Interstate Electrical Services Corp. v. Cummings Properties, LLC

825 N.E.2d 1059, 63 Mass. App. Ct. 295, 2005 Mass. App. LEXIS 381
CourtMassachusetts Appeals Court
DecidedApril 20, 2005
DocketNo. 02-P-1169
StatusPublished
Cited by3 cases

This text of 825 N.E.2d 1059 (Interstate Electrical Services Corp. v. Cummings Properties, LLC) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interstate Electrical Services Corp. v. Cummings Properties, LLC, 825 N.E.2d 1059, 63 Mass. App. Ct. 295, 2005 Mass. App. LEXIS 381 (Mass. Ct. App. 2005).

Opinion

McHugh, J.

Anderson Estates, Inc. (Anderson), and Cummings Properties, LLC (Cummings), appeal from a judgment entered in the Superior Court enforcing a mechanic’s lien, see G. L. c. 254, §§ 1 et seq., in favor of the plaintiff, Interstate Electrical Services Corporation (Interstate), and from a judge’s order denying the defendants’ motion to alter or amend that judgment or to make additional findings. We affirm.2

[296]*296The controversy arises out of electrical work Interstate performed in late 1999 and early 2000. In late summer of 1999, Aurora Graphics, Inc. (Aurora), entered into a lease of a building owned by Anderson and managed by Cummings. Shortly after beginning its tenancy, Aurora sought to increase the building’s electrical capacity. To that end, Aurora entered into two written contracts with Interstate and informed Cummings that Interstate was going to provide electrical work “in accordance with their contracts.”

The first of the two contracts, dated October 20, 1999, required Interstate to supply and install a “GE 1200 amp circuit breaker combination cabinet” and to install conduits, ground rods, and copper wire at a cost of $24,542.72. The cabinet was essentially a metal box used to enclose the circuit breaker. Both Federal and State electrical codes required a label on the outside of the cabinet and on the circuit breaker, identifying the breaker’s 1,200-ampere (amp) capacity. The contract included a note reading, “Excavation price to follow.” On November 17, 1999, Interstate applied for, and was granted, the necessary permits to perform the work the first contract required.

The second contract, dated October 27, 1999, required Interstate to (1) subcontract with an excavator to dig a trench that was necessary for the underground connection between a Boston Edison transformer and the 1,200-amp circuit breaker combination cabinet that was the subject of the October 20 contract, and (2) supply Aurora with additional electrical equipment for Aurora’s in-house electrician to install. The contract price was $19,172.70. Interstate supplied the equipment and subcontracted with the excavator at some point before December 31, 1999.3

By December 29, 1999, Interstate had completed most of the work required under both contracts. However, the label on the circuit breaker cabinet incorrectly read “800 AMP” rather than [297]*297the required 1,200 amps.4 An inspector for the city of Woburn noted the 800-amp label in the report of his final inspection of the installed system. Because of that label, he approved the electrical system to operate at only 800 amps, although the permit had been for 1,200-amp service.

Over the next four months, Interstate negotiated with General Electric and Underwriters Laboratories (UL), the cabinet maker and label supplier, respectively, regarding the required label change. Ultimately, on April 17, 2000, an Interstate employee and a UL representative went to the building to perform certain tests and switch the labels. Although the tests were performed, faulty paperwork prevented the replacement of the label at that time.

On April 18, 2000, the day after the tests, Aurora filed for bankruptcy. The label, therefore, was never corrected. On May 30, 2000, Interstate recorded two notices of contract and two statements of account in the Middlesex County registry of deeds. See G. L. c. 254, §§ 2, 8. The recordings referred to the October 20 contract and the October 27 contract. The same day, Interstate filed a verified complaint seeking enforcement of the lien pursuant to G. L. c. 254, § 5. The defendants opposed the enforcement effort on the grounds that Interstate had not filed the notices of contract and statements of account within the time the statute required; that the defendants had not consented to the work; and that Interstate’s work did not constitute an improvement to the property.5 G. L. c. 254, § 2.

Following a bench trial, a Superior Court judge concluded that the work Interstate performed in April was required under “the contract” but did not specify which contract. The judge awarded Interstate $43,715.42, the total due under both contracts, plus costs and $9,342.01 in interest.

On appeal, all parties agree that the judge implicitly found that the April work was performed under both contracts. They [298]*298disagree somewhat on the underpinnings for that finding. The defendants contend that the trial judge implicitly concluded either that Interstate’s April work was required by both contracts or that, the contracts, though written separately, were constituent parts of a single project and, thus, should be treated as one. Interstate urges simply that the judge implicitly found that the April work was necessary to complete both contracts.

Against that backdrop, the defendants make three arguments. First, they claim that any implicit finding of fact that Interstate’s April work was required by the October 27 contract was clearly erroneous. Second, they assert that, to the extent that the April work was required by the October 20 contract, performance of that work could not have extended the filing deadline for the October 27 contract as a matter of law. Finally, the defendants argue that the work required by the October 20 contract was substantially complete in December of 1999 and the work performed in April was repair or warranty work that did not extend the filing deadline for that contract.

Interstate, of course, disagrees. It begins with the judge’s finding that the contract required Interstate to provide the correct label for the electrical equipment it installed. According to Interstate, the judge’s decision reflects an implicit determination that both contracts required a proper label because he explicitly found that the contracts had a single purpose, i.e., the provision of labor and materials for electrical improvements to Aurora’s leased premises. Finally, Interstate contends that the judge was correct in finding that the April work was necessary to complete the contract work, and was not simply repair or warranty work, because installation of an accurate label was required under State law before the system could operate at the contractually required amperage level.

In resolving those competing claims, we must “not reverse [the judgment below] ‘unless the facts on which the conclusion was based are clearly erroneous’ or unless ‘the findings or conclusions are tainted by an error of law.’” Davidson Pipe Supply Co. v. Johnson, 14 Mass. App. Ct. 518, 525 (1982), quoting from New England Canteen Serv., Inc. v. Ashley, 372 Mass. 671, 674 (1977).

Under the Massachusetts mechanic’s lien statute, a person [299]*299who has entered into a written contract with the “owner of any interest in real property, or. . . with the consent of such owner,” G. L. c. 254, § 2, inserted by St. 1996, c. 364, § 2, “for improvements to that property, or for the furnishing of equipment, appliances, or tools for such improvements, ‘shall have a hen upon such real property ... to secure the payment of all labor, . . . services, and material. . . which shall be furnished by virtue of said contract.’ ” Tremont Tower Condominium, LLC v. George B.H. Macomber Co., 436 Mass. 677, 679-680 (2002), quoting from G. L. c. 254, § 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Madigan v. Trace Construction, Inc.
878 N.E.2d 568 (Massachusetts Appeals Court, 2007)
Quinn Bros. of Essex, Inc. v. R.L. Jeannotte, Inc.
2007 Mass. App. Div. 198 (Mass. Dist. Ct., App. Div., 2007)
Butler Contracting, Inc. v. Court Street, LLC
631 S.E.2d 252 (Supreme Court of South Carolina, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
825 N.E.2d 1059, 63 Mass. App. Ct. 295, 2005 Mass. App. LEXIS 381, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interstate-electrical-services-corp-v-cummings-properties-llc-massappct-2005.