Tremont Tower Condominium, LLC v. George B.H. Macomber Co.

767 N.E.2d 20, 436 Mass. 677, 2002 Mass. LEXIS 281
CourtMassachusetts Supreme Judicial Court
DecidedMay 3, 2002
StatusPublished
Cited by20 cases

This text of 767 N.E.2d 20 (Tremont Tower Condominium, LLC v. George B.H. Macomber Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tremont Tower Condominium, LLC v. George B.H. Macomber Co., 767 N.E.2d 20, 436 Mass. 677, 2002 Mass. LEXIS 281 (Mass. 2002).

Opinion

Sosman, J.

The defendant, George B.H. Macomber Company (Macomber), appeals from a judgment discharging a mechanic’s lien and a notice of contract recorded on certain real property owned by the plaintiff, Tremont Tower Condominium, LLC (Tremont Tower). See G. L. c. 254, § 15A. We granted Mac-omber’s application for direct appellate review. On March 14, 2002, we issued an order reversing the judgment of the Superior Court and remanding the case for further proceedings. This opinion explains the basis for our conclusion that the voluntary dissolution of a mechanic’s hen under G. L. c. 254, § 10, does [678]*678not prevent a contractor’s later recording of another timely notice of contract.

1. Background. The essential facts are not in dispute. In a contract dated December 2, 1999, Tremont Tower, owner of a development project in downtown Boston, engaged Macomber as the general contractor for the construction of a condominium building. On February 15, 2000, Macomber recorded a notice of this contract in the Suffolk County registry of deeds, thereby establishing a mechanic’s lien on the Tremont Tower property to secure payment for labor and materials. G. L. c. 254, § 2. According to the president and chief executive officer of Mac-omber, Tremont Tower thereafter advised that the project lenders would not fund applications for loan advances because Mac-omber had established a lien on the property, and asked that Macomber withdraw the notice of contract. On March 3, 2000, Macomber dissolved the lien by recording a notice of dissolution in the registry of deeds. G. L. c. 254, § 10.

Construction on the project moved forward without dispute for approximately one year. At the insistence of Tremont Tower and its lenders, Macomber executed a partial waiver and subordination of lien each month, in accordance with G. L. c. 254, § 32, as a condition of payment. In the spring of 2001, however, a dispute arose between Tremont Tower and Mac-omber, with Macomber claiming over $3 million in past due payments. On April 23, 2001, Macomber recorded a second notice of contract. Macomber alleges that Tremont Tower again advised that the lenders would not fund amounts due under Ma-comber’s applications for payment because of the filing of another notice of contract.

On May 2, 2001, Tremont Tower applied to the Superior Court for a discharge of Macomber’s notice of contract, arguing that Macomber could not again claim a méchame’s lien on the property when it had previously filed a notice dissolving the lien. Macomber counterclaimed and filed a claim against the lenders, seeking an order enjoining all of the parties from refusing to fund work on the development project because of the notice of contract. See G. L. c. 254, §§ 15A, 33.

A judge in the Superior Court ruled in favor of Tremont Tower, holding that the prior notice of dissolution permanently [679]*679barred Macomber from filing another notice of contract. She noted that “[t]his result is harsh, and arguably inconsistent with the purpose of the statute to provide contractors with effective security for payment for work performed,” and expressed concern that Macomber’s earlier notice of dissolution “may have resulted from conduct on the part of the owner and/or its lender that could fairly be construed as an effort to circumvent the prohibition of [G. L. c. 254,] § 32.”1 She felt constrained, however, by prior precedent from this court (which she characterized as “similarly harsh”), to interpret the notice of dissolution as a permanent dissolution, citing Mullen Lumber Co. v. Lore, 404 Mass. 750, 756-757 (1989), and Blount Bros. Corp. v. Lafayette Place Assocs., 399 Mass. 632, 636-639 (1987).

2. Discussion. Mechanic’s liens are created and governed purely by statute. See G. L. c. 254. “The primary purpose of the lien is to provide security to contractors, subcontractors, laborers, and suppliers for the value of their services and goods provided for improving the owner’s real estate. ... At the same time, the statute contains fifing and notice requirements to protect the owner and others with an interest in the property.” (Citations omitted.) Hammill-McCormick Assocs., Inc. v. New England Tel. & Tel. Co., 399 Mass. 541, 542-543 (1987). We look then to the statutory provisions concerning the creation, perfection, and enforcement of a lien to determine whether Ma-comber has met the statutory prerequisites for a valid and enforceable lien.

A person who has entered into a written contract with an owner of real property for improvements to that property, or for the furnishing of equipment, appliances, or tools for such improvements, “shall have a lien upon such real property . . . to secure the payment of all labor, including construction management and general contractor services, and material or rental equipment, appliances, or tools which shall be furnished [680]*680by virtue of said contract.” G. L. c. 254, § 2. In order to claim such a hen, the contractor must record a “notice of contract” in the registry of deeds for the county in which the property is located. Id. The statute sets a deadhne for the recording of such a notice of contract, and calculates that deadhne according to the way that the contract is either terminated or completed. If the parties to the contract have filed a notice of substantial completion (signifying the parties’ agreement that the “work under the written contract is sufficiently complete so that it can be occupied or utilized for its intended use,” G. L. c. 254, § 2A), the contractor must file the notice of contract no later than sixty days after the filing of the notice of substantial completion. G. L. c. 254, § 2. If the contract has been terminated and the owner has filed a notice of termination (see G. L. c. 254, § 2B), the contractor must file the notice of contract no later than ninety days after the fifing of the notice of termination. G. L. c. 254, § 2. Or, in the absence of any such notice of substantial completion or notice of termination, the deadline for fifing a notice of contract is ninety days after the contractor “last performed or furnished labor or materials or both labor and materials.” Id. A notice of contract may be recorded “at any time after execution of the written contract,” as long as it is recorded before the applicable deadline. Id.

The recording of the notice of contract establishes the priority of the mechanic’s lien. As a general matter, the lien takes priority over all other later-recorded encumbrances on the property.2 Thus, once filed, the notice of contract sets the date for the lien’s priority.

The enforcement of the lien requires further steps, which must also be performed within time frames established by the statute. The contractor must record a statement of account, setting forth the amount due or to become due. G. L. c. 254, § 8. That statement of account must be filed within ninety days of the fifing of a notice of substantial completion; within 120 days of the fifing of a notice of termination; or within 120 days after the contractor last performed or furnished labor, materials, [681]*681equipment, appliances, or tools for the project, whichever is earliest. Id. Failure to file a statement of account within these time frames results in the lien’s being “dissolved.” Id. After filing the statement of account, the contractor has a brief period of time in which to enforce the lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City Electric Supply Co. v. Arch Insurance Co.
119 N.E.3d 735 (Massachusetts Supreme Judicial Court, 2019)
Midwest Constr. Servs., Inc. v. Avalonbay Cmtys., Inc.
104 N.E.3d 682 (Massachusetts Appeals Court, 2018)
NES Rentals v. Maine Drilling & Blasting, Inc.
992 N.E.2d 291 (Massachusetts Supreme Judicial Court, 2013)
Botany Bay Construction Co. v. Pullman Modular Industries, Inc.
29 Mass. L. Rptr. 398 (Massachusetts Superior Court, 2011)
General Mechanical Contractors, Inc. v. C.E. Floyd Co.
27 Mass. L. Rptr. 290 (Massachusetts Superior Court, 2010)
Maverick Construction Management Services, Inc. v. Evergrass, Inc.
27 Mass. L. Rptr. 41 (Massachusetts Superior Court, 2010)
In Re Globe Manufacturing Corp.
567 F.3d 1291 (Eleventh Circuit, 2009)
Carrier Corp. v. Buckley
567 F.3d 1291 (Eleventh Circuit, 2009)
Madigan v. Trace Construction, Inc.
878 N.E.2d 568 (Massachusetts Appeals Court, 2007)
Quinn Bros. of Essex, Inc. v. R.L. Jeannotte, Inc.
2007 Mass. App. Div. 198 (Mass. Dist. Ct., App. Div., 2007)
W.C. Smith & Son, Inc. v. Brooks/Maxi Drug, Inc.
22 Mass. L. Rptr. 140 (Massachusetts Superior Court, 2007)
Mammoet Usa, Inc. v. Entergy Nuclear Generation Co.
831 N.E.2d 349 (Massachusetts Appeals Court, 2005)
Interstate Electrical Services Corp. v. Cummings Properties, LLC
825 N.E.2d 1059 (Massachusetts Appeals Court, 2005)
Golden v. General Builders Supply LLC
807 N.E.2d 822 (Massachusetts Supreme Judicial Court, 2004)
Rosano-Davis, Inc. v. Sastre
2004 Mass. App. Div. 55 (Mass. Dist. Ct., App. Div., 2004)
National Lumber Co. v. United Casualty & Surety Insurance
802 N.E.2d 82 (Massachusetts Supreme Judicial Court, 2004)
Bloomsouth Flooring Corp. v. Boys' & Girls' Club of Taunton Inc.
800 N.E.2d 1038 (Massachusetts Supreme Judicial Court, 2003)
Davenport Mammoet Heavy Transport, Inc. v. Entergy Nuclear Generation Co.
16 Mass. L. Rptr. 133 (Massachusetts Superior Court, 2003)
Burkhard Hotel Partners, LLC v. A. Giacalone Construction Corp.
15 Mass. L. Rptr. 634 (Massachusetts Superior Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
767 N.E.2d 20, 436 Mass. 677, 2002 Mass. LEXIS 281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tremont-tower-condominium-llc-v-george-bh-macomber-co-mass-2002.