County of Audrain Ex Rel. First National Bank of Mexico v. Walker

155 S.W.2d 251, 236 Mo. App. 627, 1941 Mo. App. LEXIS 124
CourtMissouri Court of Appeals
DecidedOctober 31, 1941
StatusPublished
Cited by11 cases

This text of 155 S.W.2d 251 (County of Audrain Ex Rel. First National Bank of Mexico v. Walker) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Audrain Ex Rel. First National Bank of Mexico v. Walker, 155 S.W.2d 251, 236 Mo. App. 627, 1941 Mo. App. LEXIS 124 (Mo. Ct. App. 1941).

Opinions

*631 MAYFIELD, S. J.

— This is a suit brought against a performance bond given by one James C. Walker, an individual doing business as Acme Contracting Company, as principal, and the Fidelity and Casualty Company of New York, a corporation, as surety, for the faithful performance of a building contract made by Walker with’ the board of trustees for Audrain County, Missouri, for the erection of a Nurses’ Home at Mexico, Missouri. Judgment of the trial court was against Walker and his surety, but only the surety appealed here. The action is brought at the relation of the First National Bank of M'exieo, and by it the bank seeks in its own right, and not as an assignee or subrogee, to recover on such bond. For purposes of designation and identification the respective parties will be referred to in the following manner: James C. Walker, doing business as Acme Contracting Company, as Walker; the board of trustees, of Audrain County, as board; the Fidelity and Casualty Company of New York, as surety; First National Bank of Mexico, as the bank; and the building contract will be called contract. A jury was legally waived by all of the parties to the trial and verdict and judgment was rendered by the trial court in favor of the bank for the sum of the penalty of the bond, to be satisfied upon the payment of the principal sum of $3094.46, together with interest thereon at the rate of six per cent per annum from the 27th day of August, 1937, to the date of the rendition of the judgment, and amounting at the time of such rendition to $285.70, which made the total sum of the judgment amount to $3380.16. The defendant surety company had filed a counterclaim along with other defenses and the court denied recovery on such counterclaim. The answer of Walker was a general denial but did not rise to the status of a legal denial of the execution of the building contract or bond by him.

The petition filed by the plaintiff set up the incorporation of the bank and the surety company, alleged the style under which Walker was doing business, and that on the 5th day of December, 1935, Walker made a contract with the Board for the erection of a Nurses’ Home in the City of Mexico, Missouri, with the surety company and Walker giving a bond for the performance of such contract; that by the terms of such bond the obligors thereof bound themselves “to *632 pay to the proper parties as soon as the work contemplated by the contract had been completed, all amounts due for material, lubricants, oil, gasoline, grain, hay, feed, coal and coke, repairs on machinery, groceries and foodstuffs, equipment and tools, consumed or used in connection with the construction of such work, and for all labor performed in such work, whether by sub-contractor or otherwise, and to faithfully perform all and singular the terms and stipulations of said contract. Plaitniff further states that the work contemplated by said contract, has prior to the filing of this petition, been completed.”

The petition further alleged that before Walker began a performance of his contract, that he entered into an arrangement or agreement with the bank to the effect that Walker not being himself able to finance the payments for labor and materials used from time to time in the construction of the building, the bank would supply Walker with such funds; that pursuant to this arrangement the bank had advanced certain sums in various amounts and on different dates, and that the specific amount of $3094.46 was composed of funds supplied Walker by the bank between June 19, 1936, and August 7, 1936, and

“Plaintiff further states that all of the said sum of $3094.46 so furnished to Walker as aforesaid, was used by the said Walker for the payment of materials and labor used in and on the Nurses’ Home in Mexico, Missouri.

“Plaintiff further states that by reason of the foregoing breach of the terms and conditions of the bond aforesaid, by the said Walker, the said bank has been damaged in the principal sum of three thousand ninety-four and 46/100 dollars ($3,094.46) and the defendants have become liable to the said bank for said amount.”

Judgment ivas prayed for the penal sum of the bond to be satisfied upon the payment of the amount of damages with interest thereon from the first day of September; 1936, and costs. In addition to the counterclaim of the surety company referred to above, the answer of this company consisted of several pleas, among which was the usual general denial, but not the execution of the bond; also that the Statutes of Missouri in conformity to which said bond was alleged to have been given, prescribed and designated the persons entitled to sue on such bond and that the bank was not such a designated person and was not one furnishing any of the items prescribed or referred to in the Statutes. The other matters pleaded in the answer of the surety company beyond the admission of the execution of the bond sued upon, are not important to this opinion. At the trial of the cause it was shown by stipulation entered into by the surety company and the bank, by exhibits and witnesses, that in December of 1935, the County of Audrain in its regular capacity as such, desiring to erect a nurses’ home for such comity, entered into a contract with Walker for the erection of the building for that *633 purpose. The local representative of the surety company in that county, with Walker, executed the bond herein sued upon on the 5th day of December, 1935, which was the same date of the contract for the erection of said home. The condition and terms of such bond will be referred to later herein. Sometime the latter part of January, 1936, such local representative óf the surety company approached the president of the bank about furnishing funds to Walker with which to carry out his contract with the county and later such representative came back with Walker and several members of the board when the details of borrowing money for Walker were gone into and arrangements were made whereby the bank furnished funds as above stated; and on the 12th day of February, 1936, Walker executed a power of attorney to the bank, containing certain provisions, none of which are controlling in this opinion. It seems to be agreed by all of the parties, if Walker can be said to have agreed to anything in the trial, that the amount sought here to be recovered was actually advanced by the bank to Walker and was used by him in a legitimate manner for the payment of items that went into said home and toward performance of Walker’s contract. The trial court so found, and also found that the bond given here, “was required by, in pursuance of, executed under and complied with Section 2890, Session Acts of 1933, page 179, and Section 2891, R. S. Missouri, 1929.” These sections are now Sections 3277 and 3278, Revised Statutes 1939. The trial court also found that the home had been completed, and it was shown that the surety company had paid for some items for which it filed a counterclaim against the plaintiff. We do not deem either these items or the counterclaim important or controlling. In its conclusions of law, the trial court declared the capacity of the bank to maintain the action in the form it was brought; that failure to pay the bank “the balance due said bank . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. Louis Crum Corp. v. Alfred Lindgren, Inc.
564 S.W.2d 544 (Missouri Court of Appeals, 1978)
First State Bank v. Reorganized School District R-3, Bunker
495 S.W.2d 471 (Missouri Court of Appeals, 1973)
State Ex Rel. Farmers State Bank v. Kuipers Const. Co.
190 N.W.2d 769 (South Dakota Supreme Court, 1971)
United Pacific Insurance Co. v. First National Bank of Prestonsburg
457 S.W.2d 833 (Court of Appeals of Kentucky, 1970)
York v. Cline Construction Co.
336 S.W.2d 34 (Court of Appeals of Kentucky, 1960)
National Surety Corporation v. Fisher
317 S.W.2d 334 (Supreme Court of Missouri, 1958)
Bower v. Tebbs
314 P.2d 731 (Montana Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
155 S.W.2d 251, 236 Mo. App. 627, 1941 Mo. App. LEXIS 124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-audrain-ex-rel-first-national-bank-of-mexico-v-walker-moctapp-1941.