Midwest Constr. Servs., Inc. v. Avalonbay Cmtys., Inc.

104 N.E.3d 682, 93 Mass. App. Ct. 1114
CourtMassachusetts Appeals Court
DecidedJune 8, 2018
Docket17–P–435
StatusPublished

This text of 104 N.E.3d 682 (Midwest Constr. Servs., Inc. v. Avalonbay Cmtys., Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Midwest Constr. Servs., Inc. v. Avalonbay Cmtys., Inc., 104 N.E.3d 682, 93 Mass. App. Ct. 1114 (Mass. Ct. App. 2018).

Opinion

The plaintiff, Midwest Construction Services, Inc., doing business as Trillium Construction Services (Trillium), appeals from a judgment entered in the Superior Court dismissing its claims against AvalonBay Communities, Inc. (AvalonBay), and Avalon Canton, Inc. (Avalon Canton), to recover monies for work performed pursuant to a subcontract with a codefendant, Superior Mechanical Plumbing and Heating, Inc. (Superior).4 For the reasons stated below, we affirm the judgment.

Background. We summarize the undisputed facts from the summary judgment record material to the plaintiff's claims. On or about April 23, 2013, Trillium entered into an agreement with Superior to supply labor to various construction projects located in Massachusetts. One of those projects involved plumbing work for the construction of a residential apartment complex in Canton (project) owned by Avalon Canton. Avalon Canton is a wholly-owned subsidiary of AvalonBay. AvalonBay oversaw the development and managed the project for Avalon Canton.

On June 6, 2013, AvalonBay entered into a trade contract with Superior for the plumbing work at the project (trade contract). Trillium supplied the labor to Superior for the project. The terms of the trade contract provided that AvalonBay would make monthly payments to Superior upon AvalonBay's inspection of Superior's work, approval of its requisitions, and receipt of lien waivers and releases from Superior and its subcontractors and suppliers.

In connection with the trade contract, AvalonBay, Superior, and Trillium also entered into a joint check agreement (JCA), under which AvalonBay agreed that, upon receipt of Trillium's invoices, AvalonBay would issue payments to Superior in the form of joint checks payable to Superior and Trillium. The JCA provided that payments were to be made "in accordance [with the] terms and conditions of the Trade Contract between Owner [AvalonBay] and Contractor [Superior]."

From July 15, 2013, to sometime in April or May of 2014,5 Superior worked on the project with labor supplied by Trillium. Superior submitted six applications for payment to AvalonBay for work performed from July 15, 2013, to March 31, 2014. Each payment application, except for the first, contained a partial lien release certifying that all suppliers and subcontractors had provided Superior with a corresponding lien release and that Superior had paid or would pay the subcontractors with money received from AvalonBay. Trillium also provided AvalonBay with lien waivers and releases certifying that between September 13, 2013, and March 27, 2014, Superior had fully paid Trillium for all work it had performed. Those lien waivers and releases waived any and all claims against AvalonBay through March 27, 2014. Following receipt of the lien releases, AvalonBay issued electronic disbursements and joint checks payable to Superior and Trillium between August 21, 2013, and April 21, 2014.

On April 1, 2014, five days after submitting its last lien waiver and release, Trillium's vice president contacted AvalonBay representing that Superior had failed to pay many of Trillium's invoices from September 13, 2013, through March 27, 2014, and owed Trillium $204,669.80. On April 11, 2014, Trillium advised AvalonBay that due to the outstanding monies owed, it was pulling its labor from the project. On May 8, 2014, Trillium recorded a notice of contract and a statement of account in the Norfolk County Registry of Deeds relating to the unpaid labor it supplied to Superior for work on the project. On May 9, 2014, Trillium sent notice of those recordings to Avalon Canton by certified mail. Trillium claimed in its notices that Superior failed to pay it $210,572.23 out of a total of $304,976.10.6 On May 16, 2014, AvalonBay terminated the trade contract because Superior failed adequately to perform its work. AvalonBay then contracted with another plumbing contractor to complete Superior's work.7 On June 3, 2014, Trillium commenced this action. The defendants filed a motion for summary judgment and, after a hearing, the judge allowed the motion and dismissed Trillium's complaint. This appeal followed.

Discussion. We review the grant of summary judgment de novo. Miller v. Cotter, 448 Mass. 671, 676 (2007).

1. Mechanic's lien. Trillium asserts a mechanic's lien against the defendants pursuant to G. L. c. 254, § 4. Under the statute, a subcontractor who has entered into a written contract with a contractor for improvements to real property, or for furnishing labor or materials for such improvements, may file or record a notice of the contract with the registry of deeds, give actual notice to the owner of such recording, and upon the filing or recording shall have a lien on the property or building to secure payment for the labor or materials. Ibid. "The lien is a creature of the statute, and can be enforced only by strict compliance with the statute." Hammill-McCormick Assocs., Inc. v. New England Tel. & Tel. Co., 399 Mass. 541, 543-544 (1987). The statute "is strictly construed against the party claiming the lien." Ng Bros. Constr., Inc. v. Cranney, 436 Mass. 638, 644 (2002). "The primary purpose of the lien is to provide security to contractors, subcontractors, laborers, and suppliers for the value of their services and goods provided for improving the owner's real estate.... At the same time, the statute contains filing and notice requirements to protect the owner and others with an interest in the property." Tremont Tower Condominium, LLC v. George B.H. Macomber Co., 436 Mass. 677, 679 (2002), quoting from Hammill-McCormick Assocs., Inc., supra at 542-543.

General Laws c. 254, § 4, as appearing in St. 1996, c. 364, § 5, limits a mechanic's lien by providing that the lien "shall not exceed the amount due or to become due under the original contract as of the date notice of the filing of the subcontract is given by the subcontractor to the owner." See BloomSouth Flooring Corp. v. Boys' & Girls' Club of Taunton, Inc., 440 Mass. 618, 623-624 (2003). Trillium asserts that the paragraph which follows the above-quoted language, and which was newly added to the statute by the 1996 amendment, provides an exception to this limitation for a lower-tier subcontractor or supplier-i.e., one who "has no direct contractual relationship with the original contractor"-who serves a notice of identification on the general contractor. G. L. c. 254, § 4. Trillium argues that AvalonBay, in managing the project for Avalon Canton, was the general contractor, making Superior the subcontractor, and Trillium the sub-subcontractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Uproar Co. v. National Broadcasting Co.
81 F.2d 373 (First Circuit, 1936)
Hammill-McCormick Associates, Inc. v. New England Telephone & Telegraph Co.
505 N.E.2d 883 (Massachusetts Supreme Judicial Court, 1987)
Druker v. Roland Wm. Jutras Associates, Inc.
348 N.E.2d 763 (Massachusetts Supreme Judicial Court, 1976)
Anthony's Pier Four, Inc. v. HBC ASSOCIATES
583 N.E.2d 806 (Massachusetts Supreme Judicial Court, 1991)
Ng Bros. Construction, Inc. v. Cranney
766 N.E.2d 864 (Massachusetts Supreme Judicial Court, 2002)
Tremont Tower Condominium, LLC v. George B.H. Macomber Co.
767 N.E.2d 20 (Massachusetts Supreme Judicial Court, 2002)
Bloomsouth Flooring Corp. v. Boys' & Girls' Club of Taunton Inc.
800 N.E.2d 1038 (Massachusetts Supreme Judicial Court, 2003)
Miller v. Cotter
448 Mass. 671 (Massachusetts Supreme Judicial Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
104 N.E.3d 682, 93 Mass. App. Ct. 1114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midwest-constr-servs-inc-v-avalonbay-cmtys-inc-massappct-2018.