Maverick Construction Management Services, Inc. v. Evergrass, Inc.

27 Mass. L. Rptr. 41
CourtMassachusetts Superior Court
DecidedApril 15, 2010
DocketNo. 20060710
StatusPublished

This text of 27 Mass. L. Rptr. 41 (Maverick Construction Management Services, Inc. v. Evergrass, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maverick Construction Management Services, Inc. v. Evergrass, Inc., 27 Mass. L. Rptr. 41 (Mass. Ct. App. 2010).

Opinion

Kenton-Walker, Janet, J.

This action arises from the construction of an athletic field on the campus of Nichols College (“Nichols”). The plaintiff, Maverick Construction Management Services, Inc. (“Maverick”), was a subcontractor retained by one of the general contractors, Evergrass, Inc. (“Evergrass”)1 to provide a variety of various non-design-related services to Evergrass. Maverick filed a mechanic’s lien after it did not receive payment for its services from Evergrass. Subsequently, Maverick brought claim against the defendant Fidelity & Deposit Company of Maryland (“Fidelity”), the successor in interest to Nichols.2 Pursuant to Mass.R.Civ.P. 56(b), Fideliiy moves for summary judgment on the grounds that Maverick failed to properly perfect the lien pursuant to G.L.c. 254, §4. For the reasons below, Fidelity’s Motion for Summary Judgment is ALLOWED.

BACKGROUND

On November 1, 2004, Nichols entered into a contract (the “Athletic Field Contract”) with Evergrass and Rosewood (the ’’General Contractors”) to design and build an athletic field on its campus (the “Project”). Maverick’s contract with Evergrass was based on a proposal submitted by Maverick in October 2004, to provide a variety of construction and excavation services to assist the Project.

The relevant part of the Athletic Field Contract provided that “[w]hen the Owner determines that the Work or designated portion thereof is substantially complete, the Owner will issue a Certificate of Substantial Completion which shall establish the date of Substantial Completion . . .” The Athletic Field Contract further provided that “Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use.” Additionally, “[w]arranties required by the Contract Documents shall commence on the date of Substantial Completion of the Work . . .”

The field was delivered to Nichols on September 16, 2005, to use at its homecoming football game. After September 16, 2005, the field completely failed and required replacement.3 Maverick did not return to the Project after September 16, 2005. After the field failed, the General Contractors proposed repairs; however, they did not repair or replace the field. Nichols eventually hired a new general contractor to replace the field and commenced an arbitration proceeding against the General Contractors, pursuant to the Athletic Field Contract, seeking damages.

Nichols succeeded in its arbitration claim. The arbitrators found that the General Contractors “substantially and materially breached the Agreement for which they [were] jointly and severally liable.” The arbitrators held that:

Such breaches included, but are not necessarily limited to:

a) The design failed to achieve the intended purposes of the Project;
b) Drainage within the confines of the Project boundaries, did not comply with the approved design nor did it achieve the intended purposes of the Project.
c) Construction of the sub-grade for the Field was defective and did not comply with the approved design, requiring substantial remedial work on the Project.

As a result of the breach by the General Contractors, the arbitrators awarded Nichols damages in the amount of $1,005,680.00, after subtracting the unpaid contract balance of $249,909.4

Maverick alleges that Evergrass failed to pay it for its work on the Project, even though Evergrass was required to do so under the Athletic Field Contract.5 Accordingly, John Fiore (“Fiore”), Maverick’s President, sent a letter to Nichols notifying Nichols of its intent to file a mechanic’s lien. In the letter, Fiore stated “Maverick has been unable to obtain payment from Evergrass for the construction services work performed on this project.”

On October 14, 2005, Maverick recorded a Notice of Contract, indicating that it was owed $155,170.25. After receiving some additional payment for its services, on January 11, 2006, Maverick filed an amended Notice of Contract for an amount then due of $54,824.16. On April 4, 2006, Maverick commenced this lawsuit. On November 7,2007, Maverick obtained default judgment against Evergrass (Curran, J.) in the amount of $66,612.46, which judgment remains unsatisfied.

Maverick and Fideliiy disagree as to when the Project was “substantially completed” pursuant to the definition provided in the Athletic Field Contract. Fidelity argues the Project was substantially completed September 16, 2005 and, therefore, summary judgment is appropriate because Maverick failed to perfect [42]*42its mechanic’s lien pursuant to G.L.c. 254, §4, within the ninety days of that date.6 Maverick argues the construction was substantially completed later, as supported by a Notice of Contract filed by Evergrass that states “(w]ork was last performed under the contract at the site by the contractor on October 22, 2005.” Maverick contends certain other documents support an argument that the last performance date might even have been in March of 2006. Fidelity has responded by saying that any work done on the Project after September 16, 2005 represented “warranty” work, which fails to extend the time for filing a lien.7

In further support of its motion for summary judgment, Fidelity contends that the decision of the arbitrators demonstrates that no money was due or to become due to the General Contractors under the Athletic Field Contract, and therefore, no money was due or to become due to Maverick.

DISCUSSION

Summary judgment will be granted when no genuine dispute exists as to any material fact and the moving party is entitled to judgment as a matter of law. See Mass.R.Civ.P. 56; Cassesso v. Commissioner of Corr., 390 Mass. 419, 422 (1983); Community Nat'l Bank v. Dawes, 369 Mass. 550, 553 (1976). In deciding a motion for summary judgment, the court may consider pleadings, depositions, answers to interrogatories, admissions on file, and affidavits. Mass.R.Civ.P. 56(c); Community Nat'l Bank, 369 Mass. at 553. The Court views the facts “in the light most favorable to [the non-moving party], taking all the facts set forth in its supporting affidavits as true.” G.S. Enters., Inc. v. Falmouth Marine, Inc., 410 Mass. 262, 263 (1991). The moving party bears the burden of affirmatively demonstrating that there is no genuine issue of material fact on every relevant issue. Kourouvacilis v. General Motors Corp., 410 Mass. 706, 711 (1991). Once the moving party establishes the absence of a triable issue, the party opposing the motion must respond with evidence of specific facts that establish the existence of a genuine issue of material fact. Mass.R.Civ.P. 56(e); see Godbout v. Cousens, 396 Mass. 254, 261 (1985); Madsen v. Erwin, 395 Mass. 715, 719 (1985). The non-moving party cannot defeat the motion for summary judgment by resting on pleadings and mere assertions of disputed facts, but must offer evidence that would be admissible at trial. LaLonde v. Eissner, 405 Mass. 207, 209 (1989). See also Cullen Enters., Inc. v. Massachusetts Prop. Ins. Underwriting Ass’n, 399 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hammill-McCormick Associates, Inc. v. New England Telephone & Telegraph Co.
505 N.E.2d 883 (Massachusetts Supreme Judicial Court, 1987)
Godbout v. Cousens
485 N.E.2d 940 (Massachusetts Supreme Judicial Court, 1985)
LaLonde v. Eissner
539 N.E.2d 538 (Massachusetts Supreme Judicial Court, 1989)
Cullen Enterprises, Inc. v. Massachusetts Property Insurance Underwriting Ass'n
507 N.E.2d 717 (Massachusetts Supreme Judicial Court, 1987)
East Coast Steel Erectors, Inc. v. Ciolfi
632 N.E.2d 397 (Massachusetts Supreme Judicial Court, 1994)
Baltimore Contractors, Inc. v. Dupree
223 N.E.2d 702 (Massachusetts Supreme Judicial Court, 1967)
Town of Nantucket v. Beinecke
398 N.E.2d 458 (Massachusetts Supreme Judicial Court, 1979)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Mullen Lumber Co. v. Lore
537 N.E.2d 123 (Massachusetts Supreme Judicial Court, 1989)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Madsen v. Erwin
481 N.E.2d 1160 (Massachusetts Supreme Judicial Court, 1985)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
G.S. Enterprises, Inc. v. Falmouth Marine, Inc.
571 N.E.2d 1363 (Massachusetts Supreme Judicial Court, 1991)
Blount Brothers Corp. v. Lafayette Place Associates
506 N.E.2d 499 (Massachusetts Supreme Judicial Court, 1987)
Ng Bros. Construction, Inc. v. Cranney
766 N.E.2d 864 (Massachusetts Supreme Judicial Court, 2002)
Tremont Tower Condominium, LLC v. George B.H. Macomber Co.
767 N.E.2d 20 (Massachusetts Supreme Judicial Court, 2002)
Bloomsouth Flooring Corp. v. Boys' & Girls' Club of Taunton Inc.
800 N.E.2d 1038 (Massachusetts Supreme Judicial Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
27 Mass. L. Rptr. 41, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maverick-construction-management-services-inc-v-evergrass-inc-masssuperct-2010.