Bruno v. Alliance Rental Group, LLC

CourtMassachusetts Appeals Court
DecidedAugust 29, 2023
DocketAC 21-P-985
StatusPublished

This text of Bruno v. Alliance Rental Group, LLC (Bruno v. Alliance Rental Group, LLC) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bruno v. Alliance Rental Group, LLC, (Mass. Ct. App. 2023).

Opinion

NOTICE: All slip opinions and orders are subject to formal revision and are superseded by the advance sheets and bound volumes of the Official Reports. If you find a typographical error or other formal error, please notify the Reporter of Decisions, Supreme Judicial Court, John Adams Courthouse, 1 Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557- 1030; SJCReporter@sjc.state.ma.us

21-P-985 Appeals Court

MICHAEL BRUNO & another1 vs. ALLIANCE RENTAL GROUP, LLC.

No. 21-P-985.

Middlesex. September 12, 2022. – August 29, 2023.

Present: Desmond, Sacks, & D'Angelo, JJ.

Mechanic's Lien. Statute, Construction. Consumer Protection Act, Unfair act or practice, Damages, Attorney's fees. Damages, Consumer protection case, Attorney's fees. Words, "Improvement of real property," "To become due."

Civil action commenced in the Superior Court Department on May 23, 2019.

The case was heard by Douglas H. Wilkins, J.

David H. Travers (Mikaela A. Rice also present) for the defendant. Joshua M. Looney for Michael Bruno. Christian W. Habersaat for Great Midwest Insurance Company.

D'ANGELO, J. This dispute arises from the rental of heavy

machinery from a subcontractor, Alliance Rental Group, LLC

(Alliance), to a contractor, Ivester Construction Corp.

1 Great Midwest Insurance Company, as surety to the lien bonds executed by Michael Bruno. 2

(Ivester), working on property in North Reading (property) owned

by Michael Bruno. Ivester failed to pay Alliance any of the

rental fees. Alliance filed two mechanic's liens on the

property, seeking $697,479.06. See G. L. c. 254, § 4.

Following a bench trial, a Superior Court judge awarded Alliance

$180,000 for the reasonable rental value of the equipment and

awarded Bruno $100,182 for Alliance's violation of G. L. c. 93A.

In this appeal we consider, among other things, whether

G. L. c. 254, § 4, gives a judge the authority to reduce a lien

amount for periods where a subcontractor's rental equipment is

on the work site, but not being used for extended periods of

time. We conclude that it does not. Accordingly, we amend in

part and affirm in part the judgment entered in the Superior

Court.

Background. We take our facts from the findings of fact of

the trial judge and the uncontroverted facts set forth in the

exhibits.

1. The contracts. On March 27, 2013, Bruno and Ivester

entered into a subdivision contract (original contract) for

Ivester to perform subdivision improvements on the property

(project).2 In exchange, Bruno agreed to pay Ivester $300,000

2 The original contract covered work on a road in the subdivision and "Lots 1 through 11" located at 6, 8, 9, 10, 11, 12, 14, 15, 16, 17, and 19 Charles Street. 3

pursuant to a distribution schedule, and to transfer lots 6 and

7 to Ivester upon completion of the work under the original

contract. To complete the work, Ivester entered into rental

agreements with Alliance for the use of an excavator and loader.

The rental rate for each machine was $6,000 per month, plus

6.25% sales tax and any repair costs. There was no end date

specified in the rental agreements. The rental agreement for

the excavator had a "start date" of January 1, 2015, and the

start date of the rental agreement for the loader began one year

later, on January 1, 2016. The equipment was last used to

perform work under the original contract on October 4, 2018,

although the excavator remained on the property until March 18,

2019, and the loader remained on the property until May 18,

2019. From the start of the rental agreements through those

dates, Ivester did not pay any money to Alliance for the

rentals. The amount Alliance had invoiced Ivester for the

loader was $311,287.91 -- the total of $261,935 in rental

charges and $49,352.91 in repair charges. The invoice amount

for the excavator was $386,191.15 -- the total of $323,820 in

rental charges and $62,371.15 in repair charges. In total, the

invoices stated a balance of $697,479.06 owed by Ivester to

Alliance.

2. Delays in use of the equipment. There were various

periods of "down time" during the project in which construction 4

was paused and the equipment was not used, "including a one-year

period waiting for a street permit, a one-year period waiting

for an electrical permit and a period waiting for broken drains

to be fixed." Additionally, section 350-23-B of the North

Reading subdivision regulations prohibited subdivision

construction between December 1 and March 15 of each year. Both

pieces of equipment were also removed from the property in order

to complete repairs -- the excavator twice and the loader once.

Although required by the rental agreements between Ivester and

Alliance, Ivester did not maintain daily logs to track the use

of the equipment during the construction, so there was no

documentary evidence of how and when the equipment was used.

The judge determined, based on industry practice, the parties'

expectations and estimates, and the amount of down time, that

the equipment was furnished for improvements "for a total period

of one and one quarter years each," i.e., fifteen months each.

The trial judge concluded that "[g]iven the inevitability of

some degree of 'down time' on any project, it is likely that

this estimate includes short periods of inactivity during which

it would not be practical to return and re-lease the equipment."

3. Relationship between Alliance's and Ivester's

principals. Kevin Matthews was the sole manager and member of 5

Alliance. Matthews had known Kenneth Ivester,3 the owner and

principal of Ivester, for about fifteen years prior to trial.

Prior to entering into the rental agreements, Matthews had made

two personal loans to Kenneth, the first for $150,000, and the

second for $250,000. These loans were based on Matthews's

understanding that Ivester "would get two lots at the completion

of the [p]roject" and were funded using Matthews's personal home

equity line of credit.

4. Procedural history. To begin the process of

establishing mechanic's liens, Alliance recorded four notices of

contract. The first two, recorded on January 31, 2019, and

March 1, 2019, were eventually dissolved by a Superior Court

judge as untimely and incomplete, and they are not at issue in

this appeal. The subsequent two notices of contract were

recorded on March 27, 2019, regarding the excavator, and on May

3, 2019, regarding the loader, and corresponding statements of

account were recorded within the time required by G. L. c. 254,

§ 8. On May 23, 2019, Bruno brought this action against

Alliance pursuant to G. L. c. 254, § 15A, for summary discharge

of the mechanic's liens. On August 10, 2020, Bruno amended his

We hereafter refer to Kenneth by his first name to avoid 3

confusion. 6

complaint to add a count for violation of G. L. c. 93A.4

Alliance filed a counterclaim to enforce its mechanic's lien

rights. The case proceeded to a bench trial on March 16 and 17,

2021, where the judge ultimately concluded Alliance was owed a

total of $180,000 on the two liens, not the $697,479.06 that

Alliance claimed. The judge based this amount on the fair

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hammill-McCormick Associates, Inc. v. New England Telephone & Telegraph Co.
505 N.E.2d 883 (Massachusetts Supreme Judicial Court, 1987)
Freyermuth v. Lutfy
382 N.E.2d 1059 (Massachusetts Supreme Judicial Court, 1978)
PMP Associates, Inc. v. Globe Newspaper Co.
321 N.E.2d 915 (Massachusetts Supreme Judicial Court, 1975)
Commonwealth v. Brooks
319 N.E.2d 901 (Massachusetts Supreme Judicial Court, 1974)
Larkin v. CHARLESTOWN SAVINGS BANK
386 N.E.2d 790 (Massachusetts Appeals Court, 1979)
Mullen Lumber Co. v. Lore
537 N.E.2d 123 (Massachusetts Supreme Judicial Court, 1989)
Bonofiglio v. Commercial Union Insurance
591 N.E.2d 197 (Massachusetts Supreme Judicial Court, 1992)
Yorke Management v. Castro
546 N.E.2d 342 (Massachusetts Supreme Judicial Court, 1989)
Slaney v. Westwood Auto, Inc.
322 N.E.2d 768 (Massachusetts Supreme Judicial Court, 1975)
Dalli v. Board of Education
267 N.E.2d 219 (Massachusetts Supreme Judicial Court, 1971)
Allen v. Allen
16 N.E.3d 1078 (Massachusetts Appeals Court, 2014)
King v. Viscoloid Co.
106 N.E. 988 (Massachusetts Supreme Judicial Court, 1914)
Still v. Commissioner of the Department of Employment & Training
672 N.E.2d 105 (Massachusetts Supreme Judicial Court, 1996)
Bloomsouth Flooring Corp. v. Boys' & Girls' Club of Taunton Inc.
800 N.E.2d 1038 (Massachusetts Supreme Judicial Court, 2003)
Fabre v. Walton
802 N.E.2d 1030 (Massachusetts Supreme Judicial Court, 2004)
Milliken & Co. v. Duro Textiles, LLC
887 N.E.2d 244 (Massachusetts Supreme Judicial Court, 2008)
Klairmont v. Gainsboro Restaurant, Inc.
465 Mass. 165 (Massachusetts Supreme Judicial Court, 2013)
NES Rentals v. Maine Drilling & Blasting, Inc.
992 N.E.2d 291 (Massachusetts Supreme Judicial Court, 2013)
Still v. Commissioner of the Department of Employment & Training
657 N.E.2d 1288 (Massachusetts Appeals Court, 1995)
Herson v. New Boston Garden Corp.
667 N.E.2d 907 (Massachusetts Appeals Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Bruno v. Alliance Rental Group, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bruno-v-alliance-rental-group-llc-massappct-2023.