Blount Bros. v. Mondev Mass., Inc.

491 N.E.2d 640, 22 Mass. App. Ct. 96, 1986 Mass. App. LEXIS 1517
CourtMassachusetts Appeals Court
DecidedApril 22, 1986
StatusPublished
Cited by3 cases

This text of 491 N.E.2d 640 (Blount Bros. v. Mondev Mass., Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blount Bros. v. Mondev Mass., Inc., 491 N.E.2d 640, 22 Mass. App. Ct. 96, 1986 Mass. App. LEXIS 1517 (Mass. Ct. App. 1986).

Opinion

Smith, J.

This action arises out of the construction of the hotel and retail complex known as Lafayette Place in downtown [97]*97Boston. Blount Brothers Corporation (Blount) was the general contractor that constructed Lafayette Place. Lafayette Place Associates (Lafayette), a Massachusetts general partnership, the general partners of which are two corporations, Mondev Mass., Inc., and Sefrius Corporation, developed Lafayette Place and presently owns part of it.

On May 17, 1985, Blount commenced this action in the Superior Court by a complaint filed pursuant to G. L. c. 254, the mechanic’s lien statute, in order to enforce its lien on the project. It alleged, among other things, that Lafayette had refused to pay Blount approximately $15,000,000 that Blount claimed it was owed by Lafayette for the construction of Lafayette Place.2 It also recited that Blount had perfected its lien by filing a notice of contract in the registry of deeds and by later filing a statement of account, as required by G. L. c. 254.

On June 20, 1985, Lafayette filed a motion to dismiss the complaint and a motion to dissolve the lien. The motions alleged that the notice of contract filed in the registry of deeds set forth an incorrect completion date for the project, thereby violating G. L. c. 254, § 2.3 Both motions also claimed that [98]*98Blount had failed to file an attested copy of its complaint in the registry of deeds as required by G. L. c. 254, § 5.4 The motions were accompanied by affidavits. Because of the affidavits, the judge treated the motion to dismiss the complaint as a motion for summary judgment. Mass.R.Civ.P. 12(b)(6), 365 Mass. 755 (1974). After a hearing a judgment entered dissolving the lien for the reason that “ [tjhere [had not been] compliance with G. L. c. 254, [§§] 2 & 5.” Later, a substitute final judgment entered dismissing the plaintiff’s complaint.5 On appeal, Blount argues that the judge’s actions in dissolving the lien and dismissing its complaint were error because it had fully complied with the requirements of G. L. c. 254, §§ 2 & . 5, and, in any event, it had shown that there were present genuine issues of material fact. Finally, Blount contends that we should not affirm the judgment of the Superior Court because the contract contained an illegal provision.6

[99]*99We summarize the following undisputed facts taken from the materials submitted to the judge. On or about June 10, 1983, Blount and Lafayette entered into a written contract whereby Blount agreed to act as the general contractor in connection with the construction of Lafayette Place. The contract provided that construction of the retail portion of the project was to be substantially completed by October 15, 1983, and that construction of the hotel portion was to be substantially completed by May 15, 1984. The project was not completed by May 15, and Blount did not file any notice of contract prior to that date. On March 12, 1985, Blount filed a notice of contract with the Suffolk County registry of deeds pursuant to G. L. c. 254, § 2. The notice of contract recited March 22, 1985, as the contract completion date and not May 15, 1984. On April 19, 1985, Blount filed a statement of account in which it claimed a total lien in the amount of $15,329,379.7 Although this complaint to enforce the lien was filed in the Superior Court on May 17, 1985, a copy of the complaint was not filed in the registry of deeds until June 21, 1985.

1. Violation of G. L. c. 254, §§ 2 & 5. General Laws c. 254, § 2, states that a lien is created when the lienor files in the appropriate registry of deeds a notice of the written contract between the parties. The statute also provides that the notice of contract must contain the following statement: “Said contract is to be completed on or before__” Blount contends that all that is required is that the completion date inserted in the notice of contract be a reasonable estimate by the contractor as to when the contract will indeed be completed, based on all the facts and circumstances known to him at the time. Lafayette argues, however, that the statute requires that the [100]*100statement in the notice of contract must set out the same completion date as that contained in the written contract unless the date for completion has been extended by the parties.

The court in Pratt & Forrest Co. v. Strand Realty Co., 233 Mass. 314, 317 (1919), on similar facts, held that the completion date in the written contract must be the date placed in the statement in the statutory notice of contract. The court noted that a review of the relevant statutory provisions demonstrated that “substantial accuracy in the statement [in the notice of contract] of the date fixed by the principal contract for the completion of the work to be performed under it is essential to a valid notice.” Id. The court reasoned that its holding “results inevitably from the absolute requirement [in the statute] for the statement of such date in the notice, from the fact that that date is the point of time from which run the several statutory limitations of the act, and from the provision that certain inaccuracies, among which a mistake in this date is not included, shall not affect the validity of the lien.” Id.

All of the statutory provisions which led the court to its conclusion in Strand Realty Co. are still present in the mechanic’s lien statute. General Laws c. 254, § 2, contains the absolute requirement that the date of completion be stated in the notice of contract. The statute also provides that the lien created by the filing of a notice of contract is limited to “labor or material furnished prior to the date of completion of said contract as stated in said notice.” G. L. c. 254, § 3, as appearing in St. 1972, c. 774, § 7. Allowing a party to select an arbitrary date to be used in the notice of contract that is later than the completion date stated in the written contract would make it possible for a contractor improperly to expand the scope of the lien beyond that provided in the statute.

The court in Strand Realty Co., supra at 316-317, also recognized the importance of the contract completion date in relation to the statutory time limitations contained in G. L. c. 254. Those limitations are still dependent on the completion date. The mechanic’s lien statute establishes specific steps necessary to enforce a lien and provides an explicit time table for carrying them out. The notice of contract, setting forth the [101]*101contract completion date, must be filed first. It must be filed before the completion date stated in the notice of contract. Rheem Mfg. Co. v. Monsanto Co., 6 Mass. App. Ct. 461, 464 (1978). A sworn statement of account must be filed “within thirty days after the date on which the principal contract is to be performed.” G. L. c. 254, § 8. The lien is dissolved unless a timely statement of account is filed. Id. The action to enforce the lien must be commenced within sixty days after the filing of the statement required by § 8, thus indirectly referring back to the date for completion of the principal contract. G. L. c. 254, § 11. Lack of timely compliance with this requirement also results in dissolution of the lien. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mullen Lumber Co. v. Lore
537 N.E.2d 123 (Massachusetts Supreme Judicial Court, 1989)
Blount Brothers Corp. v. Lafayette Place Associates
506 N.E.2d 499 (Massachusetts Supreme Judicial Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
491 N.E.2d 640, 22 Mass. App. Ct. 96, 1986 Mass. App. LEXIS 1517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blount-bros-v-mondev-mass-inc-massappct-1986.