General Mechanical Contractors, Inc. v. C.E. Floyd Co.

27 Mass. L. Rptr. 290
CourtMassachusetts Superior Court
DecidedJune 29, 2010
DocketNo. 1000322A
StatusPublished

This text of 27 Mass. L. Rptr. 290 (General Mechanical Contractors, Inc. v. C.E. Floyd Co.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Mechanical Contractors, Inc. v. C.E. Floyd Co., 27 Mass. L. Rptr. 290 (Mass. Ct. App. 2010).

Opinion

Agnes, Peter W., J.

Introduction

The plaintiff, General Mechanical Contractors, Inc. (“GMC”) brought this action to enforce a mechanic’s lien against property owned by the defendant, The Willows at Worcester, LLC (“Willows”), pursuant to the Mechanic’s Lien Statute, G.L.c. 254. GMC seeks to collect damages arising out of a breach of contract by the defendants C.E. Floyd Company (“Floyd”) and Safeco Insurance Company of America (“Safeco”). This matter is before the court on defendant Willows’ mo[291]*291tion to dismiss. For the reasons set forth below, the defendant’s motion is ALLOWED.

Background

Defendant Floyd was hired as a general contractor for construction and renovations to property owned by defendant Willows. Floyd hired GMC on a subcontract to provide labor and materials for HVAC (Heating, Ventilation and Air Conditioning) work for a fee totaling $2,365,000.00. Floyd later requested that GMC perform extra work in the amount of $236,293.00, resulting in a total value of $2,601,293.00 for the subcontract. On October 15, 2007, defendants Floyd and Safeco recorded a lien bond for the benefit of the subcontractors, including GMC.1

GMC alleges that it substantially performed in good faith, and that the defendants have breached the contract by failing to pay $90,000.00 on the subcontract. GMC further alleges that the defendants refuse to pay the balance despite repeated requests. On August 27, 2009, nearly two years after the Lien Bond was recorded, GMC recorded a Notice of Contract with the Worcester County Registry of Deeds, pursuant to G.L.c. 254, §4, which caused a mechanic’s lien to be asserted against the property. Pursuant to G.L.c. 254, §8, GMC recorded a sworn Statement of Account on November 6, 2009, followed by Amended Statements of Account on December 15, 2009, December 29, 2009, and February 5, 2010.

GMC commenced this action against the defendants to enforce the lien bond against defendants Floyd and Safeco. GMC is also seeking to assert the mechanic’s lien against defendant Willows as the property owner in the event that the lien bond is determined to be defective or inapplicable. Willows has moved to dismiss this action claiming that GMC has not properly stated a claim for which relief can be granted.

Discussion

A motion to dismiss “argues that the complaint fails to state a claim upon which relief can be granted.” Jarosz v. Palmer, 436 Mass. 526, 529 (2002). In considering a motion to dismiss, “the allegations of the complaint, as well as such inferences as may be drawn therefrom in the plaintiffs favor, are to be taken as true.” Nader v. Citron, 372 Mass. 96, 98 (1977). To survive a motion to dismiss, the complaint must contain “allegations plausibly suggesting (not merely consistent with) an entitlement to relief,” and “must be enough to raise a right to relief above the speculative level.” Iannacchino v. Ford Motor Co., 451 Mass. 623, 636 (2008), quoting Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 555 (2007).

The issue in this case is whether G.L.c. 254, §12 allows a party to assert a mechanic’s lien after a lien bond has been recorded. Willows has moved to dismiss on the grounds that G.L.c. 254, §12 bars a mechanic’s lien from attaching after a lien bond has been recorded by an insurance company. GMC has alleged that defendants Floyd and Safeco have not admitted to the validity of the lien bond, and that §12 allows a subcontractor to assert a mechanic’s lien even after a bond is recorded.

A. Overview of the Mechanic’s Lien Statute

Massachusetts law creates a mechanism known as a mechanic’s lien which provides security to contractors, subcontractors, laborers, and suppliers who “perform! ] labor or supplies material for the improvement of real estate by agreement or with the express or implied consent of the owner . . .” and to whom a debt is due. Hammill-McCormick Assoc., Inc. v. New England Tel. & Tel Co., 399 Mass. 541, 542-43 (1987). The mechanic’s lien is asserted through strict compliance with G.L.c. 254, which “contains filing and notice requirements to protect the owner and others with an interest in the property.” Hammill-McCormick Assoc., Inc., 399 Mass. at 542-43. Massachusetts law requires the subcontractor to whom the debt is due to

record a “notice of contract” in the registry of deeds for the county in which the property is located. The statute sets a deadline for the recording of such a notice of contract, and calculates that deadline according to the way that the contract is either terminated or completed. If the parties to the contract have filed a notice of substantial completion (signifying the parties’ agreement that the “work under the written contract is sufficiently complete so that it can be occupied or utilized for its intended use,” G.L.c. 254, §2A), the contractor must file the notice of contract no later than sixty days after the filing of the notice of substantial completion. G.L.c. 254, §2. If the contract has been terminated and the owner has filed a notice of termination (see G.L.c. 254, §2B), the contractor must file the notice of contract no later than ninety days after the filing of the notice of termination. G.L.c. 254, §2. Or, in the absence of any such notice of substantial completion or notice of termination, the deadline for filing a notice of contract is ninety days after the contractor “last performed or furnished labor or materials or both labor and materials." A notice of contract may be recorded “at any time after execution of the written contract,” as long as it is recorded before the applicable deadline. The recording of the notice of contract establishes the priority of the mechanic’s lien. As a general matter, the lien takes priority over all other later-recorded encumbrances on the property.

Tremont Tower Condo. LLC v. George B.H. Macomber Co., 436 Mass. 677, 680 (2002).

“The lien shall be dissolved unless a civil action to enforce it is commenced within ninety days after the filing of the statement required by [G.L.c. 254] section eight.” G.L.c. 254, §11.2 See also Volpe Construction Co. v. First National Bank of Boston, 30 Mass.App.Ct. 249, 255 (1991). A mechanic’s lien is perfected only [292]*292by strict compliance with the statutory requirements.3 Hammill-McCormick Assoc., Inc., 399 Mass. at 543-44; Ng Bros. Const. Inc. v. Cranney, 436 Mass. 638, 644 (2002), citing East Coast Steel Erectors, Inc. v. Ciolfi, 417 Mass. 602, 605 (1994).

The Mechanic’s Lien Statute also gives security to general contractors and/or landowners by providing a remedy to avoid the adverse impact of a mechanic’s lien. “Any person, including the owner, in interest in connection with a written contract. . . may cause to be recorded in the registry of deeds in the county or district where the land lies a bond of a surety company authorized to do a surely business in Massachusetts and in a penal sum equal to the contract sum.” G.L.c. 254, §12. Furthermore, “(a]fter the recording of any such bond, no lien under this chapter shall thereafter attach in favor of any person entitled to the benefit of such bond and not named as a principal thereon for labor or for labor and materials performed under the contract in respect to which such bond is given.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Hammill-McCormick Associates, Inc. v. New England Telephone & Telegraph Co.
505 N.E.2d 883 (Massachusetts Supreme Judicial Court, 1987)
Hoffman v. Howmedica, Inc.
364 N.E.2d 1215 (Massachusetts Supreme Judicial Court, 1977)
East Coast Steel Erectors, Inc. v. Ciolfi
632 N.E.2d 397 (Massachusetts Supreme Judicial Court, 1994)
Volpe Construction Co. v. First National Bank
567 N.E.2d 1244 (Massachusetts Appeals Court, 1991)
Nader v. Citron
360 N.E.2d 870 (Massachusetts Supreme Judicial Court, 1977)
Pyle v. School Committee
423 Mass. 283 (Massachusetts Supreme Judicial Court, 1996)
Jarosz v. Palmer
766 N.E.2d 482 (Massachusetts Supreme Judicial Court, 2002)
Ng Bros. Construction, Inc. v. Cranney
766 N.E.2d 864 (Massachusetts Supreme Judicial Court, 2002)
Tremont Tower Condominium, LLC v. George B.H. Macomber Co.
767 N.E.2d 20 (Massachusetts Supreme Judicial Court, 2002)
National Lumber Co. v. United Casualty & Surety Insurance
802 N.E.2d 82 (Massachusetts Supreme Judicial Court, 2004)
Iannacchino v. Ford Motor Co.
451 Mass. 623 (Massachusetts Supreme Judicial Court, 2008)
Warren Bros. v. Peerless Insurance
397 N.E.2d 329 (Massachusetts Appeals Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
27 Mass. L. Rptr. 290, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-mechanical-contractors-inc-v-ce-floyd-co-masssuperct-2010.