William W. Jurczyk, Inc. v. American Fidelity Co.

17 Mass. App. Dec. 1
CourtMassachusetts District Court, Appellate Division
DecidedJuly 1, 1961
DocketNo. 143788
StatusPublished

This text of 17 Mass. App. Dec. 1 (William W. Jurczyk, Inc. v. American Fidelity Co.) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William W. Jurczyk, Inc. v. American Fidelity Co., 17 Mass. App. Dec. 1 (Mass. Ct. App. 1961).

Opinion

Garvey, J.

This is an action of contract. The Atlantic Refining Company executed two contracts with one Woodworth for the construction by Woodworth of two gasoline filling stations, one in Chicopee and the other in Springfield. Woodworth as principal and the defendant as surety executed a “Contractor’s Bond” for each of these projects.

Under the terms of these two bonds, the defendant surety company guaranteed the faithful performance of the contractor’s obligations under the written building contracts, [3]*3as well as the payment of all just bills or charges for labor and materials due in connection with the performance of these contracts.

The plaintiff, a sub-contractor, not having been paid for the items in suit by Woodworth brings this action against the surety, under the provisions of G. L. (Ter. Ed.) c. 149, §29A, which permits one who furnishes labor and materials to sue the surety directly. The declaration is in two counts, each with an account annexed for the two separate construction contracts. Count One for the sum of $2129.43 of which $1237.32 is for equipment used, and Count Two for the sum of $1715.08 of which $663.00 is for equipment used. The answer, as amended on February 21, 1958, the date of the trial, contains a general denial, an allegation that the obligee under the bonds made premature payments to the principal without the knowledge and consent of the defendant, thereby releasing it as surety, and an allegation that the plaintiff executed a release and waiver of liens, wherefore the defendant owes it nothing.

Plaintiff did not file within three days a specific denial of the genuineness of its signature on the releases and waiver of liens set forth in defendant’s amended answer and made no demand that it should be proved at the trial. At the hearing on the draft report the trial judge allowed a motion of the plaintiff to amend its pleadings by including a special answer to the defendant’s amended answer, setting out a denial of its signature [4]*4to the alleged releases and a demand for proof.

The case was tried on a written stipulation except for the testimony of William W. Jurczyk, an officer of the plaintiff corporation, who denied that he signed the releases and waivers of liens attached to the stipulation and marked “D” and “F” respectively, and the testimony of Woodworth, the contractor and principal under the bonds, that he saw William W. Jurczyk sign those documents.

The stipulation agreed upon was as follows:

1. The Atlantic Refining Company executed a contract dated May 22, 1956 with C. S. Woodworth for the construction of a filling station at 385 Memorial Drive in Chicopee, Mass. A duplicate original of said contract shall be introduced into evidence as Exhibit 1.

2. The Atlantic Refining Company executed a contract dated July 19, 1956 with C. S. Woodworth for the construction of a filling station at Carew and Nottingham Streets in Springfield, Mass. The provisions of said contract insofar as they are material to this action are identical with those of Exhibit 1 and reference may be had thereto in lieu of introducing that separate contract.

3. In accordance with the provisions of paragraph 3, page 2 of said contracts (see Exhibit 1 headed “Contractor’s Bond”), C. S. Woodworth as principal and defendant as surety executed Bond No. 801901 on the Memorial Drive Contract, copy of which is [5]*5attached hereto and marked “A”, and Bond No. 801028 on the Carew and Nottingham Contract, copy of which is attached hereto and marked “B”.

4. The plaintiff supplied C. S. Wood-worth with labor, materials and rental equipment as shown in Schedule “A” of the plaintiff’s declaration which were used on the Memorial Drive contract referred to in Count 1 of said declaration.

5. The plaintiff supplied C. S. Wood-worth with labor, materials and rental of equipment as shown in Schedule “B” of the plaintiff’s declaration which were used on the Carew and Nottingham contract referred to in Count 2 of said declaration.

6. In accordance with the provisions of paragraph 3, page 8 of said contracts (see Exhibit 1) headed “Waiver of Liens and Claims” no mechanics’ claims or liens were filed by C. S. Woodworth or any of the subcontractors, including the plaintiff, against the buildings, structures or site of The Atlantic Refining Company for or on account of any work done or materials furnished under either the Memorial Drive Contract or the Carew and Nottingham Contract.

7. In accordance with the provisions of paragraph 3, page 7 of said contracts (see Exhibit 1), headed “Payment of Sub-contractors and Release of Liens”, C. S. Wood-worth delivered to The Atlantic Refining Company a document entitled “Release of Liens” on the Memorial Drive Contract, a [6]*6copy of which is attached hereto and marked “C” with attached releases of all sub-contractors, including that purporting to be the release of the plaintiff (Emphasis supplied) which is attached hereto and marked “D” and a document entitled “Release of Liens” on the Carew and Nottingham Contract, a copy of which is attached hereto and marked “E” with attached releases of all sub-contractors, including that purporting to be the release of the plaintiff (Emphasis supplied) which is attached hereto and marked “F”.

8. In reliance on said documents marked “C”, “D”, “E” and “F” The Atlantic Refining Company made final payment to C. S. Woodworth on the Memorial Drive Contract on January 16, 1957 in the sum of $6150.25 and on the Carew and Nottingham Contract on February 8, 1957 in the sum of $4653.50; the provisions for final payment being on page 7 of said contracts, headed “Payment of Sub-contractors and Release of Liens” and on page 9, headed “Contract Price-Payments”.

9. Final inspection of both the Memorial Drive project and the Carew and Nottingham project was made by The Atlantic Refining Company on May 7, 1957, and both projects were accepted as completed by the Atlantic Refining Company on that date.

The trial judge found for the plaintiff and assessed damages under Count One in the sum of $2129.43 and under Count Two in the sum of $1715.08, and made the following special findings of fact:

[7]*7“The Plaintiff furnished labor and materials to Chester Woodworth as alleged in his declaration which is in two counts.
Chester Woodworth was under contract with the Atlantic Refining Co. to do this work and a penal bond was supplied by Woodworth to the Atlantic Refining Co.
“The Defendant was surety upon this bond.
“The Plaintiff has not been paid.
“The Defendant produced two releases purported to be signed by the Plaintiff.
“Chester Woodworth testified that he saw the Plaintiff sign the releases. He also testified that they were dated at a different date than that on which the Plaintiff signed. He admitted committing the contemptible act of taking these releases to a notary public and obtaining his jurat thereon although the Plaintiff was not present at the time.
“I do not accept the testimony by Chester Woodworth that he saw the Plaintiff sign the releases.
I find that the Plaintiff did not sign the releases.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Veneto v. McCloskey & Co.
128 N.E.2d 337 (Massachusetts Supreme Judicial Court, 1955)
Salvato v. DiSILVA TRANSPORTATION CO. INC.
108 N.E.2d 51 (Massachusetts Supreme Judicial Court, 1952)
True v. Dillon
138 Mass. 347 (Massachusetts Supreme Judicial Court, 1885)
Ham v. Kerwin
15 N.E. 657 (Massachusetts Supreme Judicial Court, 1888)
Loonie v. Wilson
124 N.E. 272 (Massachusetts Supreme Judicial Court, 1919)
Bay State Dredging & Contracting Co. v. W. H. Ellis & Son Co.
126 N.E. 468 (Massachusetts Supreme Judicial Court, 1920)
American Casting Co. v. Commonwealth
174 N.E. 174 (Massachusetts Supreme Judicial Court, 1931)
Griffin v. New York, New Haven & Hartford Railroad
181 N.E. 839 (Massachusetts Supreme Judicial Court, 1932)
Walsh Holyoke Steam Boiler Works, Inc. v. McCue
289 Mass. 291 (Massachusetts Supreme Judicial Court, 1935)
Gallo v. Foley
11 N.E.2d 803 (Massachusetts Supreme Judicial Court, 1937)
Arabia v. John Hancock Mutual Life Insurance
17 N.E.2d 202 (Massachusetts Supreme Judicial Court, 1938)
Dunbar v. Ferrera Bros.
27 N.E.2d 675 (Massachusetts Supreme Judicial Court, 1940)
Boutillier v. Wesinger
78 N.E.2d 195 (Massachusetts Supreme Judicial Court, 1948)
Blender v. Epstein
138 N.E.2d 270 (Massachusetts Supreme Judicial Court, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
17 Mass. App. Dec. 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-w-jurczyk-inc-v-american-fidelity-co-massdistctapp-1961.