Hickey v. Thomas G. Gallagher, Inc. (In Re H & a Construction Co.)

65 B.R. 213, 1986 Bankr. LEXIS 5268, 14 Bankr. Ct. Dec. (CRR) 1215
CourtUnited States Bankruptcy Court, D. Massachusetts
DecidedSeptember 23, 1986
Docket19-10193
StatusPublished
Cited by15 cases

This text of 65 B.R. 213 (Hickey v. Thomas G. Gallagher, Inc. (In Re H & a Construction Co.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hickey v. Thomas G. Gallagher, Inc. (In Re H & a Construction Co.), 65 B.R. 213, 1986 Bankr. LEXIS 5268, 14 Bankr. Ct. Dec. (CRR) 1215 (Mass. 1986).

Opinion

MEMORANDUM

JAMES N. GABRIEL, Bankruptcy Judge.

The matters before the Court are the complaints filed by Thomas J. Hickey, the Trustee of H & A Construction Co., Inc. (“H & A” or the “Debtor”) on September 7, 1983 against Thomas G. Gallagher, Inc. (“Gallagher”), Maurer & Sforza, Inc. (“Maurer”) and E.G. Sawyer, Inc. (“Sawyer”) (collectively, the “defendants”). The Trustee alleges that the defendants received preferential transfers pursuant to 11 U.S.C. § 547(b). A hearing on all the complaints was held on June 20, 1986. At that time, the parties submitted a stipulation of facts, thereby eliminating the need for an evidentiary hearing, and the Court requested that briefs be filed. The following legal issues emerge from the briefs submitted:

1) Whether the payments made by the Debtor to the defendants within the 90 day period preceding the filing of the bankruptcy, pursuant to the terms of the Debtor’s subcontracts with the defendants, were transfers of property of the Debtor;
2) Whether the debts incurred by the Debtor, for purposes of 11 U.S.C. § 547(c)(2), were incurred when work was performed by the defendants or when payments were required under the subcontracts; and
3) Whether, under 11 U.S.C. § 547(c)(4), new value in an amount greater than the amount of a preferential transfer may be set off against a subsequent preferential transfer.

FACTS

In August 1982, the Debtor entered into a prime contract with the Massachusetts General Hospital (“MGH”) for renovation and construction of its Biomedical Engineering Building (Project # 1). In September 1982, the Debtor entered into another prime contract with MGH for renovation *215 and construction of its Computer Science Laboratory (Project # 2).

On October 6, 1982, the Debtor entered into a subcontract with Maurer for the heating, ventilation and air conditioning (“HVAC”) work required under the prime contract for Project # 1 for a price of $69,-000. On October 12, 1982, the Debtor entered into a subcontract with Sawyer for performance of the electrical work required under its prime contract for Project # 2 for a price of $152,000. Shortly thereafter, on October 22, the Debtor subcontracted with Gallagher for performance of plumbing and HVAC work required under its prime contract for Project # 2 for a price of $271,-400.

H & A’s prime contracts with MGH for Projects # 1 and # 2 were the identical AIA (American Institute of Architects) form of contract and differed only with respect to the scope of work and price. Both prime contracts contained the following provisions regarding periodic payments:

Article 13.1 The Contractor shall at least ten days before each payment falls due, deliver to the Architect an itemized statement ... showing ... all moneys [sic] paid out or costs incurred ... on account of ... Work during the previous month....
Article 14.1 The Architect will review the Contractor’s Application for Payment and will promptly take appropriate action thereon ... Such amount as he may recommend for payment shall be payable by the Owner not later that the last day of the month.
General Conditions Article 9.5.2 The Contractor shall promptly pay each Subcontractor, upon receipt of payment from Owner, out of the amount paid to the Contractor on account of such Subcontractors Work....

H & A’s subcontracts with the defendants were in the identical form and included the following provision regarding periodic payments:

... .the Contractor agrees that he will pay the Sub-contractor, in progress payments, the sum of $ ... for materials and work, said amount to be paid as follows: 90% of all labor and materials which has [sic] been fixed in place by the Sub-contractor, to be paid on or about the thirtieth of the following month....

Maurer commenced its subcontract work in October 1982; Sawyer commenced work in October 1982; and Gallagher commenced work in November 1982. During construction, all H & A subcontractors, including the defendants, submitted monthly requisitions to H & A for periodic payments. These requisitions were submitted prior to the end of the calendar month in which work was performed, but included amounts based on a percentage of the subcontract work each subcontractor estimated would be in place through the end of the month.

On both Projects, the Debtor submitted applications for periodic payment to MGH which included specific amounts on account of work performed by the defendants during the pay period. MGH then approved each of the applications for payments. The dates of approval by MGH were shown on the face page of each application. MGH paid the amount of each application to H & A within a week of the approval date. The periodic payments of Maurer, Sawyer and Gallagher were processed and paid as shown in Appendix 1.

The parties do not dispute the fact that H & A’s payments to Maurer, Sawyer and Gallagher, which the Trustee seeks to recover, were for antecedent debts incurred in the ordinary course of H & A’s and the subcontractors’ businesses; were paid in the ordinary course of business affairs between H & A and the subcontractors; were made according to ordinary business terms; and were made within 90 days of H & A’s bankruptcy petition, which was filed on March 29, 1983, at a time when H & A was insolvent.

Maurer furnished new value after January 7, 1983 in the following amounts:

Alleged Date Preference New Net Alleged Value Preference
1/7/83 $17,820 $13,567 $4,253
2/11/83 9,000 3,783 5,217
3/9/83 7,500 0 7,500

*216 Sawyer furnished new value after January 19, 1983 in the following amounts:

Date 1/19/83 3/8/83 Alleged Preference $29,700 38,000 3/21/83 20,000 5,146 Net Alleged Preference -$13,808 30,567 (16,759 if prior unused new value of $13,808 is carried forward) 14,854 Gallagher furnished new value after March 9, 1983 in the following amounts: Alleged New Net Alleged Date Preference Value Preference 3/1783 $71,181 $ 9,870 $61,311 3/18/83 35,000 14,258 20,742

CONCLUSIONS OF LAW I

Section 547(b) provides:

Except as provided in subsection (c) ... the trustee may avoid any transfer of property of the debtor
(1) to or for the benefit of a creditor;
(2) for or on account of an antecedent debt owed by the debtor before such transfer was made;
(3) made when the debtor was insolvent;
(4) made ... within 90 days before the date of filing the petition ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
65 B.R. 213, 1986 Bankr. LEXIS 5268, 14 Bankr. Ct. Dec. (CRR) 1215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hickey-v-thomas-g-gallagher-inc-in-re-h-a-construction-co-mab-1986.