Hickey v. Nightingale Roofing, Inc. (In Re Alter-Hall Construction Co.)

73 B.R. 989, 1987 Bankr. LEXIS 763
CourtUnited States Bankruptcy Court, D. Massachusetts
DecidedJune 2, 1987
Docket14-10041
StatusPublished
Cited by7 cases

This text of 73 B.R. 989 (Hickey v. Nightingale Roofing, Inc. (In Re Alter-Hall Construction Co.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hickey v. Nightingale Roofing, Inc. (In Re Alter-Hall Construction Co.), 73 B.R. 989, 1987 Bankr. LEXIS 763 (Mass. 1987).

Opinion

MEMORANDUM

JAMES N. GABRIEL, Chief Judge.

The matter before the Court is the complaint filed on July 17, 1983 by the Trustee of Alter-Hall Construction Co., Inc. (“Alter-Hall” or the “Debtor”). The complaint seeks the turnover of $29,004.78 from Nightingale Roofing, Inc. (“Nightingale”), pursuant to 11 U.S.C. § 547(b). Prior to trial that was scheduled for April 6, 1987, the parties submitted a joint stipulation of facts, thereby obviating the need for the submission of evidence. At the April 6th hearing, the Court heard oral argument and directed the parties to submit briefs within a three week period.

FACTS

Prior to the filing of the Chapter 7 petition on March 29,1983, Nightingale, a roofing sub-contractor, performed several roofing jobs for Alter-Hall, a general contractor. Two projects, one known as the Hall-ston Plaza project and the other known as the Serono Labs project were among the roofing jobs performed by Nightingale for the Debtor.

Nightingale entered into a written subcontract with Alter-Hall, dated July 15, 1983, for roofing the Serono Labs, located in Randolph, Massachusetts, for a price of $50,000. The contract required periodic payments with a ten percent retainage to be held by the Debtor pending final completion. Except for completing punch list items and furnishing the manufacturer’s roof guarantee, Nightingale had substantially completed the roof at Serono Labs by the end of December 1982.

Nightingale’s contract at Hallston Plaza consisted of a proposal dated September 9, 1982, which Alter-Hall, through an agent, orally accepted. The proposal stated “Terms Net Completion” and provided for a ten year manufacturer’s warranty. The agreed price was $26,800. Between September 9, 1982 and the end of December, 1982, Nightingale substantially completed the roof at Hallston Plaza except for certain punch list items. However, it had not provided the ten year manufacturer’s guarantee required by the contract.

On December 24, 1982, Nightingale filed, in the Suffolk Superior Court, a “Complaint to Reach and Apply,” accompanied by an affidavit executed on December 24,1982 by John T. Nightingale, the president of Nightingale. The complaint alleged that Alter-Hall previously had made some payment on work performed by Nightingale on the Hallston Plaza project and sought judgment for the balance allegedly due to Nightingale on the contract. In his affidavit, Mr. Nightingale stated that, as of December 24, 1982, Nightingale had completed its work on the Hallston Plaza project with the exception of $4,300 worth of punch list items. He further stated that Nightingale had demanded payment from Alter-Hall on at least four occasions in the sixty days prior to the date of the affidavit. On December 28,1982, George Alter, president of Alter-Hall, in connection with the state court litigation, executed an affidavit stating that Nightingale had not been paid by Alter-Hall because the roofing work was incomplete, the roof was leaking, and Nigh- *991 tíngale had not provided the ten year roof guarantee.

On March 4, 1983, twenty-five days prior to the filing of the Chapter 7 petition, Alter-Hall delivered a check in the amount of $29,004.78 to Nightingale. On the same day, Nightingale and Alter-Hall executed a stipulation dismissing the action brought by Nightingale against Alter-Hall in the Suffolk Superior Court. The parties also exchanged releases.

With respect to the substantive aspects of the Debtor’s preference claim, the parties agree that 1) the $29,004.78 payment was for debts incurred by Alter-Hall in the ordinary course of business; 2) that at the time the payment was made Alter-Hall was insolvent; and 3) that the payment enabled Nightingale to receive more than it would receive in a Chapter 7 proceeding.

After the commencement of this adversary proceeding, Nightingale returned the sum of $1,679 to the Trustee. This sum had been allocated to projects known as Synectecs, Heart Associates and Computer Devices and was returned because the payments for those projects were payments for antecedent debts incurred by Alter-Hall more than 45 days prior to the date of payment to Nightingale.

Of the remaining $27,325, $3,800 1 was allocated to the Serono Labs project and $23,525 was allocated to the Hallston Plaza project. Nightingale has refused to return amounts allocated to these contracts because it believes the payments were not preferences subject to recovery by the Trustee. Of the $3,800 allocated to the Serono Labs contract, $2,500 was allocated to secure the future delivery of a manufacturer’s roof guarantee required under the contract and $1,300.00 represented the balance due Nightingale for completion of the roofing work. Of the $1,300, $750 was subject to the assertion of an Alter-Hall repair claim by July 4, 1983.

Nightingale delivered the Serono Labs roof guarantee to Alter-Hall’s attorney on May 19, 1983. Nightingale completed the roofing work at the Serono Labs project on February 1 and February 2,1983. Nightingale’s counsel received no invoice from Alter-Hall concerning the repair claim by the specified date or at any time thereafter and the $750 remained in Nightingale’s possession.

On the Hallston Plaza project, Nightingale performed work on punch list items and did corrective work during the week of January 31, 1983. Nightingale completed all punch list work on February 23, 1983. The roofing work was thereafter inspected and accepted. On February 18,1983, Nightingale received the roof guarantee from the manufacturer and provided that guarantee to Alter-Hall. From the March 4, 1983 payment, Nightingale applied the remaining $23,525 to the balance due it on the Hallston Plaza project.

At the April 6, 1987 hearing, Trustee’s counsel conceded that of the $3,800 allocated to the Serono Labs project $2,500 was to secure the future delivery of a roofing guaranty and that Nightingale performed approximately $1,300 worth of work on that project within 45 days of the date of payment. Thus, the Court is primarily concerned with monies allocated to the Hall-ston Plaza project.

DISCUSSION

Section 547(b) provides:

Except as provided in subsection (c) ... the trustee may avoid any transfer of property of the debtor—
(1) to or for the benefit of a creditor;
(2) for or on account of an antecedent debt owed by the debtor before such transfer was made;
(3) made when the debtor was insolvent;
(4) made..within 90 days before the date of filing the petition ...
(5) that enables such creditor to receive more than such creditor would receive if—
(A) the case were under chapter 7 of this title;
*992 (B) the transfer had not been made; and
(C) such creditor received payment of such debt to the extent provided by the provisions of this title.

11 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
73 B.R. 989, 1987 Bankr. LEXIS 763, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hickey-v-nightingale-roofing-inc-in-re-alter-hall-construction-co-mab-1987.