Butler Contracting, Inc. v. Court Street, LLC

631 S.E.2d 252, 369 S.C. 121, 2006 S.C. LEXIS 183
CourtSupreme Court of South Carolina
DecidedMay 30, 2006
Docket26160
StatusPublished
Cited by52 cases

This text of 631 S.E.2d 252 (Butler Contracting, Inc. v. Court Street, LLC) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Butler Contracting, Inc. v. Court Street, LLC, 631 S.E.2d 252, 369 S.C. 121, 2006 S.C. LEXIS 183 (S.C. 2006).

Opinion

*125 Chief Justice TOAL:

This appeal raises issues relating to whether a mechanic’s lien was timely perfected and the denial of prejudgment interest to the prevailing party. We affirm in part and reverse in part.

Factoal/Procedural Background

Butler Contracting, Inc. (Subcontractor) signed a contract with Morris Construction Co. (Contractor) to provide labor and materials for interior walls and ceilings in a commercial renovation project. Court Street, LLC (Owner) hired the companies to transform and expand a former church site in Greenville into condominiums. The original contract amount between Subcontractor and Contractor was $493,156. 1 Including additional work and change orders, Subcontractor asserted it was owed a total of $713,364, of which Contractor paid $536,363, leaving a balance due of $177,001.

Henry Holseberg, a principal owner of both Owner and Contractor who apparently controlled both companies, did not dispute the original contract amount, the various amounts for additional work and changes asserted by Subcontractor, or the amount still owed to Subcontractor. Owner, however, filed a counterclaim seeking an offset for $94,878 in damages allegedly caused by delays attributable to Subcontractor and work which Subcontractor failed to timely or properly perform. 2

During construction, Owner or Contractor apparently began having financial difficulties and fell behind in payments to various companies working on the project. Contractor did not prepare contemporaneous records of tasks Subcontractor allegedly failed to perform or provide detailed back-charges to Subcontractor as the project progressed. Instead, Contractor declined to pay Subcontractor’s invoices in full. After Subcontractor filed a notice of mechanic’s lien and a lawsuit seeking to enforce the lien, Contractor reviewed past records such as time and material sheets in an attempt to document the proper amount of back-charges allegedly owed by Subcontrac *126 tor. Contractor’s staff made these calculations during or after Holseberg’s deposition; some two years after the project was completed.

Holseberg testified the work Subcontractor failed to do included work in the church basement, repairing areas damaged by other subcontractors, completing changes requested by owners who had purchased units, and completing “punch lists” of minor problems in finished units. Contractor eventually hired a drywall finisher fired by Subcontractor to help complete the necessary work. There apparently was some degree of miscommunication and disagreement between the parties regarding changes and repairs, with Subcontractor insisting it properly performed the work and objecting to potential back-charges due to confusion about which company had performed repairs.

Subcontractor provided labor and materials at the project on a regular basis from mid-1999 until December 2000, although it apparently was not constantly at the jobsite due to delays caused by asbestos removal and the work of other subcontractors. Danny Hodge testified Subcontractor was supposed to perform additional work in the church basement after December 2000, and was ready, willing, and able to do so, but Contractor never asked Subcontractor to complete the work.

In early 2001, Subcontractor, at the request of Contractor’s supervisor, delivered one box of ceiling tiles to replace tiles at the project which had been damaged by water leaks. Hodge testified the ceiling tiles were surplus materials from the project stored at Subcontractor’s warehouse. Subcontractor routinely included the cost of replacing some damaged ceiling tiles in its estimates, and often provided replacement tiles even though it was not explicitly required to do so by a particular contract. A project foreman for Contractor signed a form accepting delivery of the tiles. Holseberg testified the tiles were not needed, although he was uncertain whether they were used.

Subcontractor filed a notice and certificate of its mechanic’s lien in circuit court approximately one month after delivering the ceiling tiles. About two months later, Subcontractor filed a lawsuit in circuit court against Owner and Contractor, *127 asserting causes of action based in contract, the mechanic’s lien statute, and quantum meruit. Subcontractor sought the balance due of $177,001, attorney’s fees, prejudgment interest, and foreclosure and sale of the real property to satisfy its lien.

The case was referred with finality to a master-in-equity. After a bench trial, the trial court found the mechanic’s lien had been timely served and recorded as required by statute. The trial court awarded $152,001 to Subcontractor, which represented a reduction of $25,000 from the original demand stemming from delays attributable to Subcontractor. The trial court did not offset any damages claimed by Contractor for work it allegedly performed that was Subcontractor’s responsibility. Subcontractor requested payment of attorney’s fees of $43,529 as the prevailing party, and the trial court separately awarded $35,000 in attorney’s fees. The trial court denied Subcontractor’s request for prejudgment interest.

Owner and Contractor appealed and Subcontractor cross-appealed. We certified this case from the court of appeals pursuant to Rule 204(b), SCACR, and the parties present the following issues for review:

I. Did the trial court err in ruling Subcontractor timely served and recorded its mechanic’s lien?
II. Did the trial court err in ruling Subcontractor was not entitled to prejudgment interest on the balance due?

Standard op Review

A proceeding for the enforcement of a statutory lien, such as a mechanic’s lien, is legal in nature. Willard v. Finch, 123 S.C. 56, 116 S.E. 96 (1923); Stoudenmire Heating & Air Conditioning Co. v. Craig Bldg. Partnership, 308 S.C. 298, 301, 417 S.E.2d 634, 636 (Ct.App.1992). In an action at law, when a case is tried without a jury, the trial court’s findings of fact will be upheld on appeal when they are reasonably supported by the evidence. Stated another way, the trial court’s findings of fact will not be disturbed on appeal unless wholly unsupported by the evidence or unless it clearly appears the findings were influenced or controlled by an error of law. The trial court’s findings in such a case are equivalent to a jury’s findings in a law action. Townes Assocs., Ltd. v. City *128 of Greenville, 266 S.C. 81, 86, 221 S.E.2d 773, 775 (1976); Willard, 123 S.C. at 58, 116 S.E. at 96; Stoudenmire, 308 S.C. at 301, 417 S.E.2d at 636.

Law/Analysis

I. Perfection of Mechanic’s Lien

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rosen Hagood, LLC v. Albert Henson, Jr.
Court of Appeals of South Carolina, 2025
Fast Formliners Company v. Construction Resource Group, Inc.
Court of Appeals of South Carolina, 2025
Paired Pay Inc v. Clearobject Inc
D. South Carolina, 2024
Julia Sibley-Jones v. Decide4Action, Inc. (2)
Court of Appeals of South Carolina, 2024
The Shops at Wescott, LLC v. Sake House IV, Inc.
Court of Appeals of South Carolina, 2023
R-Anell Housing Group, LLC v. Homemax, LLC
Court of Appeals of South Carolina, 2023
Twin Bridge Logistics, LLC v. Fisher Tank Company
Court of Appeals of South Carolina, 2022
Challenge Golf Group of South Carolina, LLC v. Brandimarte
Court of Appeals of South Carolina, 2021
The Kitchen Planners v. Friedman
Court of Appeals of South Carolina, 2020
Moore v. Moore
Court of Appeals of South Carolina, 2019
Gambrell v. Smith
Court of Appeals of South Carolina, 2017
Miller Construction Co. v. PC Construction of Greenwood, Inc.
791 S.E.2d 321 (Court of Appeals of South Carolina, 2016)
Maybank v. BB&T Corp.
787 S.E.2d 498 (Supreme Court of South Carolina, 2016)
Vision Contracting v. Geter
Court of Appeals of South Carolina, 2016
Mevers Kitchens v. Maryann Wagner
Court of Appeals of South Carolina, 2015
Elite Construction v. Tummillo
Court of Appeals of South Carolina, 2015
MicroClean Technology, Inc. v. EnviroFix, Inc.
773 S.E.2d 579 (Supreme Court of South Carolina, 2015)
Ferguson Fire & Fabrication, Inc. v. Preferred Fire Protection, L.L.C.
762 S.E.2d 561 (Supreme Court of South Carolina, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
631 S.E.2d 252, 369 S.C. 121, 2006 S.C. LEXIS 183, Counsel Stack Legal Research, https://law.counselstack.com/opinion/butler-contracting-inc-v-court-street-llc-sc-2006.