NES Rentals v. Maine Drilling & Blasting, Inc.

992 N.E.2d 291, 465 Mass. 856, 2013 WL 3481869, 2013 Mass. LEXIS 580
CourtMassachusetts Supreme Judicial Court
DecidedJuly 15, 2013
StatusPublished
Cited by10 cases

This text of 992 N.E.2d 291 (NES Rentals v. Maine Drilling & Blasting, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NES Rentals v. Maine Drilling & Blasting, Inc., 992 N.E.2d 291, 465 Mass. 856, 2013 WL 3481869, 2013 Mass. LEXIS 580 (Mass. 2013).

Opinions

Duefly, J.

We address in this appeal whether a subcontractor’s amendment of its original complaint to enforce a mechanic’s lien constituted timely commencement of its action to enforce a bond pursuant to G. L. c. 254, § 14, as amended through St. 2002, c. 400, § 2 (§ 14), which sets forth procedures for execution and enforcement of bonds to dissolve mechanic’s liens. The plaintiff, NES Rentals, Inc. (NES Rentals), filed an action [857]*857in the Superior Court to enforce a mechanic’s lien recorded pursuant to G. L. c. 254, § 4, as amended through St. 1996, c. 364, § 5 (§ 4), on land owned by Berkshire Wind and Power Cooperative Corporation (Berkshire Wind). More than a year later, Maine Drilling and Blasting, Inc. (Maine Drilling), acting as principal debtor, and the surety, Berkley Regional Insurance Company (Berkley), executed and recorded a surety bond to dissolve the lien pursuant to § 14. The bond named NES Rentals as an obligee. Within ninety days of receiving notice of the bond, NES Rentals served on Maine Drilling and Berkley a motion to amend its original complaint, seeking to include them as defendants in its underlying complaint and to add a claim to enforce the bond against them.2

After NES Rentals filed the amended complaint with leave of court, a judge in the Superior Court denied Maine Drilling’s motion to dismiss the amended complaint, explaining that although NES Rentals had not filed the amended complaint within ninety days of receipt of notice of the bond, service of the motion on the defendants within that ninety-day period provided the defendants with actual notice of the action to enforce the bond, and satisfied the § 14 requirement that a claimant have “commenced” a civil action within that period in order to enforce the bond. The defendants sought leave to appeal, which was allowed, and we transferred the case to this court on our own motion.

We affirm the order denying the defendant’s motion to dismiss, but for reasons different from those relied on by the judge. We conclude that the term “commenced” as used in § 14 contemplates the filing of an action in court in accordance with Mass. R. Civ. P. 3, as amended, 385 Mass. 1215 (1982), and that the commencement requirement in § 14 is satisfied on the facts of this case because the amendment to the complaint relates back to the date on which NES Rentals filed its original action against Berkshire Wind under Mass. R. Civ. P. 15 (c), 365 Mass. 761 (1974) (rule 15 [c]).

1. Background and prior proceedings. NES Rentals alleges that McManus Excavating, Inc., contracted with it to rent equipment for construction use on property owned by Berkshire Wind. [858]*858On April 26, 2010, NES Rentals perfected a mechanic’s lien on the Berkshire Wind property by recording a notice of its contract with McManus, as required by § 4,3 and a sworn statement of account that claimed $89,101 as the amount due for the rental equipment, as required by G. L. c. 254, § 8, as amended by St. 1996, c. 364, § 9 (§ 8).4 On May 25, 2010, NES Rentals filed and recorded its complaint against Berkshire Wind in the Superior Court, seeking to enforce the lien. See G. L. c. 254, § 5, as amended by St. 1996, c. 364, § 9 (§ 5) (setting forth procedures for enforcement of mechanic’s lien by civil action).

On April 29, 2011, Maine Drilling5 and Berkley recorded a bond in the penal sum of $89,101, thereby dissolving the lien pursuant to § 14.6 NES Rentals received notice of recording [859]*859of the bond on June 13, 2011, and on August 23, 2011, NES Rentals served on Maine Drilling and Berkley a motion for leave to amend its complaint against Berkshire Wind by adding them as defendants, and asserting against Maine Drilling and Berkley a new claim to enforce the bond. On October 3, 2011, NES Rentals filed its motion to amend with the Superior Court, and Berkshire Wind filed a cross motion to dismiss the lien enforcement action.

On November 2, 2011, a judge of the Superior Court allowed both the motion of NES Rentals to amend the complaint and Berkshire Wind’s cross motion to dismiss the underlying complaint against it; NES Rentals then filed its amended complaint with the court. Thereafter, Maine Drilling filed a motion to dismiss the amended complaint on the ground that it was not timely filed in accordance with the terms of § 14, because the amended complaint, which constituted the action to enforce the bond, was not filed within ninety days after NES Rentals received notice of recording of the bond, that is, by September 11, 2011.

The judge denied Maine Drilling’s motion to dismiss the amended complaint. He explained that “even though the amended complaint was actually not ‘filed’ within the 90 day period, the defendants had actual notice of it well within that period,” where NES Rentals had served the motion to amend on Maine Drilling and Berkley within that time, and that, therefore, “the purpose of the statute, i.e., notice to the issuer of the bond within 90 days, was satisfied.”* ***7 Maine Drilling filed an application for leave to prosecute an interlocutory appeal with a single justice of the Appeals Court. That motion was allowed, and we subsequently transferred the case to this court on our own motion.

[860]*8602. Discussion. In reviewing the denial of a motion to dismiss, we consider the matter de novo, Curtis v. Herb Chambers 1-95, Inc., 458 Mass. 674, 676 (2011), accepting as true “the factual allegations in the plaintiff[’s] complaint, as well as any favorable inferences reasonably drawn from them.” Ginther v. Commissioner of Ins., 427 Mass. 319, 322 (1998), citing Nader v. Citron, 372 Mass. 96, 98 (1977), abrogated on other grounds, Iannacchino v. Ford Motor Co., 451 Mass. 623, 635 (2008).

In this case we consider whether amendment of a complaint, originally brought as an action to enforce a lien, by adding a claim to enforce a lien dissolution bond constitutes timely commencement of an action to enforce the bond within the meaning of § 14. We begin our discussion of the applicable provisions of G. L. c. 254 (mechanic’s lien statute) with the observation that it is the primary purpose of the mechanic’s lien statute “to provide security to contractors, subcontractors, laborers, and suppliers for the value of their services and goods provided for improving the owner’s real estate” through perfection of a mechanic’s lien on the owner’s real estate. Hammill-McCormick Assocs., Inc. v. New England Tel. & Tel. Co., 399 Mass. 541, 542-543 (1987), citing Mitchell v. Packard, 168 Mass. 467, 469 (1897).

“At the same time, the statute contains filing and notice requirements to protect the owner and others with an interest in the property.” Id. at 543, and cases cited. The mechanic’s lien statute is “designed to ensure that a person searching the land records in a registry of deeds can determine with certainty whether or not title to a particular parcel of land is encumbered by a mechanic’s lien.” National Lumber Co. v. LeFrancois Constr. Corp., 430 Mass. 663, 668 (2000) (.National Lumber I), citing Pratt & Forrest Co. v. Strand Realty Co., 233 Mass. 314, 317-318 (1919).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruno v. Alliance Rental Group, LLC
Massachusetts Appeals Court, 2023
City Electric Supply Co. v. Arch Insurance Co.
119 N.E.3d 735 (Massachusetts Supreme Judicial Court, 2019)
Roby v. Superintendent
113 N.E.3d 898 (Massachusetts Appeals Court, 2018)
Fid. & Deposit Co. of Md. v. Beyond Constr., Inc.
111 N.E.3d 305 (Massachusetts Appeals Court, 2018)
M.M. v. J.M.
103 N.E.3d 1240 (Massachusetts Appeals Court, 2018)
Bence v. Hunt
103 N.E.3d 765 (Massachusetts Appeals Court, 2018)
The Gillette Co. v. Provost
Massachusetts Appeals Court, 2017
Aggregate Industries - Northeast Region, Inc. v. Hugo Key and Sons, Inc.
57 N.E.3d 1027 (Massachusetts Appeals Court, 2016)
Clean Properties, Inc. v. Riselli
32 Mass. L. Rptr. 234 (Massachusetts Superior Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
992 N.E.2d 291, 465 Mass. 856, 2013 WL 3481869, 2013 Mass. LEXIS 580, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nes-rentals-v-maine-drilling-blasting-inc-mass-2013.