Barry v. Duffin

195 N.E. 511, 290 Mass. 398, 1935 Mass. LEXIS 1319
CourtMassachusetts Supreme Judicial Court
DecidedApril 10, 1935
StatusPublished
Cited by13 cases

This text of 195 N.E. 511 (Barry v. Duffin) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barry v. Duffin, 195 N.E. 511, 290 Mass. 398, 1935 Mass. LEXIS 1319 (Mass. 1935).

Opinion

Lummus, J.

In November, 1931, the original defendant Kennedy became the general contractor for the building of a road in Boston for the Commonwealth. The plaintiff Barry, a dealer furnishing crushed stone and stone dust to Kennedy for the job, brought this bill under G. L. (Ter. Ed.) c. 30, § 39, to obtain the benefit of security in the form of a bond upon which the defendant Maryland Casualty Company is surety and of money retained by the Commonwealth. Various subcontractors, and persons furnishing material to the contractor or a subcontractor, intervened for the purpose of sharing in the security.

The case was referred to a master under the form of reference set forth in Rule 86 of the Superior Court (1932). The claims of the plaintiff Barry and of many of the interveners are not now in controversy. The appeals of Kennedy’s trustee in bankruptcy and of Maryland Casualty Company present for our consideration the allowance of the claims of the interveners Bowen Contracting Company, Fisher Hill Company and Charles I. Hosmer, Inc., in addition to the disallowance of the claim of Kennedy to a larger award against the Commonwealth than was made.

1. The claim of Bowen Contracting Company. This company performed work in excavation as a subcontractor under Kennedy. The master found a balance due it of $2,532.21. The defendants seek to wipe out that balance by a charge in favor of Kennedy for the rehandling and spreading of excavated loam. Its contract required it to perform “Loam Excavation, including disposal” in “accord-

[401]*401anee with Section 3 of the Standard Specifications for state highway work.” Those specifications called for the “removal and satisfactory disposal” of all excavated material, and under the heading “Disposal of Material” provided: “All suitable materials removed from the excavation shall be used as far as practicable in the formation of the embankments, sub-grade, shoulders, etc., and at such other places as directed.” The master finds that the parties, while the work was being done and “until after the proceedings in this case were commenced interpreted the term ‘disposal’ as meaning only the initial removing and stacking of loam available for future removal to its final resting place.” That finding must stand, since no evidence is reported from which a different finding might be made. If Kennedy was content to accept the loam where it was stacked, and directed the claimant to stack it there, as might be found, the contract was satisfied according to its terms. The conclusion that Bowen Contracting Company owes nothing to Kennedy cannot be pronounced wrong.

The claim of Bowen Contracting Company is attacked also on what are thought to be technical grounds. It is not now argued that its contract was invalid because executed before its articles of organization were filed. See Colpitts v. L. C. Fisher Co. 289 Mass. 232, 233, and cases cited. It is contended, however, that an assignment of its claim to Oliver G. Kelley on September 6, 1932, deprived Bowen Contracting Company of the right to preserve its claim by a statement signed and sworn to by its attorney on September 14, 1932, and then duly filed. As a corporation, it could act only by an agent or attorney. Whether the attorney had authority at the time is unimportant, for the subsequent intervening petition for the enforcement of the claim impliedly ratified his act. Batchelder v. Hutchinson, 161 Mass. 462, 467.

There is nothing in the objection that the statement was filed, and the petition brought, by and in the name of Bowen Contracting Company, the assignor. The statute (G. L. [Ter. Ed.] c. 30, § 39), in providing that “the claimant” shall file a statement and subsequently a peti[402]*402tian, does not prohibit assignments. In Dolben v. Duncan Construction Co. 276 Mass. 242, 252, an assignor of a similar claim under the similar statute relative to public works undertaken by municipalities (G. L. [Ter. EdJ c. 149, § 29), filed the statement of claim without mentioning the assignment. This was held proper. The court said, “An assignee may by statute sue in his own name but he may also sue in the name of the assignor. G. L. c. 231, § 5.” In Williams v. Weinbaum, 178 Mass. 238, the assignor of a claim secured by a statutory mechanic’s lien upon real estate preserved the lien effectively by filing a sworn statement alleging a debt due to himself and bringing a petition in his own name for the benefit of the assignee. See also Moore v. Dugan, 179 Mass. 153, 158; Wiley v. Connelly, 179 Mass. 360; American Carpet Lining Co. v. Chipman, 146 Mass. 385. It is of no concern to the debtor whether proceedings are brought in the name of the assignor, or, where permitted, in the name of the assignee (Mayhew v. Pentecost, 129 Mass. 332, 338; Lewis v. Club Realty Co. 264 Mass. 588; Universal Adjustment Corp. v. Midland Bank, Ltd., of London, 281 Mass. 303, 311; Arwshan v. Meshaka, 288 Mass. 31), so long as the debtor is in no danger of double liability. Rogers v. Murch, 253 Mass. 467, 470, 471.

2. The claim of Fisher Hill Company, Inc. This company furnished to the intervener Bowen Contracting Company, and to the contractor Kennedy, gasoline which was consumed in the operation of machinery employed in doing the work of construction. In addition, it furnished to the contractor Kennedy other gasoline which was “used on this project,” being supplied to trucks. It cannot be assumed or found upon the master’s report that the trucks were not used in the work of construction. The claim was properly allowed. American Casting Co. v. Commonwealth, 274 Mass. 1.

3. The claim of Charles I. Hosmer, Inc. This claim is more complicated. Charles I. Hosmer and one Terrell M. Ragan were officers of Boston-Continental National Bank. On October 29, 1931, an agreement under seal was entered into between them and Kennedy, whereby “In consideration [403]*403of Charles I. Hosmer and/or Terrell M. Ragan being instrumental in obtaining financial backing for John F. Kennedy in connection with a bid of Morton and. Canterbury Streets, Boston, running to the Commonwealth of Massachusetts; and in further consideration of one dollar each to the other paid and duly received, it is hereby understood and agreed: 1. That all bridge work called for under the said contract is to be awarded to Charles I. Hosmer at the Coleman bid price so-called. 2. That all work other than the drainage shall, at the direction of Charles I. Hosmer, be let to subcontractors so chosen and approved by him. 3. That all checks received from the Commonwealth shall be sent to a nominee of Hosmer and Ragan and the disbursements therefrom countersigned by either of them or their nominee. 4. That in consideration of the foregoing the net profits arising out of this contract shall be divided: fifty percent to John F. Kennedy, twenty-five percent each to Ragan and Hosmer.” On the same day, as appears by a letter offered by the defendants, Ragan as president of the bank assured Maryland Casualty Company that the bank would lend Kennedy as much as $50,000 to insure the completion of the work. The master finds that the words, "being instrumental in obtaining financial backing for” Kennedy, meant that Hosmer and Ragan were to use their official positions in the bank to induce the bank to lend money to Kennedy up to the amount of $50,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Platt v. Plymouth Rock Assurance Corp.
2006 Mass. App. Div. 1 (Mass. Dist. Ct., App. Div., 2006)
Jach v. Trust Insurance Companies
1999 Mass. App. Div. 70 (Mass. Dist. Ct., App. Div., 1999)
Sanabia v. Travelers Insurance Co.
1999 Mass. App. Div. 46 (Mass. Dist. Ct., App. Div., 1999)
Proteon, Inc. v. Digital Equipment Corp.
9 Mass. L. Rptr. 445 (Massachusetts Superior Court, 1999)
Rubenstein v. Royal Insurance Co. of America
696 N.E.2d 973 (Massachusetts Appeals Court, 1998)
Gillespie v. McCourt
889 F. Supp. 5 (D. Massachusetts, 1995)
Jet Construction Co. v. C. C. Whitten, Inc.
54 Mass. App. Dec. 145 (Mass. Dist. Ct., App. Div., 1974)
Vance v. City of Haverhill
225 N.E.2d 373 (Massachusetts Supreme Judicial Court, 1967)
Pappastergion v. Royal Footwear, Inc.
33 Mass. App. Dec. 51 (Boston Municipal Court, 1965)
Duteau v. Salvucci
115 N.E.2d 726 (Massachusetts Supreme Judicial Court, 1953)
Massachusetts Gas & Electric Light Supply Co. v. Rugo Construction Co.
71 N.E.2d 408 (Massachusetts Supreme Judicial Court, 1947)
Mario Pandolf Co. v. Commonwealth
21 N.E.2d 221 (Massachusetts Supreme Judicial Court, 1939)
Atlantic National Bank v. Hupp Motor Car Corp.
14 N.E.2d 167 (Massachusetts Supreme Judicial Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
195 N.E. 511, 290 Mass. 398, 1935 Mass. LEXIS 1319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barry-v-duffin-mass-1935.