Hammill-McCormick Associates, Inc. v. New England Telephone & Telegraph Co.

505 N.E.2d 883, 399 Mass. 541, 1987 Mass. LEXIS 1214
CourtMassachusetts Supreme Judicial Court
DecidedApril 6, 1987
StatusPublished
Cited by35 cases

This text of 505 N.E.2d 883 (Hammill-McCormick Associates, Inc. v. New England Telephone & Telegraph Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hammill-McCormick Associates, Inc. v. New England Telephone & Telegraph Co., 505 N.E.2d 883, 399 Mass. 541, 1987 Mass. LEXIS 1214 (Mass. 1987).

Opinion

Hennessey, C.J.

In this case a judge of the Superior Court ordered partial summary judgment to be entered in favor of a subcontractor against the owner of a building for which the subcontractor had supplied labor and materials. The judge then reported the following question: “Whether a subcontractor who furnishes labor or material or both under a written contract with a contractor wherein a completion date for that contract is set out, establishes a subcontractor’s lien in compliance with M.G.L. c. 254, § 4 by filing a notice of contract in the appropriate registry of deeds after the required work is performed but prior to the completion date stated in the contract. The Court has determined that in all other respects, the plaintiff has com *542 plied with the mechanics lien statute.” We answer the reported question in the affirmative.

The defendant, New England Telephone and Telegraph Company, Inc. (owner), entered into a general contract with A.L. Phelps, Inc. (general contractor), on September 8, 1982, for the repair and maintenance of the owner’s Dial Exchange Building in East Longmeadow. On October 29, 1982, the general contractor entered into a subcontract with the plaintiff, Hammill-McCormick Associates, Inc. (subcontractor), for the performance of work and the supply of materials in connection with the general contract. The subcontract provided that all work must be completed by April 23, 1983. The subcontractor filed a notice of contract in the Hampden County registry of deeds on April 22, 1983, and actual notice dated April 22, 1983, was received by the owner on April 27, 1983. 1 The notice of contract was filed after the subcontractor’s work had been performed, but before the date set for the completion of the contract. On May 2, 1983, the owner made a payment to the general contractor in the amount of $60,991.

On July 15, 1983, the subcontractor commenced this suit naming both the general contractor and the owner as defendants. The subcontractor moved for summary judgment against the owner on the lien. The judge entered partial summary judgment for the subcontractor, finding that the lien had been established in compliance with G. L. c. 254, § 4 (1984 ed.), in the amount of $26,345, plus interest. The owner appealed from the entry of partial judgment, and the judge reported the question set forth above. This court took the case on its own motion.

General Laws c. 254 provides that a debt due to a person who performs labor or supplies material for the improvement of real estate by agreement or with the express or implied consent of the owner is secured by a mechanic’s lien. The primary purpose of the lien is to provide security to contractors, subcontractors, laborers, and suppliers for the value of their *543 services and goods provided for improving the owner’s real estate. See Mitchell v. Packard, 168 Mass. 467, 469 (1897). At the same time, the statute contains filing and notice requirements to protect the owner and others with an interest in the property. See Pratt & Forrest Co. v. Strand Realty Co., 233 Mass. 314, 317-318 (1919); Rheem Mfg. Co. v. Monsanto Co., 6 Mass. App. Ct. 461, 465 (1978). A subcontractor with a written contract may perfect the lien by filing a notice of the contract as specified by G. L. c. 254, § 4. 2 The lien is a *544 creature of the statute, and can be enforced only by strict compliance with the statute. See Valentine Lumber & Supply Co. v. Thibeault, 336 Mass. 411, 413 (1957); Street Lumber Co. v. Sullivan, 201 Mass. 484, 485 (1909).

The issue in this case is when must a subcontractor file notice of the contract, and give actual notice, to secure his claim. The subcontractor contends that the time limit is the completion date stated in its contract with the general contractor. The owner contends that filing and notice must occur before the subcontractor actually completes performance.

The statute does not explicitly state a deadline for filing. Language in the statute describing the completion date specified in the notice is prospective: “Said contract is to be completed on or before . . .” (emphasis added). G. L. c. 254, §§ 2, 4. “For the purposes of this chapter the date of completion stated in the notice of contract filed . . . shall be the date on which the contract is to be performed” (emphasis added). G. L. c. 254, § 4.

The defendant relies on the Rheem case, but we think that case does not support the defendant’s position. In that case, the general contractor in July, 1974, entered into a contract with the owner to construct a building on the owner’s land. The general contractor engaged a subcontractor to do heating and air conditioning work, and the subcontractor in turn ordered seven air cqnditioner units from the Rheem Company, apparently without a written contract specifying a completion date. Rheem delivered the units to the job site shortly before January 1, 1975. Rheem submitted a bill to the subcontractor about that time, which the subcontractor never paid. On November 14, 1975, Rheem filed a notice of contract, which recited that Rheem had completed its performance of the contract on October 6, 1975. On November 26,1975, Rheem filed a statement *545 of account setting forth the payments it was due. In early January, 1976, at the request of the general contractor, Rheem reversed some panels on one of the units to prevent snow from blowing into the building. On January 6, 1976, Rheem filed a second notice of contract which stated that it had completed the contract on December 14, 1975, and filed a second statement of account.

The Appeals Court concluded that Rheem had not timely filed its notice of contract, and that, therefore, it had not secured the payment it was due with a lien on the property of the owner. Language in the Appeals Court’s opinion suggests that the subcontractor must file a notice of contract prior to actually completing performance, and the owner in this case argues that Rheem should control. We disagree. Rheem involved substantially different facts from this case. Rheem had no contractually specified completion date. Although Rheem completed actual performance by January 1, 1975, it did not file a notice of contract until November 14,1975. Moreover, Rheem recited in that notice that the completion date was October 6, 1975. Even accepting Rheem’s recital of the completion date, Rheem filed notice of contract after both dates in question.

In this case, the subcontractor had a written contract with a specified completion date, and filed notice before that date. We conclude that a subcontractor who files before the completion date stated in its contract has timely filed its notice of contract under G. L. c. 254, § 4. The statute indicates that the date of completion to be specified in the notice of contract is that date specified in the written contract itself.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruno v. Alliance Rental Group, LLC
Massachusetts Appeals Court, 2023
City Electric Supply Co. v. Arch Insurance Co.
119 N.E.3d 735 (Massachusetts Supreme Judicial Court, 2019)
Aa & D Masonry, LLC v. S. St. Bus. Park, LLC
107 N.E.3d 1229 (Massachusetts Appeals Court, 2018)
Midwest Constr. Servs., Inc. v. Avalonbay Cmtys., Inc.
104 N.E.3d 682 (Massachusetts Appeals Court, 2018)
D5 Iron Works, Inc. v. Danvers Fish & Game Club, Inc.
102 N.E.3d 427 (Massachusetts Appeals Court, 2018)
Groleau v. Russo-Gabriele
32 Mass. L. Rptr. 513 (Massachusetts Superior Court, 2014)
NES Rentals v. Maine Drilling & Blasting, Inc.
992 N.E.2d 291 (Massachusetts Supreme Judicial Court, 2013)
McAnarney v. Clinton Millworks, LLC
30 Mass. L. Rptr. 236 (Massachusetts Superior Court, 2012)
Botany Bay Construction Co. v. Pullman Modular Industries, Inc.
29 Mass. L. Rptr. 398 (Massachusetts Superior Court, 2011)
Avanti Systems, USA, Inc. v. Plattypus, LLC
28 Mass. L. Rptr. 134 (Massachusetts Superior Court, 2010)
National Lumber Co. v. Inman
933 N.E.2d 675 (Massachusetts Appeals Court, 2010)
General Mechanical Contractors, Inc. v. C.E. Floyd Co.
27 Mass. L. Rptr. 290 (Massachusetts Superior Court, 2010)
Maverick Construction Management Services, Inc. v. Evergrass, Inc.
27 Mass. L. Rptr. 41 (Massachusetts Superior Court, 2010)
McNally v. Dominion Energy Salem Harbor, LLC
27 Mass. L. Rptr. 164 (Massachusetts Superior Court, 2010)
Nitro Dynamics, Inc. v. Petruzzi Bros.
24 Mass. L. Rptr. 493 (Massachusetts Superior Court, 2008)
Madigan v. Trace Construction, Inc.
878 N.E.2d 568 (Massachusetts Appeals Court, 2007)
John Marini Management Co. v. Butler
873 N.E.2d 1150 (Massachusetts Appeals Court, 2007)
W.C. Smith & Son, Inc. v. Brooks/Maxi Drug, Inc.
22 Mass. L. Rptr. 140 (Massachusetts Superior Court, 2007)
National Lumber Co. v. Lombardi
834 N.E.2d 267 (Massachusetts Appeals Court, 2005)
Mammoet Usa, Inc. v. Entergy Nuclear Generation Co.
831 N.E.2d 349 (Massachusetts Appeals Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
505 N.E.2d 883, 399 Mass. 541, 1987 Mass. LEXIS 1214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hammill-mccormick-associates-inc-v-new-england-telephone-telegraph-co-mass-1987.