East Coast Steel Erectors, Inc. v. Ciolfi

632 N.E.2d 397, 417 Mass. 602, 1994 Mass. LEXIS 219
CourtMassachusetts Supreme Judicial Court
DecidedApril 27, 1994
StatusPublished
Cited by18 cases

This text of 632 N.E.2d 397 (East Coast Steel Erectors, Inc. v. Ciolfi) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
East Coast Steel Erectors, Inc. v. Ciolfi, 632 N.E.2d 397, 417 Mass. 602, 1994 Mass. LEXIS 219 (Mass. 1994).

Opinion

Nolan, J.

The plaintiff, East Coast Steel Erectors, Inc. (East Coast), appeals from a Superior Court judge’s dismissal of its claim against Phillip K. Ciolfi, trustee of Danvers Executive Park Trust (trust), seeking to enforce a mechanic’s lien it recorded under G. L. c. 254, § 4 (1992 ed.). The judge held that East Coast failed to perfect its mechanic’s lien in accordance with c. 254, the mechanic’s lien statute. We granted East Coast’s request for direct appellate review. We reverse.

This dispute arises out of a project for the construction of a building on land owned by the trust in Danvers. Whitney Development Corporation (Whitney) served as the general contractor and East Coast served as a subcontractor on the structural steel work. On October 24, 1990, East Coast brought suit in Superior Court against Whitney and the trust, claiming that it had not been paid for its services rendered on the project. It sought relief from Whitney under theories of contract and quasi contract. Against the trust, it sought to enforce a mechanic’s lien pursuant to G. L. 254, §§ 4, 5, 8, 11 (1992 ed.). The claims against Whitney were subsequently settled. The case proceeded to trial solely on. the mechanic’s lien count.

The pertinent facts follow. 2 East Coast and Whitney negotiated a written contract, in which East Coast agreed to perform the structural steel work for Whitney’s project. The contract required that the steel erection be substantially completed within fifteen working days of February 12, 1990. A working day was identified as any day, Monday through Friday, excluding days when the contractor would be unable *604 to be on the property because of weather, lack of materials, or other such matters. The contract also provided that no extra work or changes under the contract would be recognized unless agreed to in writing.

Prior to erecting the steel structure, as provided in the contract, East Coast was required to supply anchor bolts and base plates which were to be imbedded in concrete. On February 12, 1990, East Coast sent a truck load of steel, anchor bolts, and plates to the job site. After East Coast unloaded the anchor bolts and plates, Whitney directed East Coast to remove the steel from the premises, stating that it had not obtained the necessary building permits. On February 15, 1990, East Coast had recorded a notice of contract pursuant to G. L. c. 254, § 4, in the Essex South registry of deeds. This notice of contract specified February 26, 1990, as the contract’s completion date. East Coast then filed its first notice of extension specifying the extended completion date as March 30, 1990. On February 21, 1990, Whitney sent a letter to East Coast requesting that it stop all work on the project until the necessary permits were obtained. Unable to proceed, East Coast subsequently filed four additional notices of extension. Each of these notices of extension was filed before the completion date specified in the previous notice. East Coast’s last notice of extension specified the completion date as August 31, 1990. Whitney never agreed to any of these extensions of the completion date. The trust never objected to any completion date specified in the notice of contract and notices of extension. East Coast properly notified the trust of the recording of the notice of contract and the notices of the extensions. On August 28, 1990, East Coast recorded a statement of account. On September 5, 1990, East Coast notified the trust of the filing of the statement of account. On October 24, 1990, East Coast filed a complaint seeking to enforce its mechanic’s lien and recorded a certified copy.

On these facts, the judge ruled that East Coast’s lien was invalid. Relying on Blount Bros. Corp. v. Lafayette Place Assocs., 399 Mass. 632 (1987), the judge concluded that the *605 five notices of extension which East Coast had filed were ineffective because Whitney had not agreed to the extensions of the completion date specified in the notices. The judge ruled that the lien dissolved under G. L. c. 254, § 8, because East Coast had failed to file its statement of account within thirty days of the completion date specified in its notice of contract. The judge stated that the date by which to file a statement of account would have been extended if East Coast had recorded valid notices of extension. Accordingly, the judge ordered the dismissal of East Coast’s claim. The judge did not specifically address whether the contract contained a completion date.

East Coast claims that it fully complied with the strict requirements of G. L. c. 254, § 4, in attempting to perfect its mechanic’s lien. “General Laws c. 254 provides that a debt due to a person who performs labor or supplies material for the improvement of real estate by agreement or with the express or implied consent of the owner is secured by a mechanic’s lien.” Hammil-McCormick Assocs. v. New England Tel. & Tel. Co., 399 Mass. 541, 542 (1987). The lien’s primary purpose is “to provide security to contractors, subcontractors, laborers, and suppliers for the value of their services and goods provided for improving the owner’s real estate.” Id. at 542-543. The statute contains filing and notice requirements to protect the owner and others with an interest in the real estate. Id. at 543. The lien is solely a statutory creation and, as such, can only be enforced by strict compliance with the statutory specifications. Section 4 sets forth the specifications for a subcontractor’s lien. It provides in pertinent part that a subcontractor who “furnishes labor or material . . . under a written contract with a contractor . . . may file in the registry of deeds ... a notice of his contract.” This notice of contract is to follow substantially a form included in § 4. In following this form, the subcontractor is required to state the date by which the contract will be completed. This section further provides that “[a] notice of any extension of such contract, stating the date to which it is extended, shall also be filed . . . prior to the date stated in the notice of *606 the contract for the. completion thereof.” Section 2, which sets forth the filing and notice requirements for perfecting a general contractor’s lien, also requires the contractor to specify the contract completion date in its notice of contract and contains similar language concerning notice of any extension.

Unlike § 2, however, § 4 also provides that the time for the performance of the subcontract “shall not be extended beyond the time for the performance of the original contract and any extension thereof, if the objection thereto of the owner is filed . . . and actual notice of such objection is given ... to the sub-contractor within five days after the owner received notice of the filing of the contract.” Section 4 further provides that for purposes of the mechanic’s lien statute, the dates of completion stated in a properly filed notice of contract and notices of extension shall be the date the subcontract is to be performed. In addition, § 4 specifies a procedure to be followed where the subcontract does not contain a completion date. There is no corresponding provision in § 2. The last paragraph of § 4 provides in pertinent part: “If the contract does not contain a completion date, the person filing the notice of contract . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Mechanical Contractors, Inc. v. C.E. Floyd Co.
27 Mass. L. Rptr. 290 (Massachusetts Superior Court, 2010)
Maverick Construction Management Services, Inc. v. Evergrass, Inc.
27 Mass. L. Rptr. 41 (Massachusetts Superior Court, 2010)
Philip Alan, Inc. v. MSarcia Construction Services, Inc.
19 Mass. L. Rptr. 705 (Massachusetts Superior Court, 2005)
Oueliet v. Armstrong
18 Mass. L. Rptr. 100 (Massachusetts Superior Court, 2004)
Golden v. General Builders Supply LLC
807 N.E.2d 822 (Massachusetts Supreme Judicial Court, 2004)
National Lumber Co. v. Lombardi
2004 Mass. App. Div. 50 (Mass. Dist. Ct., App. Div., 2004)
National Lumber Co. v. United Casualty & Surety Insurance
802 N.E.2d 82 (Massachusetts Supreme Judicial Court, 2004)
National Lumber Co. v. LeFrancois Construction Corp.
2002 Mass. App. Div. 228 (Mass. Dist. Ct., App. Div., 2002)
Ng Bros. Construction, Inc. v. Cranney
766 N.E.2d 864 (Massachusetts Supreme Judicial Court, 2002)
Capital Funding Services, Inc. v. Red Oak Corp.
14 Mass. L. Rptr. 244 (Massachusetts Superior Court, 2001)
Johnson Lumber Co. v. Woodscape Homes, Inc.
746 N.E.2d 533 (Massachusetts Appeals Court, 2001)
NG Bros. Construction v. Cranney
12 Mass. L. Rptr. 556 (Massachusetts Superior Court, 2000)
National Lumber Co. v. Epstein
2000 Mass. App. Div. 317 (Mass. Dist. Ct., App. Div., 2000)
New Boston Housing Enterprises, LLC v. Fitzgerald Contracting Co.
12 Mass. L. Rptr. 310 (Massachusetts Superior Court, 2000)
National Lumber Co. v. LeFrancois Construction Corp.
723 N.E.2d 10 (Massachusetts Supreme Judicial Court, 2000)
Fraser Engineering Co. v. Franchi Group Associates, Inc.
8 Mass. L. Rptr. 595 (Massachusetts Superior Court, 1998)
Commonwealth v. Butler
668 N.E.2d 832 (Massachusetts Supreme Judicial Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
632 N.E.2d 397, 417 Mass. 602, 1994 Mass. LEXIS 219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/east-coast-steel-erectors-inc-v-ciolfi-mass-1994.