Blount Brothers Corp. v. Lafayette Place Associates

506 N.E.2d 499, 399 Mass. 632, 1987 Mass. LEXIS 1223
CourtMassachusetts Supreme Judicial Court
DecidedApril 14, 1987
StatusPublished
Cited by15 cases

This text of 506 N.E.2d 499 (Blount Brothers Corp. v. Lafayette Place Associates) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blount Brothers Corp. v. Lafayette Place Associates, 506 N.E.2d 499, 399 Mass. 632, 1987 Mass. LEXIS 1223 (Mass. 1987).

Opinion

Nolan, J.

The plaintiff, Blount Brothers Corporation (Blount), appeals from the entry of summary judgment for the defendant, Lafayette Place Associates (Lafayette). The Appeals Court affirmed. Blount Bros. v. Mondev Mass., Inc., 22 Mass. App. Ct. 96 (1986). We granted Blount’s application for further appellate review. We affirm.

The dispute arises out of the construction of the Lafayette Place project in downtown Boston. Blount was the general contractor that constructed the Lafayette Place project and Lafayette developed and presently owns part of the complex. See Blount Bros. v. Mondev Mass., Inc., 22 Mass. App. Ct. at 97. The sole issue in this appeal concerns the validity of a mechanic’s lien Blount attempted to establish pursuant to G. L. c. 254 (1984 ed.).

The essential facts are not in dispute. On June 10, 1983, Blount and Lafayette entered into a written contract under which Blount was to act as the general contractor for the construction of Lafayette Place. The contract provided that the retail portion of the project was to be substantially completed by October 15, 1983, and that the construction of the hotel portion was to be substantially completed by May 15, 1984. Blount did not complete either portion of the project by May 15, nor did it file a notice of contract prior to that date. On March 12, 1985, Blount filed a notice of contract in the Suffolk County registry of deeds pursuant to G. L. c. 254, § 2. 2 The *634 notice of contract stated March 22, 1985, as the completion date, not May 15, 1984.* * 3 Blount argues that the date set forth in the notice of contract should be a date which is a reasonable estimate of when the work will actually be finished. Lafayette counters that the completion date in the notice of contract must be the completion date specified in the written contract between the parties.

Prior to 1972, the mechanic’s lien statute only secured payment for work which was performed after a notice of contract was filed. Hammill-McCormick Assocs. v. New England Tel. & Tel. Co., ante 541, 546 (1987). See St. 1972, c. 774, § 6. Thus, before 1972, we had no reason to consider whether the statute imposed a deadline for filing. In 1972, however, the Legislature amended the mechanic’s lien statute, extending the lien to secure payment for work and materials supplied before as well as after the filing of a notice of contract. In Hammill-McCormick Assocs., ante, we considered for the first time whether the amended section of the mechanic’s lien statute applicable to subcontractors, G. L. c. 254, § 4, imposes a deadline for the filing of a notice of contract. We concluded that a notice of contract which stated the completion date set forth in the contract itself as the date of completion was sufficient to establish a lien. Ante at 545. We did not, *635 however, reach the question now before us: whether the completion date in the notice of contract must be the contract date, not the estimated actual completion date, in order to establish a valid lien.

Section 2, which is the provision of the mechanic’s lien statute applicable to general contractors, does not clearly require the notice of contract to be filed before a certain date. The statute provides that a person who improves another’s real estate pursuant to a written contract “shall have a lien . . . when notice of said contract is filed or recorded in the registry of deeds.” G. L. c. 254, § 2. See note 2, supra. The statute provides a form for the notice, and included in the form is the statement, “Said contract is to be completed on or before__” G. L. c. 254, § 2. This language simply provides that a lien is established when a notice of contract which recites a completion date is filed. The statutory provisions do not clearly specify what date is to be included as the completion date.

The following paragraph of § 2, however, suggests that the completion date must be the date set forth in the written contract. It requires a notice of any extension of the written contract to be filed “prior to the date stated in the notice of contract.” We agree with the Appeals Court that the extension provision of § 2 would be meaningless if the contract date differed from the date stated in the notice of contract. Blount Bros., 22 Mass. App. Ct. at 101. In such a scenario, a contractor would be able to establish a lien for work performed after the agreed upon contract completion date without ever having to negotiate successfully a contract extension. Mortgagees and other third parties who relied on the contract completion date recorded in the registry of deeds could be significantly prejudiced by the assertion of a lien after the contract completion date. See Gettens Elec. Supply Co. v. W.R.C. Properties, Inc., 21 Mass. App. Ct. 658, 661 n.2 (1986). 4

*636 Our examination of the statute’s legislative history also indicates that the completion date set forth in the notice of contract must be the date recited in the written contract. In 1914, the Legislature appointed a special commission to consider and recommend changes in the laws relative to mechanic’s liens. Res. 1914, c. 121. In its report, the commission noted that one of the problems with the lien statute was that “it is . . . entirely uncertain when [the contract] may end” and “it is,, impossible for a purchaser or mortgagee to tell. . . that a lien . may not exist.” Extract from the Report of the Special Commission Appointed to Consider and Recommend Changes in the Laws Relative to Liens, Mortgages, and Tax Titles 1 Mass. L.Q. 344, 349 (1916) (excerpt of 1915 House Doc. No. 1600). To solve this problem, the special commission recommended that the Legislature require the filing of a notice of contract. Id. at 350. The Legislature adopted this recommendation as a substitution for the earlier requirement of recording the contract itself. Id. This parallel between the notice of contract and the actual contract is a strong indication that the Legislature intended the completion date set forth in the notice of contract to be the completion date set forth in the written contract. In addition, we note that the current practice in Massachusetts is to recite the contract date as the completion date in the notice of contract. J.J. Myers & C.L. Noble, Massachusetts Construction Law 235 (1986).

Prior decisions of this court interpreting the mechanic’s lien statute also indicate that the completion date in the notice of contract must be the completion date set forth in the written contract. In Pratt & Forrest Co. v. Strand Realty Co., 233 Mass. 314, 317 (1919), the court said “that substantial accuracy in the statement [in the notice of contract] of the date fixed by the principal contract for the completion of the work to be performed under it is essential to a valid notice.” Our holding in Pratt

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maverick Construction Management Services, Inc. v. Evergrass, Inc.
27 Mass. L. Rptr. 41 (Massachusetts Superior Court, 2010)
Preferred Contractors, Inc. v. Connecticut General Life Insurance
16 Mass. L. Rptr. 219 (Massachusetts Superior Court, 2003)
Tremont Tower Condominium, LLC v. George B.H. Macomber Co.
767 N.E.2d 20 (Massachusetts Supreme Judicial Court, 2002)
Ng Bros. Construction, Inc. v. Cranney
766 N.E.2d 864 (Massachusetts Supreme Judicial Court, 2002)
Capital Funding Services, Inc. v. Red Oak Corp.
14 Mass. L. Rptr. 244 (Massachusetts Superior Court, 2001)
NG Bros. Construction v. Cranney
12 Mass. L. Rptr. 556 (Massachusetts Superior Court, 2000)
New Boston Housing Enterprises, LLC v. Fitzgerald Contracting Co.
12 Mass. L. Rptr. 310 (Massachusetts Superior Court, 2000)
National Lumber Co. v. LeFrancois Construction Corp.
723 N.E.2d 10 (Massachusetts Supreme Judicial Court, 2000)
Fraser Engineering Co. v. Franchi Group Associates, Inc.
8 Mass. L. Rptr. 595 (Massachusetts Superior Court, 1998)
East Coast Steel Erectors, Inc. v. Ciolfi
632 N.E.2d 397 (Massachusetts Supreme Judicial Court, 1994)
In re Brown
160 B.R. 401 (D. Massachusetts, 1993)
Volpe Construction Co. v. First National Bank
567 N.E.2d 1244 (Massachusetts Appeals Court, 1991)
Mullen Lumber Co. v. Lore
537 N.E.2d 123 (Massachusetts Supreme Judicial Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
506 N.E.2d 499, 399 Mass. 632, 1987 Mass. LEXIS 1223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blount-brothers-corp-v-lafayette-place-associates-mass-1987.