Avanti Systems, USA, Inc. v. Plattypus, LLC

28 Mass. L. Rptr. 134
CourtMassachusetts Superior Court
DecidedDecember 6, 2010
DocketNo. SUCV2009273E
StatusPublished

This text of 28 Mass. L. Rptr. 134 (Avanti Systems, USA, Inc. v. Plattypus, LLC) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Avanti Systems, USA, Inc. v. Plattypus, LLC, 28 Mass. L. Rptr. 134 (Mass. Ct. App. 2010).

Opinion

Roach, Christine M., J.

This is a commercial contract dispute involving installation of high-end glass partitions in an office condominium in downtown Boston. Plaintiff Avanti is the glass installer; the two defendants were the general contractor for the renovation project (Plattypus) and the owner of the preme-sis (Nucleus), respectively. Avanti sued for enforcement of a mechanic’s lien in the amount of $57,929. The defendants counterclaimed for breach of contract and violation of Chapter 93A. The case was tried to the bench July 26-27, 2010. Following post-trial briefing the court finds and rules as follows with respect to the claims in this action.

FINDINGS OF FACT

All of the below-enumerated Findings of Fact represent findings by the court, including but not limited to determinations of the credibility, weight, and probative value of the evidence adduced at hearing and reasonable inferences drawn from that evidence, as well as stipulations by the parties.

1. Avanti is a New York corporation, engaged in the installation of high-end glass walls, doors and partitions. This was its first job in Massachusetts. Mordaunt Trial Testimony.

2. Plattypus, LLC is a general contractor engaged in both residential and commercial renovation, with a principal place of business in Canton, Massachusetts. Nucleus, also a Massachusetts limited liability company with a principal place of business in Wellesley, Massachusetts, is the owner of the commercial premises at issue. Nucleus hired Plattypus to complete the in-process renovation of an office condominium at 100 State Street, Unit 10, Boston, in about April 2008 which had been begun by another contractor. Platt Trial Testimony; Campbell Trial Testimony.

3. A portion of the renovation designed by Nucleus’ architect included the manufacture and installation of glass partitions. The defendants found Avanti as a potential vendor for the glass through Avanti’s internet web site. Platt Trial Testimony; Campbell Trial Testimony.

4. Nucleus authorized Plattypus to contract with Avanti to deliver and install the glass at the premises. The contract price was $54,000. The contract terms and price are memorialized in a series of emails between Plattypus and Avanti dated May 30, 2008 through June 20, 2008. Platt Trial Testimony; Mordaunt Trial Testimony; Trial Exhibits 1-4, and 11.

5. Plattypus provided one-third of the contract price, or $16,200, to Avanti as an initial deposit on June 26, 2008. Trial Exhibit 5; Trial Exhibit 8 at page 9.

6. Glass was ultimately delivered to the premises in ■three stages, on August 26, 2008, September 6, 2008, and on some later date in September. Platt Trial Testimony; Mordaunt Trial Testimony.

7. Prior to the first delivery on August 26, 2008, a dispute arose among the three parties regarding responsibility for the cost of renting and staffing a crane to deliver glass to the tenth floor of the building, and to prepare the premises for the crane. The premises elevators were not large enough to carry the glass, but no one from Avanti had inspected the elevators prior to setting the contract price. Avanti’s experience had been that it was industry practice for the customer to be responsible for access to the premises for the glass, usually by freight elevator. Platt Trial Testimony; Mordaunt Trial Testimony; Trial Exhibit 7.

8. Nucleus ultimately paid $3,000.00 towards these August 24, 2008 costs, and Plattypus paid $1,901.24. Platt Trial Testimony; Trial Exhibit 12.

9. Portions of the glass (including larger sliding panes) delivered on August 24, 2008 were mis-mea-sured and mis-cut by the manufacturer (not Avanti); the glass was backwards from the proper configuration required for installation. This mistake required reordering and re-delivering replacement glass. Platt Trial Testimony; Mordaunt Trial Testimony.

10. Nonetheless, Plattypus paid Avanti a second installment due on the contract, of $16,500, on August 24, 2008. Trial Exhibit 11.

11. Avanti and Plattypus again negotiated, but disagreed about, the cost of re-craning the re-delivered glass on September 6, 2008. Plattypus arranged for the crane and ultimately bore the cost, as Avanti and Nucleus declined to do so. The crane rental was $1,512. Plattypus principal Kevin Platt estimates Plattypus’ additional costs (preparing the premises and paying workers) to have been roughly $1,500. Platt Trial Testimony; Mordaunt Trial Testimony; Campbell Trial Testimony; Trial Exhibit 13.

12. Avanti and Plattypus also disagreed about the most economical method and who should bear responsibility for disposing of the mis-cut glass. Plattypus ultimately disposed of the glass, for a cost to it of $500. Platt Trial Testimony; Mordaunt Trial Testimony; Trial Exhibit 8 at pages 2, 5-9.

13. There was a third delivery date in mid- to late-September to replace some additional panes of glass, which were smaller and were successfully transported in the building elevator. Mordaunt Trial Testimony; Schindler Trial Testimony.

14. Following the final installation Nucleus notified Plattypus of the following defects: A “hair” scratch in the door to Nucleus’ principal (Campbell’s) office, at approximately eye level and approximately six inches long; one chip on each of two main glass partitions at the edge where they meet; incorrectly aligned rails (door guides); and two missing door stops for swinging office doors. Platt Trial Testimony; Campbell Trial Testimony; Schindler Trial Testimony.

[136]*13615. The first record documentation of notice to Avanti by Plattypus of these issues is on September 26, 2008. Mordaunt Trial Testimony; Trial Exhibit 8, at page 3.

16. Despite his lack of experience with high-end glass, Platt undertook to develop a “very loose” estimate of the cost to accomplish the repairs. Platt’s estimate is $10,230. Nucleus withheld this amount from its payments to Plattypus. Platt Trial Testimony. Mordaunt believed this estimate was “high.” At trial Avanti estimated the cost of repairs to be $2,000. Mordaunt Trial Testimony.

17. Avanti declined to come back to Boston to make the repairs unless Plattypus “brought his payments up to date,” by which Avanti was referring to the third, post-delivery, payment under the contract of $16,200. Mordaunt Trial Testimony; Trial Exhibit 11.

18. The parties engaged in a series of vituperative emails regarding the defective installation, the possibility of repairs, and the amounts due under the contract. Avanti claimed it wanted to finish the job and get paid. Plattypus and Nucleus offered to escrow funds, but declined to pay Avanti until the repairs were made, and continued to seek reimbursement of costs for the second crane delivery. Nucleus informed Plattypus that it wanted Avanti, not another contractor, to repair the work, and at the time of trial the work had not been repaired. Campbell Trial Testimony; Trial Exhibit 8 at pages 2-5; Trial Exhibit 14.

19. Notwithstanding the ongoing dispute, Plattypus paid Avanti an additional $5,000 on October 6, 2008, and $3,929 on November 10, 2008. However, the $3,929 check was never cashed by Avanti and was ultimately cancelled by Plattypus, for a total of $37,700 paid—and $16,300 owed—on the $54,000 contract. Platt Trial Testimony; Trial Exhibits 10 and 22.

20. On October 27, 2008, Avanti filed a notice of mechanic’s lien at the Suffolk Registry of Deeds against the Premises at 100 State Street, stating that Avanti was owed $41,629 on the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hammill-McCormick Associates, Inc. v. New England Telephone & Telegraph Co.
505 N.E.2d 883 (Massachusetts Supreme Judicial Court, 1987)
International Fidelity Insurance v. Wilson
443 N.E.2d 1308 (Massachusetts Supreme Judicial Court, 1983)
Leardi v. Brown
474 N.E.2d 1094 (Massachusetts Supreme Judicial Court, 1985)
Madan v. Royal Indemnity Co.
532 N.E.2d 1214 (Massachusetts Appeals Court, 1989)
Hawthorne's, Inc. v. Warrenton Realty, Inc.
606 N.E.2d 908 (Massachusetts Supreme Judicial Court, 1993)
Canney v. New England Telephone & Telegraph Co.
228 N.E.2d 723 (Massachusetts Supreme Judicial Court, 1967)
Halper v. Demeter
610 N.E.2d 332 (Massachusetts Appeals Court, 1993)
Anthony's Pier Four, Inc. v. HBC ASSOCIATES
583 N.E.2d 806 (Massachusetts Supreme Judicial Court, 1991)
Squeri v. McCarrick
588 N.E.2d 22 (Massachusetts Appeals Court, 1992)
Datacomm Interface, Inc. v. Computerworld, Inc.
489 N.E.2d 185 (Massachusetts Supreme Judicial Court, 1986)
Massachusetts Employers Insurance Exchange v. Propac-Mass, Inc.
420 Mass. 39 (Massachusetts Supreme Judicial Court, 1995)
Columbia Chiropractic Group, Inc. v. Trust Insurance
430 Mass. 60 (Massachusetts Supreme Judicial Court, 1999)
National Lumber Co. v. LeFrancois Construction Corp.
723 N.E.2d 10 (Massachusetts Supreme Judicial Court, 2000)
Kattar v. Demoulas
433 Mass. 1 (Massachusetts Supreme Judicial Court, 2000)
Ng Bros. Construction, Inc. v. Cranney
766 N.E.2d 864 (Massachusetts Supreme Judicial Court, 2002)
Uno Restaurants, Inc. v. Boston Kenmore Realty Corp.
805 N.E.2d 957 (Massachusetts Supreme Judicial Court, 2004)
Ayash v. Dana-Farber Cancer Institute
822 N.E.2d 667 (Massachusetts Supreme Judicial Court, 2005)
Green v. Blue Cross & Blue Shield of Massachusetts, Inc.
713 N.E.2d 992 (Massachusetts Appeals Court, 1999)
Tech Plus, Inc. v. Ansel
793 N.E.2d 1256 (Massachusetts Appeals Court, 2003)
Zabin v. Picciotto
896 N.E.2d 937 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
28 Mass. L. Rptr. 134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/avanti-systems-usa-inc-v-plattypus-llc-masssuperct-2010.