement concerning one of them. The court entered a decree disallowing the claims of certain interveners and allowing the claims of the petitioner and other subcontractors in the total amount of $40,588.57 with interest; holding that the bond furnished by the contractor and the surety was the sole security obtained by the city for the payment of the subcontractors’ claims and that the building was completed by the city in accordance with the terms of the contract; and adjudging that at the time the surety filed its cross bill the city owed the surety, as assignee of the contractor in respect to the contract, the sum of $33,335.34. The decree ordered that the city apply this money in satisfaction of the subcontractors’ claims, the additional funds necessary for the purpose to be furnished by the surety. The intervening petition of the Manufacturers National Bank was dismissed. From this decree the city, the surety and the bank appealed.

G. L. c. 149, § 29, required the officers contracting in behalf of the city to obtain security by bond or otherwise for the payment by the contractor and subcontractors for labor performed or furnished and materials used in the construction of the building. One of the contract documents referred to in the contract contained a provision that the contractor [248]*248should furnish a satisfactory surety bond in an amount equal to fifty per cent of the contract price for the payment of all labor performed or furnished and all materials used in the fulfillment of the contract, and for the faithful performance of all the terms and conditions of the contract, and a form of bond accompanied the contract substantially like that later given. The bond furnished was upon condition that the contractor would faithfully perform the contract on its part , and satisfy all claims and demands incurred for the same and would fully indemnify and save harmless the city from all costs and damages which it might suffer by reason of the contractor’s failure so to do, and would fully reimburse and pay the city all outlays and expense which the city might incur in making good any default and would pay all persons who had contracts directly with the contractor for labor and materials. This bond given in compliance with the contract was in terms broad enough to meet the statutory requirements, and the master found that it was intended by all parties to be security taken by the city under the statute. The trial judge was right in his conclusion that the bond while conditioned on the performance of the contract was also obtained as security for payment by the contractor and subcontractors for labor performed or furnished and for materials used in the construction of the building, as provided by statute. See J. H. McNamara, Inc. v. McGuire, 254 Mass. 589; A. L. Smith Iron Works v. Maryland Casualty Co. 275 Mass. 74. Neither the provision in the bond limiting the term within which an action may be brought on it nor its other provisions required the conclusion that it was not a bond under the statute. See now St. 1929, c. 110.

By the contract the right was reserved in the city to retain from the monthly payments to the contractor a percentage of the value of labor and materials incorporated in the work and of materials stored at the site during the preceding month. Final payment was to become due sixty-three days after substantial completion of the work provided it be completed and the contract fully performed. The city having obtained security by bond was not required to furnish other [249]*249and additional security for payment by contractors and subcontractors for labor and materials. George H. Sampson Co. v. Commonwealth, 208 Mass. 372. Hunter v. Boston, 218 Mass. 535, 538. McClintic-Marshall Co. v. New Bedford, 239 Mass. 216. See J. H. McNamara, Inc. v. McGuire, 254 Mass. 589.

The bond was given to afford protection to laborers and materialmen as well as to the owner. Equitable Surety Co. v. McMillen, 234 U. S. 448, 454. In Hunter v. Boston, 218 Mass. 535, the bond purported to be security only for the faithful furnishing of material and doing of the work required of the contractor by the contract, while the contract provided that the payments were to be retained to settle claims for materials or labor furnished where claims have been filed with the city by subcontractors.

In Otis Elevator Co. v. Long, 238 Mass. 257, there was a finding by the master that both the money retained by the city and the bond were security, but in the case at bar there is no such finding as to the money retained by the city. The provisions for the retention of money by the city to which reference has been made must be held upon this record to be for the city’s own protection and not to provide security for labor and materials furnished, and the conclusion of the trial judge that the bond was the sole security under G. L. c. 149, § 29, for payment for labor furnished and materials used in the construction of the building was right.

It is contended by the surety that, because of two clauses numbered 9 and 18 in the printed parts of several of the contracts between the contractor and subcontractors who had filed claims, these claimants have waived their equitable liens or, if not, that their claims were prematurely filed. Clause number 9 in substance provided that these contractors waived and released all lien or right of lien then existing or that might thereafter arise for work or labor performed or material furnished under this contract, under any lien laws upon the building, the land upon which the same is situated, and upon any money or moneys due or to become due from any person or persons to the contractor, [250]*250and agreed to furnish a good and sufficient waiver of lien on the premises from every person or corporation furnishing labor or material for the premises under the subcontractor.

The judge ruled that the waiver expressed in this clause applied only to such lien, if any, as the subcontractor might thereafter have upon any money or moneys due or to become due from the city to the principal contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Venus Drywall, Inc. v. Kullman Industries, Inc.
5 Mass. L. Rptr. 70 (Massachusetts Superior Court, 1996)
Warren Brothers Company, Etc. v. Cardi Corporation
471 F.2d 1304 (First Circuit, 1973)
WARREN BROTHERS ROADS CO. v. Joseph Rugo, Inc.
245 N.E.2d 243 (Massachusetts Supreme Judicial Court, 1969)
Vance v. City of Haverhill
225 N.E.2d 373 (Massachusetts Supreme Judicial Court, 1967)
Duteau v. Salvucci
115 N.E.2d 726 (Massachusetts Supreme Judicial Court, 1953)
Hartford Accident & Indemnity Co. v. Casassa
16 N.E.2d 860 (Massachusetts Supreme Judicial Court, 1938)
Broga v. Leo
4 N.E.2d 295 (Massachusetts Supreme Judicial Court, 1936)
Gerber v. Berstein
3 N.E.2d 223 (Massachusetts Supreme Judicial Court, 1936)
Barry v. Duffin
195 N.E. 511 (Massachusetts Supreme Judicial Court, 1935)
Carter v. Commonwealth
194 N.E. 915 (Massachusetts Supreme Judicial Court, 1935)
Boston Heating Co. v. Middleborough Savings Bank
193 N.E. 12 (Massachusetts Supreme Judicial Court, 1934)
Hub Steel & Iron Works, Inc. v. Dyer
186 N.E. 645 (Massachusetts Supreme Judicial Court, 1933)
Peerless Unit Ventilation Co. v. D'Amore Construction Co.
186 N.E. 280 (Massachusetts Supreme Judicial Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
177 N.E. 105, 276 Mass. 242, 1931 Mass. LEXIS 1014, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dolben-v-duncan-construction-co-mass-1931.