George H. Sampson Co. v. Commonwealth

94 N.E. 473, 208 Mass. 372, 1911 Mass. LEXIS 835
Massachusetts Supreme Judicial Court·Decided March 7, 1911·Published·Cited by 8 cases

Opinion

Morton, J.

This case was before this court and is reported in 202 Mass. 326. One of the questions then before the court was whether the right to compel the surety on the bond which the Commonwealth had taken from the contractors pursuant to Pub. Sts. c. 16’ § 64, (now R. L. c. 6, § 77,) to make payment for the benefit of the plaintiff could be enforced in that suit, and it was held that it could be so enforced. Another of the questions was whether the plaintiff was entitled to a lien for the powder which it had sold to the contractors and which they had [373] expended in excavating the trench for the aqueduct by blasting out rock the greater part of which was used in its construction. It was held that the plaintiff was entitled to a lien for the powder so used. After the filing of the bill in this case, pursuant to an arrangement between' the parties interested, by which no one’s rights were to be affected except so far as the amount of the plaintiff’s claim might be reduced thereby, the Commonwealth paid to the plaintiff and others, from funds in its hands reserved by it from moneys due to the contractors, thirty-five per cent of their respective claims against the contractors. These payments were made with the assent of the contractors, and, upon receiving the payment made to it, the plaintiff with the consent of the surety released the Commonwealth. The amount so paid to the plaintiff was $1,793.89. The total amount of the plaintiff’s claim was $5,125.41. That was the sum on which the percentage was calculated. Of that amount $4,315.71 was for powder which had been used and expended as aforesaid, and the balance, $809.70, was for fittings to replace worn parts of machinery, tools and other supplies sold and delivered to the contractors for and on account of the work to which their contract with the Commonwealth to build the aqueduct related. The plaintiff applied $809.70 of the amount received by it to the payment of its bill for fittings, tools and other supplies, and the remainder, $984.19, to the bill for powder. The surety contended that the whole amount should be applied to the bill for powder. But the judges of the Superior Court * ruled in favor of the plaintiff and entered a decree accordingly. The surety appealed.

In addition to the amount received from the Commonwealth the plaintiff was allowed a dividend from the estate of Shanahan, one of the contractors, of $1,452.97. The costs of collection were $363.24, and the plaintiff contended that it should be required to credit only the net proceeds. But the judges ruled otherwise and required the plaintiff to credit the whole amount of the dividend. No exception to this ruling and no appeal from the decree was taken by the plaintiff, and no question in regard to that matter is, therefore, now before us.

[374] The Commonwealth- has filed no brief and the parties at issue now are the plaintiff and the surety, and the principal question between them is whether the plaintiff had a right to apply the amount received from the Commonwealth as it did. We think that it had the right, and that the ruling of the judges was correct. The surety company contends that the decree should run against the Commonwealth and not against it, on the ground that according to the decree in Wash v. Commonwealth, 174 Mass. 335, the Commonwealth held the money which it paid over as security for the payment of the claims filed with the sewerage board and to the extent to which it paid over the same it discharged the surety company. But this case differs materially from the case of Wash v. Commonwealth, supra, and also from the similar cases of Friedman v. County of Hampden, 204 Mass. 494, and Burr v. Massachusetts School for the Feeble-Minded, 197 Mass. 357. In those cases no bond was taken by the Commonwealth as required by the statute, and unless the provision in the contract giving the public authorities the right to reserve from the contractors money due to the latter were construed as constituting the security required by the statute, the Commonwealth had taken no security. In this case bonds were taken as required by the statute for the express purpose of complying with the statute, and those decisions are not, therefore, applicable. If the money in the hands of the Commonwealth had been reserved for lienable claims as it was in the cases cited above, the surety would have been discharged pro tanto, at least, by any different application of it. Guild v. Butler, 127 Mass. 386. But the money reserved in this case did not come within the rule laid down in those cases.

Free access — add to your briefcase to read the full text and ask questions with AI

George H. Sampson Co. v. Commonwealth, 94 N.E. 473, 208 Mass. 372, 1911 Mass. LEXIS 835 (Mass. 1911).

94 N.E. 473 (George H. Sampson Co. v. Commonwealth) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

County of Audrain Ex Rel. First National Bank of Mexico v. Walker
155 S.W.2d 251 (Missouri Court of Appeals, 1941)
State Bank of Wheatland v. Turpen
34 P.2d 1 (Wyoming Supreme Court, 1934)
Metropolitan Casualty Ins. v. United Brick & Tile Co.
1934 OK 14 (Supreme Court of Oklahoma, 1934)
Hub Steel & Iron Works, Inc. v. Dyer
186 N.E. 645 (Massachusetts Supreme Judicial Court, 1933)
Dolben v. Duncan Construction Co.
177 N.E. 105 (Massachusetts Supreme Judicial Court, 1931)
McClintic-Marshall Co. v. City of New Bedford
131 N.E. 444 (Massachusetts Supreme Judicial Court, 1921)
Aetna Accident & Liability Co. v. Alexander Lumber Co.
215 Ill. App. 555 (Appellate Court of Illinois, 1919)
Turner v. Woodard
259 F. 737 (First Circuit, 1919)