Bay State Dredging & Contracting Co. v. W. H. Ellis & Son Co.

126 N.E. 468, 235 Mass. 263, 1920 Mass. LEXIS 725
CourtMassachusetts Supreme Judicial Court
DecidedMarch 17, 1920
StatusPublished
Cited by16 cases

This text of 126 N.E. 468 (Bay State Dredging & Contracting Co. v. W. H. Ellis & Son Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bay State Dredging & Contracting Co. v. W. H. Ellis & Son Co., 126 N.E. 468, 235 Mass. 263, 1920 Mass. LEXIS 725 (Mass. 1920).

Opinion

Pierce, J.

This is a bill in equity brought by the plaintiff in behalf of itself and of all other creditors of the defendant W. H. Ellis and Son Company who may be permitted to join as parties plaintiff against W. H. Ellis and Son Company, the Commonwealth of Massachusetts and the National Surety Company, under R. L. c. 6, § 77, to recover for labor performed or furnished and for materials used in the construction or repair of a pier and steel shed in the city of New Bedford under a contract dated January 5, 1915, between the Commonwealth of Massachusetts, acting by its Board of Harbor and Land Commissioners, and W. H. Ellis and Son Company, and is before this court on a reservation from the Superior Court. No question is raised as to the validity of the contract. ■

On January 6, 1915, W. H. Ellis and Son Company, as principal, and the National Surety Company, as surety, in pursuance of the contract and of. the statutes of the Commonwealth, executed and delivered to the Commonwealth of Massachusetts a bond conditional upon the payment by it for labor performed or furnished and for materials used in the construction or repair of said public work. Thereafter the Ellis company began work under said contract, and from time to time entered into subcontracts with the remaining intervening plaintiffs to furnish materials and perform labor of various kinds in connection therewith. While" the work was progressing under the contract, on April 11, 1917, the Commonwealth of Massachusetts, acting by the Commission on Waterways and Public Lands, which commission had succeeded to the powers and duties of the Harbor and Land Commission, entered into a written modification of the original contract with the Ellis company, which modification released the Ellis company from its obligation under the contract to construct a driveway through the centre of the pier and through the shed, of vitrified paving brick, wood blocks or granite blocks.

When the contract was thus modified, the driveway had been filled with dirt, but had not been surfaced in any way. Regard[266]*266ing the driveway the master found that the Commonwealth of Massachusetts always intended to have it constructed; that it was an important portion of the public work being constructed and was reasonably necessary to its efficient use; that the commission had not fully decided as to the method of construction when the contract was modified at the request of the Ellis company; that the commission then stated to the Ellis company that "they proposed to re-advertise for bids for the driveway;” that it was re-advertised in a manner "to change the original method [of construction^ as provided in the original Ellis company contract, by laying a concrete surface over a portion of the driveway, viz., under the shed and across the end of the pier.” This method was adopted and executed by another contractor under a new contract concerning this particular work. The work contracted to be done by the Ellis company under the contract of January 5, 1915, as modified by the agreement of April 11, 1917, was completed on September 4, 1917. The driveway under the new contract was constructed and completed some time in October, 1917, by the new contractor, in the method advertised after the release of the Ellis company from its contract in relation to its construction. After the entry of the petition the plaintiff and one intervener settled their claims against the defendants, and the suit is prosecuted by the remaining intervenors.

At the hearing before the master there was evidence and the master-found that the various plaintiffs filed with the Harbor and Land Commission or their successors, the Commission on Waterways and Public Lands, claims against the Ellis company in the proper form and in compliance with the statute, except as to the question whether some of them were seasonably filed; and the issues now presented are whether certain of the plaintiffs seasonably filed proofs of claim, and, as to certain of them, (Joseph Langlois and Charles S. Ashley and Sons Company,) whether the labor performed and materials furnished are of such a character as to permit them to recover in this proceeding.

The claim of Langlois is for the use of a staging and falls which were reasonably used by a subcontractor of the Ellis company in the necessary work of painting and plastering upon the pier and steel shed. They remained upon the premises after the completion of the work of painting and plastering, were damaged and ren[267]*267dered unfit for use, and their whereabouts became unknown before the plaintiff or the subcontractor was notified to remove them. They were not incorporated in the building, and the mere use of an appliance, however necessary or useful it may be to the prosecution of a contract for “the construction or repair of public buildings or other public works,” is not labor performed or furnished or material used in such construction or repair within the reasonable intendment of R. L. c. 6, § 77. The claim has no standing under R. L. c. 6, § 77. Kennedy v. Commonwealth, 182 Mass. 480. Thomas v. Commonwealth, 215 Mass. 369.

The claim of Charles S. Ashley and Sons Company is for a premium on an insurance liability policy issued to the" Ellis company; it is not for labor or material performed or furnished, and is not within the statute. Kennedy v. Commonwealth, supra. Sampson v. Commonwealth, 202 Mass. 326. Friedman v. County of Hampden, 204 Mass. 494.

The remaining claims which are contested fall into one or the other of two classes: (1) those wherein the sworn statements of claims were filed before September 4, 1917, and (2) those wherein the sworn statements of claims were filed more than sixty days after September 4, 1917. The defendant National Surety Company contends that the statute is in derogation of common right, should be strictly construed, and that so construed the sworn statement of every claimant under the statute must be filed within the period of sixty days which begins September 4, 1917, and ends November 3, 1917. Assuming, without deciding, that the statute in question in analogy to the construction of mechanic lien statutes is to be construed strictly, as to which see Gale v. Blaikie, 129 Mass. 206, 209; Whalen v. Collins, 164 Mass. 146; Angier v. Bay State, Distilling Co. 178 Mass. 163; Pratt & Forest Co. v. Strand Realty Co. of Lowell, 233 Mass. 314; Nash v. Commonwealth, 174 Mass. 335, 182 Mass. 12; Burr v. Massachusetts School for Feeble-Minded, 197 Mass. 357; Friedman v. County of Hampden, 204 Mass. 494; E. I. Dupont De Nemours Powder Co. v. CulginPace Contracting Co. 206 Mass. 585; Philadelphia v. Fidelity & Deposit Co. of Maryland, 231 Penn. St. 208; Ann. Cas. 1912 B 1085 note, no one could be injured in the legal sense if a claim within the terms of the statute was filed with the designated officer or agent of the Commonwealth at any time within sixty [268]*268days after labor had been performed for or material had been furnished to the contractor. The contractor and his creditors could not be injured because the filing of the sworn statement before the completion of the work covered by the principal contract could-have no legal effect to establish the debt, to create a lien or to accelerate the time at which the laborer or materialman would be entitled to obtain the benefit of the security which the statute requires the agents of the Commonwealth to obtain of the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William W. Jurczyk, Inc. v. American Fidelity Co.
17 Mass. App. Dec. 1 (Mass. Dist. Ct., App. Div., 1961)
Pan American Surety Co. v. Board of Public Instruction
76 So. 2d 868 (Supreme Court of Florida, 1955)
Tanzilli v. Casassa
85 N.E.2d 220 (Massachusetts Supreme Judicial Court, 1949)
Sherrer v. Sherrer
69 N.E.2d 801 (Massachusetts Supreme Judicial Court, 1946)
Johnson-Foster Co. v. D'Amore Construction Co.
50 N.E.2d 89 (Massachusetts Supreme Judicial Court, 1943)
Pittsburgh v. Parkview Construction Co.
23 A.2d 847 (Supreme Court of Pennsylvania, 1942)
Anderson v. United States Fidelity & Guaranty Co.
104 P.2d 906 (New Mexico Supreme Court, 1940)
Mario Pandolf Co. v. Commonwealth
21 N.E.2d 221 (Massachusetts Supreme Judicial Court, 1939)
McFarland v. Rogers
184 A. 391 (Supreme Judicial Court of Maine, 1936)
Employers' Liability Assur. Corp. v. Cannon
1935 OK 795 (Supreme Court of Oklahoma, 1935)
Peerless Unit Ventilation Co. v. D'Amore Construction Co.
186 N.E. 280 (Massachusetts Supreme Judicial Court, 1933)
Dolben v. Duncan Construction Co.
177 N.E. 105 (Massachusetts Supreme Judicial Court, 1931)
American Casting Co. v. Commonwealth
174 N.E. 174 (Massachusetts Supreme Judicial Court, 1931)
Royal Indemnity Co. v. Day & Maddock Co.
150 N.E. 426 (Ohio Supreme Court, 1926)
Southern Surety Co. v. Metropolitan Sewerage Commission
187 Wis. 206 (Wisconsin Supreme Court, 1923)
Carey v. Casey
139 N.E. 384 (Massachusetts Supreme Judicial Court, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
126 N.E. 468, 235 Mass. 263, 1920 Mass. LEXIS 725, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bay-state-dredging-contracting-co-v-w-h-ellis-son-co-mass-1920.