Anthony's Pier Four, Inc. v. HBC ASSOCIATES

583 N.E.2d 806, 411 Mass. 451, 1991 Mass. LEXIS 586
CourtMassachusetts Supreme Judicial Court
DecidedDecember 30, 1991
StatusPublished
Cited by676 cases

This text of 583 N.E.2d 806 (Anthony's Pier Four, Inc. v. HBC ASSOCIATES) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anthony's Pier Four, Inc. v. HBC ASSOCIATES, 583 N.E.2d 806, 411 Mass. 451, 1991 Mass. LEXIS 586 (Mass. 1991).

Opinion

Abrams, J.

This case arises from two agreements (agreements), dated August 1, 1983, between Anthony’s Pier Four, Inc. (Anthony’s), 1 and HBC Associates (HBC), 2 providing for HBC’s acquisition and development of Fan Pier. 3

The development was halted in May, 1987, as a result of a dispute between Anthony’s and HBC. In January, 1988, Anthony’s sued HBC. On the same day, HBC brought suit against Anthony’s. Each claimed contract violations against the other (as well as other claims). The cases were consolidated for trial. After a jury-waived trial, the judge ruled that Anthony’s violated the express terms of the agreements and the implied covenant of good faith and fair dealing. The judge rejected HBC’s claim that Anthony’s was liable to HBC under G. L. c. 93A (1990 ed.). Thereafter, there was a trial on damages. The judge ruled in favor of HBC in the *454 sum of $42.6 million, plus postbreach expenses incurred by HBC and monies owed by Anthony’s and others for the cost of joint development consultants. 4 Both parties appeal.

Anthony’s argues that we should (1) vacate the proceedings; (2) not accord the judge’s findings and rulings any deference; (3) conclude that the inconsistencies in the judge’s findings and rulings preclude appellate review; (4) reject the judge’s determination that there was a material breach of the express contract; (5) reject the judge’s conclusion that Anthony’s had violated the implied covenant of good faith and fair dealing; (6) affirm the judge’s holding that Anthony’s is not liable to HBC under G. L. c. 93A; (7) reverse the determination on liability for evidentiary errors; (8) determine that the judge erred in using an improper measure of damages, making erroneous evidentiary rulings on damages, committing a mathematical error, and awarding post-breach expenditures; (9) determine that the judge erred in holding a number of Athanas family ventures jointly and severally liable for environmental consultants’ fees; and (10) reverse the judge’s partial final judgment and enter a judgment for Anthony’s. HBC cross-appealed the denial of its claims for violation of G. L. c. 93A. Both sides filed applications for direct appellate review. We allowed the applications. We affirm the award of expectancy damages, postbreach rent and taxes paid by HBC to Anthony’s, and consultants’ fees. We set aside the award of postbreach expenditures not attributable to rent or taxes. We reverse so much of the judgment as denied G. L. c. 93A damages to HBC. We remand the matter to the trial judge for further proceedings consistent with this opinion.

The judge found the following facts. Fan Pier is a parcel (approximately eighteen and one half acres) of undeveloped land located in South Boston. Fan Pier abuts Pier Four to the east. HBC’s development plans for Fan Pier included a *455 high-rise hotel, office towers, luxury condominiums, and a marina. At the time that HBC was developing Fan Pier, Anthony’s was developing Pier Four. Anthony’s was planning a smaller but similar development on Pier Four, which was also to include a hotel, condominiums, and office and retail space.

The agreements between Anthony’s and HBC to develop the Fan Pier site, among other things, confer on Anthony’s limited rights of approval of changes in HBC’s basic development plan. 5 Specifically, the 1983 development agreement provides that changes in the development team and the basic development plan shall be subject to the approval of Athanas. In the agreement, “Athanas acknowledges that the [bjasic [development [pjlan was flexible and tentative since it was prepared before extensive engineering studies of the property were made and before HBC commenced the public process of obtaining permits and approvals. Therefore, Athanas’s approval of a change in the [bjasic [development [pjlan will be required only if such change would have a materially adverse effect on the factors set forth in (i), (ii), or (iii) below [the review conditions].” The factors are: “(i) ensuring that the changes are consistent with the [b]asic [development [p]Ian as previously approved; (ii) ensuring that a hotel is located reasonably close to [Anthony’s] remaining property to the extent consistent with its being a waterfront hotel, it being understood that HBC shall not be required to construct the hotel closer than Pier 2; and (iii) *456 ensuring that the design of such hotel integrates with and is not detrimental to [Anthony’s] property adjacent to the [Fan Pier site] . . ;

The agreements also stipulate that “HBC shall submit a reasonable explanation” of any changes in the basic development plan. Anthony’s covenants that “approval shall not be unreasonably withheld or delayed and shall be deemed given if Athanas has failed to respond with specified objections within fourteen days after receipt by Athanas of HBC’s request and the requisite information.”

Anthony’s and HBC’s development efforts were cooperative, with shared consultants, coordinated planning, and joint filings for public approvals. Their goal was to develop projects which would-be fully integrated and compatible with each other. Representatives of Anthony’s, including Athanas himself, appeared along with HBC representatives before numerous groups — from public agencies to the Boston Globe newspaper — to promote the Fan Pier and Pier Four projects. 6 The Fan Pier project director met with Athanas regularly in order to keep him informed of HBC’s progress and to review with him decisions HBC faced as it proceeded. 7

In 1984, HBC changed architects for the Fan Pier project. Athanas and his sons travelled to Chicago with HBC representatives to interview the new architectural firm (the second architects). The second architects began work on a new master plan for Fan Pier that fall. They met with Anthony’s architects to coordinate the development of the Fan Pier and Pier Four master plans. 8 The second architects presented *457 their preliminary master plan to Athanas at two meetings in November, 1984.

In March, 1985, Athanas convened a meeting with the Fan Pier project director to express his concern that the Fan Pier project was moving ahead of the Pier Four project, and reiterated his desire to have the two projects proceed in tandem through the government permitting process. In response, the Fan Pier project director advised Athanas to hire á development adviser in order to ensure that the Pier Four development proceeded apace and in tandem with the Fan Pier project. A few months later, Anthony’s hired such an adviser.

Through the spring and summer of 1985, the second architects worked on developing a “lesser scale alternative,” a refinement of their first development scheme. In the fall of 1985, HBC learned that Anthony’s had, like HBC, dismissed its first architect and retained a new architectural firm.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.K.S. v. D.S.S.
Massachusetts Appeals Court, 2024
Serebrennikov v. Proxet Group LLC
D. Massachusetts, 2024
Columbia Plaza Associates v. Northeastern University
Massachusetts Supreme Judicial Court, 2024
Williamson v. Barlam
Massachusetts Appeals Court, 2024
American Paper Recycling Corp. v. Ihc Corp.
775 F. Supp. 2d 322 (D. Massachusetts, 2011)
Trenwick America Reinsurance Corp. v. Irc, Inc.
764 F. Supp. 2d 274 (D. Massachusetts, 2011)
Wilder v. TOYOTA FINANCIAL SERVICES AMERICAS CORP.
764 F. Supp. 2d 249 (D. Massachusetts, 2011)
Commonwealth v. McCowen
939 N.E.2d 735 (Massachusetts Supreme Judicial Court, 2010)
Banco Do Brasil, S.A. v. 275 Washington Street Corp.
750 F. Supp. 2d 279 (D. Massachusetts, 2010)
Kuchera v. Parexel International Corp.
719 F. Supp. 2d 121 (D. Massachusetts, 2010)
Law Offices of Jeffrey S. Glassman v. Palmisciano
690 F. Supp. 2d 5 (D. Massachusetts, 2009)
Vreeken v. Lockwood Engineering, B.V.
218 P.3d 1150 (Idaho Supreme Court, 2009)
Sax v. DiPrete
639 F. Supp. 2d 165 (D. Massachusetts, 2009)
Moore v. La-Z-Boy, Inc.
639 F. Supp. 2d 136 (D. Massachusetts, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
583 N.E.2d 806, 411 Mass. 451, 1991 Mass. LEXIS 586, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anthonys-pier-four-inc-v-hbc-associates-mass-1991.