W.C. Smith & Son, Inc. v. Brooks/Maxi Drug, Inc.

22 Mass. L. Rptr. 140
CourtMassachusetts Superior Court
DecidedFebruary 2, 2007
DocketNo. 04195
StatusPublished

This text of 22 Mass. L. Rptr. 140 (W.C. Smith & Son, Inc. v. Brooks/Maxi Drug, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.C. Smith & Son, Inc. v. Brooks/Maxi Drug, Inc., 22 Mass. L. Rptr. 140 (Mass. Ct. App. 2007).

Opinion

MacDonald, D. Lloyd, J.

Before the Court is the defendants’ motion for summary judgment. It is ALLOWED for the reasons that follow.

Pertinent Facts

The case arises from the construction of a Brooks brand pharmacy in New Bedford. The defendant Brooks/Maxi Drug, Inc. (“Brooks”) entered into a contract (“the general contract”) with C.P.C. ‘76, Inc. (“C.P.C.”) to build the store. Brooks leased the premises from the defendant P.J.C. Realty Co., Inc. (“P.J.C. Realty") but executed the general contract as the “owner.” P.J.C. Realty was not a signatory to the contract. The building was constructed between August 2000 and March 2001.

On or about September 20, 2000, C.P.C., as general contractor, entered into a subcontract (“the subcontract”) with the plaintiff W.C. Smith & Son, Inc. (“Smith”) to do construction site work. C.P.C. is not a party to this action. The subcontract between C.P.C. and Smith identified Brooks as the “owner” of the store. Neither Brooks nor P.J.C. Realty were signatories on the subcontract. The subcontract provided that C.P.C. would pay Smith $273,850.00 for its work.

In June 2001 Smith filed a “Notice of Contract” in the Bristol County Registry of Deeds pursuant to the mechanics lien statute, G.L.c. 254, §4. The notice recited the contract with C.P.C. and the identity of Brooks and P.J.C. Realty as “owner.” It also noted the contract price, the amount of change orders and payments received to date.

Eventually Smith billed C.P.C. $252,850.00 for work it performed under their subcontract and an additional $30,833.49 for add-ons. C.P.C. received $218,277.00 in payment from Brooks on Smith’s requisitions for payment. C.P.C. in turn remitted that amount to Smith. At present there is an outstanding combined balance on the subcontract between Smith and C.P.C. and related add-ons of $61,202.49. That is the amount at issue in the case.

In March 2003 Smith filed an arbitration claim against C.P.C. in connection for the unpaid invoices. Smith alleges that Brooks was provided with a copy of the claim. The arbitration did not resolve the dispute, and in December 2003, C.P.C. filed a voluntary petition in bankruptcy. It appears that the bankruptcy filing put an end to Smith’s effort to get payment from C.P.C.

In February 2004, W.C. Smith filed this lawsuit against P.J.C. Realty and Brooks to recover the above amounts due from C.P.C. The complaint sounds in contract and quasi-contract. The defendants move for summary judgment on the basis that Smith’s recourse for amounts due pursuant to its subcontract is exclusively against C.P.C. inasmuch as there was no privity between Smith and them. Further, the defendants allege that Smith failed to comply with the requisites of G.L.c. 254 to create a mechanic’s lien that otherwise would have enabled Smith to proceed against them. In its complaint Smith made no claim or reference to a mechanic’s lien. However, in Smith’s opposition to the defendants’ summary judgment motion, Smith submits that it is entitled to the benefit of G.L.c. 254, §31’s special provisions for a subcontractor’s mechanic’s lien where its general contractor has filed for bankruptcy.

DISCUSSION

I. Standard of Review

Summary judgment is appropriate where there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Mass.R.Civ.P. 56(c); Casseso v. Commissioner of Corrections, 390 Mass. 419, 422 (1983); Community Nat’l Bank v. Dawes, 369 Mass. 550, 553 (1976). The moving party bears the burden of affirmatively demonstrating the absence of a triable issue. Pederson v. Time, Inc., 404 Mass. 14, 16-17 (1989). If the moving party does not bear the burden of proof at trial, it must either: 1) submit affirmative evidence negating an essential element of the non-moving party’s claim; or 2) demonstrate that the non-moving party’s evidence is insufficient to establish its claim. Kourovacilis v. General Motors Corp., 410 Mass. 706, 711 (1991). The non-moving party may not defeat the motion for summary judgment by resting merely on the allegations and denials in its pleadings, but must set forth specific facts with affidavits, deposition testimony, answers to interrogatories, or admissions on file showing that there is a genuine issue for trial. Mass.R.Civ.P. 56(e). “If the moving party establishes the absence of a triable issue, the party opposing the motion must respond and allege specific facts establishing the existence of a material fact in order to defeat the motion.” Pederson, 404 Mass. at 17. The court will interpret all inferences in the light most favorable to the non-mov[142]*142ing party. Blare v. Husky Injection Molding Sys. Boston, Inc., 419 Mass. 437, 438 (1995). Conclusoiy statements or argumentative assertions will not suffice. Key Capital Corp. v. M&S Liquidating Corp., 27 Mass.App.Ct. 721, 727-28 (finding insufficient “bare assertions and conclusions regarding the [party’s] understandings, beliefs and assumptions”).

II. The Contract and Quasi-Contract Claims

Smith has an insurmountable problem at the threshold with regard to its contract-based claims: “In the absence of a lien perfected under G.L.c. 254, an owner who enters into a general contract for improvements on real property is not ordinarily liable to subcontractors whose sole contractual arrangements are with the general contractor.” Brick Constr. Corp v. CEI Dev. Corp., 46 Mass.App.Ct. 837, 840 (1999); Evans v. Multicon Constr. Corp., 30 Mass.App.Ct. 728, 740 (1991).

The phrase, “not ordinarily liable,” as used in Evans and Brick, supra, has not been further defined other than by the Evans court’s illustrative hypothetical which posited a situation where “the owner agreed to pay to subcontractors all claims in connection with the owner’s job against the contractor which were reduced to judgment.” Evans, 30 Mass.App. at 740.

In a recent case the District Court Appellate Division, however, addressed a subcontractor’s quasi-contract and quantum meruit claim that was substantially similar to Smith’s. The court aptly rejected an expansive reading of the qualifying phrase in the Evans court’s opinion in the following terms:

Allowing a subcontractor to recover damages in a quasi-contract action against a property owner with whom that subcontractor was not in contractual privity would in essence eliminate the reason the long-lived mechanic’s-lien statute exists, and would render its strictly-construed provisions superfluous in their entirety. .The statute exists to provide security to subcontractors and others for the value of their goods and services provided to improve the owner’s real property, and it affords the protections it does likely because of the long-standing bar preventing a subcontractor’s recovery against a landowner when the general contractor fails to pay the subcontractor.

Rosano-Davis Inc. v. Sastre, 2004 Mass.App.Div. 55 (2004) (citing, inter alia, Tremont Tower Condo., LLC v. George B. H. Macomber Co., 436 Mass. 677, 679 (2002)).

There is no basis in the summary judgment record that would justify an exception to the general rule that an owner is not liable to subcontractors with whom the owner did not contract. Thus, Smith’s entitlement to relief is dependent upon its being able to demonstrate the existence of an enforceable mechanic’s lien.

III. W.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hammill-McCormick Associates, Inc. v. New England Telephone & Telegraph Co.
505 N.E.2d 883 (Massachusetts Supreme Judicial Court, 1987)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Key Capital Corp. v. M&S LIQUIDATING CORP.
542 N.E.2d 603 (Massachusetts Appeals Court, 1989)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Mullen Lumber Co. v. Lore
537 N.E.2d 123 (Massachusetts Supreme Judicial Court, 1989)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
Evans v. Multicon Construction Corp.
574 N.E.2d 395 (Massachusetts Appeals Court, 1991)
Whitford v. Newell
84 Mass. 424 (Massachusetts Supreme Judicial Court, 1861)
Forbes v. Mosquito Fleet Yacht Club
56 N.E. 615 (Massachusetts Supreme Judicial Court, 1900)
Webber Lumber & Supply Co. v. Erickson
102 N.E. 940 (Massachusetts Supreme Judicial Court, 1913)
Registrar of Motor Vehicles v. Board of Appeal on Motor Vehicle Liability Policies & Bonds
416 N.E.2d 1373 (Massachusetts Supreme Judicial Court, 1981)
Blare v. Husky Injection Molding Systems Boston, Inc.
646 N.E.2d 111 (Massachusetts Supreme Judicial Court, 1995)
National Lumber Co. v. LeFrancois Construction Corp.
723 N.E.2d 10 (Massachusetts Supreme Judicial Court, 2000)
Ng Bros. Construction, Inc. v. Cranney
766 N.E.2d 864 (Massachusetts Supreme Judicial Court, 2002)
Tremont Tower Condominium, LLC v. George B.H. Macomber Co.
767 N.E.2d 20 (Massachusetts Supreme Judicial Court, 2002)
National Lumber Co. v. United Casualty & Surety Insurance
802 N.E.2d 82 (Massachusetts Supreme Judicial Court, 2004)
Golden v. General Builders Supply LLC
807 N.E.2d 822 (Massachusetts Supreme Judicial Court, 2004)
Sullivan v. Liberty Mutual Insurance
825 N.E.2d 522 (Massachusetts Supreme Judicial Court, 2005)
Brick Construction Corp. v. CEI Development Corp.
710 N.E.2d 1006 (Massachusetts Appeals Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
22 Mass. L. Rptr. 140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wc-smith-son-inc-v-brooksmaxi-drug-inc-masssuperct-2007.