Superior Glass Co. v. First Bristol County National Bank

394 N.E.2d 972, 8 Mass. App. Ct. 356, 1979 Mass. App. LEXIS 937
CourtMassachusetts Appeals Court
DecidedSeptember 20, 1979
StatusPublished
Cited by15 cases

This text of 394 N.E.2d 972 (Superior Glass Co. v. First Bristol County National Bank) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Superior Glass Co. v. First Bristol County National Bank, 394 N.E.2d 972, 8 Mass. App. Ct. 356, 1979 Mass. App. LEXIS 937 (Mass. Ct. App. 1979).

Opinion

Kass, J.

Two subcontractors seek (in consolidated actions) to recover from an owner of property unpaid balances owed to them by a general contractor on the ground that the owner acted in a fashion which led them to believe payment for their work was covered by a performance bond.

When the defendant First Bristol County National Bank (bank) embarked upon the construction of a branch facility in Seekonk, it invited bids from general contractors based on plans and specifications containing "General Requirements” 3 which, in turn, included a provision that the contractor who received the award must furnish a performance bond. 4 C. A. Thomson Construction Company, Inc. (contractor), won the award to build the job. Because the contractor was insufficiently credit worthy, it could not obtain a performance bond. Nevertheless, the bank elected to let the contractor continue the job, thus waiving the performance bond requirement. Superior Glass Co., Inc. (Superior), and M. F. Cash Corporation (Cash), the plaintiffs in these cases, were the glazing and paving subcontractors, respectively. The supplementary general conditions of the construction contract required the contractor to "see that all subcontractors read the *358 terms of the General Conditions [and] the Supplementary-General Conditions.” Officers of Superior and Cash testified that, indeed, they had read the General Conditions, including the General Requirements, and had relied upon the requirement that whoever was the general contractor would be bonded.

As the job proceeded and the branch bank building went up, the financial condition of the contractor went down. Prior to making its last construction advance (as owner) to the contractor, the bank had possession of a list of unpaid subcontractors and suppliers, among which were Superior, which was owed a balance of $2,424, and Cash, which was owed a balance of $4,951.30. On February 21,1975, the bank made its last construction advance in the form of a cashier’s check in the amount of $13,728.30, payable to the contractor. That check was simultaneously endorsed back to the bank to satisfy a debt of $12,500 which the contractor owed the bank. The balance of $1,228.30 was credited to the contractor’s checking account at the bank.

We have drawn these facts from the findings of fact of the trial judge, which we accept unless clearly erroneous. Mass.R.Civ.P. 52(a), 365 Mass. 816 (1974). C.C. & T. Constr. Co. v. Coleman Bros., ante 133, 135 (1979), and cases cited. On our examination of the testimony and exhibits, the judge’s findings are amply supported. The judge entered judgment in the amount of $2,424 for Superior and $4,951.30 for Cash, plus interest and costs, and it is from these judgments that the bank has appealed.

1. We are invited by the plaintiffs, Superior and Cash, to decide that subcontractors are entitled to rely on, and hold an owner liable under, contract documents which contain a requirement for a payment bond in the event an owner unilaterally, and without notice to subcontractors, relieves the general contractor of the bond obligation. In the instant case, the form of the bond to be furnished, an American Institute of Architects form, does *359 not appear in the record and, consequently, there was, and is, no basis for any determination that the plaintiffs would have been entitled to the benefit of the bond had it been obtained. Contrast Waite Hardware Co. v. Ardini & Pfau, Inc., 339 Mass. 634, 638 (1959), where the bond named the owner as the sole obligee, and Morse Bros. Elec. v. Martin Shore Realty Co., 344 Mass. 81, 84-85 (1962), where the terms of the bond covered liens only. These cases call to attention that the decisions in Massachusetts have interpreted the range of obligees and beneficiaries of payment and performance bonds narrowly (Waite at 638) and that owners have no direct contractual relations with subcontractors and suppliers, even though the subcontractors might be bound by the general conditions in some circumstances (Morse at 85). For instances where a subcontractor has been able to claim against the bond see Johnson-Foster Co. v. D'Amore Constr. Co., 314 Mass. 416 (1943); Robinson Clay Prod. Co. v. Beacon Constr. Co., 339 Mass. 406, 408-410 (1959). But cf. Philip Carey Mfg. Co. v. Peerless Cas. Co., 330 Mass. 319, 320-321 (1953).

2. It was open to the subcontractors to protect their interests by filing a notice of contract under G. L. c. 254, § 4, as amended through St. 1973, c. 801, § 2, at any time before completing work under the subcontract. 5 It is not surprising that they did not do so since the bank’s architect, who supervised construction on its behalf and approved construction requisitions, asked (through the contractor) that the subcontractors supply releases of liens each time construction funds were paid to the contractor. The evidence received reflects that the bank was aware of, and encouraged this procedure. 6 Paired with *360 the construction documents, Superior and Cash suggest the request for a lien waiver constituted a misrepresentation of the degree of assurance of payment of the subcontractors on the job. However, neither the bank’s requesting, nor the subcontractors’ granting the waivers of lien was of legal effect since G. L. c. 254, § 32, makes void and unenforceable a promise purporting to bar the filing of a notice of contract or the taking of any steps to enforce a lien. Only a person named as a principal on a lien bond may give an effective waiver of lien under G. L. c. 254, § 32. There is no support in the record for a conclusion that Superior and Cash thought they had the protection of a lien bond. Liability cannot be imposed on the bank solely on the basis of the request for a waiver of lien.

3. We consider next whether the bank had a fiduciary obligation to Superior and Cash at the time it paid its last construction requisition. By January, 1975, the bank, through its architect, had become well aware that the contractor had fallen behind in its obligations to subcontractors who had provided labor and materials on the Seekonk branch job. By February 15, 1975, this awareness became specific and quantified when the bank received from its architect a list of amounts due subcontractors, with invoices and letters attached. Six days later, the bank, not as lender, but as owner, issued a check for $13,728.30 to the contractor and simultaneously took the check back, with the contractor’s endorsement to the bank on it, in order to discharge a loan owed by the contractor to the bank. By so doing, the bank crossed the line from action which was merely shabby to that which was legally actionable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Melo v. Villarcon
2015 Mass. App. Div. 32 (Mass. Dist. Ct., App. Div., 2015)
Gatof v. Northland Investment Corp.
32 Mass. L. Rptr. 468 (Massachusetts Superior Court, 2014)
Botany Bay Construction Co. v. Pullman Modular Industries, Inc.
29 Mass. L. Rptr. 398 (Massachusetts Superior Court, 2011)
Rosano-Davis, Inc. v. Sastre
2004 Mass. App. Div. 55 (Mass. Dist. Ct., App. Div., 2004)
Atlantic Industrial Services, Inc. v. Sevenson Environmental Services, Inc.
15 Mass. L. Rptr. 130 (Massachusetts Superior Court, 2002)
Cox v. Cox (In Re Cox)
247 B.R. 556 (D. Massachusetts, 2000)
Brick Construction Corp. v. CEI Development Corp.
710 N.E.2d 1006 (Massachusetts Appeals Court, 1999)
Healy v. Massachusetts Civil Service Commission
10 Mass. L. Rptr. 22 (Massachusetts Superior Court, 1999)
Blount Brothers Corp. v. Lafayette Place Associates
506 N.E.2d 499 (Massachusetts Supreme Judicial Court, 1987)
Gilmore v. Century Bank & Trust Co.
477 N.E.2d 1069 (Massachusetts Appeals Court, 1985)
County of Middlesex v. City of Newton
434 N.E.2d 1297 (Massachusetts Appeals Court, 1982)
John D. Ahern Co. v. Trustees of Boston University
421 N.E.2d 477 (Massachusetts Appeals Court, 1981)
John Alden Transportation Co. v. Bloom
415 N.E.2d 250 (Massachusetts Appeals Court, 1981)
Superior Glass Co. v. First Bristol County National Bank
406 N.E.2d 672 (Massachusetts Supreme Judicial Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
394 N.E.2d 972, 8 Mass. App. Ct. 356, 1979 Mass. App. LEXIS 937, Counsel Stack Legal Research, https://law.counselstack.com/opinion/superior-glass-co-v-first-bristol-county-national-bank-massappct-1979.