Franklin Building Supply Co. v. Sumpter

87 P.3d 955, 139 Idaho 846, 2004 Ida. LEXIS 37
CourtIdaho Supreme Court
DecidedMarch 4, 2004
Docket29822
StatusPublished
Cited by18 cases

This text of 87 P.3d 955 (Franklin Building Supply Co. v. Sumpter) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Franklin Building Supply Co. v. Sumpter, 87 P.3d 955, 139 Idaho 846, 2004 Ida. LEXIS 37 (Idaho 2004).

Opinion

BURDICK, Justice.

Franklin Building Supply filed a material-man’s hen on the home of Douglas and Pamela Sumpter after their contractor, Pond Construction, defaulted on its account with Franklin and filed for bankruptcy. The appeal challenges the district court’s order holding that the hen was not timely filed and dismissing Franklin’s foreclosure proceedings, and the district court’s use of the statutory rate of interest to be applied on the hen claim. Because the hen was filed within ninety days of the date that the last item was supplied by the materialman, we reverse the district court’s ruling as to timeliness of the lien; and we affirm the application of the statutory rate of interest.

FACTS AND PROCEDURAL BACKGROUND

In May 1998, Douglas and Pamela Sump-ter entered into an agreement with Clarence Pond and Pond Construction, Inc. (“Pond”) to build their home. Pond began construction in July 1998. On November 25, 1998, the city building inspector orally advised the Sumpters that they could occupy the home, and he issued the certificate of occupancy for the home on November 27, 1998, subject to the completion of the porch columns. After the Sumpters moved in, they prepared several pynch lists of items that needed to be completed in the home. While the punch list items were being worked on, the Sumpters initially withheld final payment to Pond. The Sumpters signed the borrower’s acceptance statement on December 17, 1998, but only sent it to Pond on December 29. The Sump-ters made their final payment to Pond on January 11, 1999, although some punch list items still remained to be completed.

From July 2 to December 16,1998, Franklin Building Supply (“Franklin”) supplied the materials used to construct the Sumpters’ *849 home through Pond’s open account. On December 16, 1998, Pond purchased a sheet of cedar and a locking door handle for the Sumpters’ home, as well as some electrical cords and a hammer that were not used in the Sumpters’ home. Franklin maintained separate open accounts for each of Pond’s construction projects, and it submitted separate monthly bills to Pond for materials supplied for the Sumpters’ home.

Pond failed to pay Franklin for the materials used in the Sumpters’ home and eventually filed for bankruptcy. So as not to compound Pond’s financial problems, Franklin waited as long as possible to file a lien on the Sumpters’ home. On the ninetieth day following the December 16, 1998, order by Pond, Franklin filed its claim of lien on the Sumpters’ property, in accordance with the I.C. § 45-507. The lien amount was the cost of the materials supplied to Pond, as well as eighteen percent interest for the period of July 1998 to December 16,1998.

Franklin filed its complaint in September 1999 seeking to foreclose its lien. Both parties filed motions for summary judgment, which were denied by the district court because there were genuine issues of material fact, which required that the case proceed to trial. During the pendency of the trial to the court, Franklin sought to admit Pond’s application for credit, for the purpose of establishing an 18 percent interest rate that was a term of the parties’ credit agreement. The district court ruled the application inadmissible and held that statutory interest applied, because the Sumpters were not party to the credit agreement between Franklin and Pond.

On October 1, 2001, the district court issued its Findings of Fact, Conclusions of Law and Order granting dismissal of the claims against the Sumpters. The district court found that although Franklin’s lien was filed within ninety days of the last items supplied by Franklin on the Sumpters’ home, the statute required it to be filed within ninety days from the date of substantial completion of the home. The district court, therefore, concluded that Franklin’s lien was untimely and entered judgment against Franklin.

Franklin appeals, challenging the district court’s interpretation of the lien statute, I.C. § 45-507, and its evidentiary ruling barring admission of Pond’s credit application. On Franklin’s appeal in this Court, we assigned the case to the Court of Appeals; the Court of Appeals reversed and remanded the ease to the district court to determine the amount due to Franklin under its claim of lien, including interest and other costs or fees provided by law. This Court granted the Sump-ters’ petition for review.

STANDARD OF REVIEW

“When considering a case on review from the Court of Appeals, this Court gives serious consideration to the Court of Appeals; however, this Court reviews the trial court decision directly. This Court is not merely reviewing the correctness of the Court of Appeals’ decision; rather, this Court is healing the matter as if the ease were on direct appeal from the district judge’s decision.” Northland Ins. Co. v. Boise’s Best Autos & Repairs, 131 Idaho 432, 433, 958 P.2d 589, 590 (1998). Where there is no dispute as to the factual circumstances, our review consists of ascertaining the effect of applicable law on the undisputed facts. Simplot v. William C. Owens, M.D., P.A., 119 Idaho 243, 244, 805 P.2d 449, 450 (1990).

A district court’s findings of fact in a court-tried case will be liberally construed on appeal in favor of the judgment entered, in view of the district court’s role as trier of fact. Western Heritage Ins. Co. v. Green, 137 Idaho 832, 835, 54 P.3d 948, 951 (2002) (citing Conley v. Whittlesey, 133 Idaho 265, 269, 985 P.2d 1127 (1999); Lindgren v. Martin, 130 Idaho 854, 857, 949 P.2d 1061, 1064 (1997)). Review of the decision is limited to ascertaining whether the evidence supports the findings of fact and whether the findings of fact support the conclusions of law. Id. If the findings of fact are based on substantial evidence, even if the evidence is conflicting, they will not be overturned on appeal. Id. However, this Court exercises free review over questions of law. Id.

*850 DISCUSSION

I.

Idaho’s materialman’s lien statute provides that every person who performs labor, furnishes materials or renders professional services in the construction of a building or other structure “has a lien upon the same for the work or labor done or professional services or materials furnished.” I.C. § 45-501 (Supp.1998). “The purpose of these statutes is to compensate persons who perform labor upon or furnish material to be used in construction, alteration or repair of a structure.” Barber v. Honorof, 116 Idaho 767, 768-69, 780 P.2d 89, 90-91 (1989). The laws regarding materialman’s liens are liberally construed in favor of the person who performs labor upon or furnishes materials to be used in the construction of a building. L & W Supply Corp. v. Chartrand Family Trust,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Regdab, Inc. v. Graybill
Idaho Supreme Court, 2019
Duane Kemmer v. Bob Newman
387 P.3d 131 (Idaho Supreme Court, 2016)
ACI Northwest, Inc. v. Monument Heights, LLC
342 P.3d 618 (Idaho Supreme Court, 2015)
Hap Taylor & Sons, Inc. v. Summerwind Partners, LLC
338 P.3d 1204 (Idaho Supreme Court, 2014)
Allied General F&S v. DeBest Fire
Idaho Court of Appeals, 2014
De Groot v. Standley Trenching, Inc.
338 P.3d 536 (Idaho Supreme Court, 2014)
DeGroot v. Standley Trenching, Inc.
Idaho Supreme Court, 2014
Credit Suisse AG v. Teufel Nursery, Inc.
321 P.3d 739 (Idaho Supreme Court, 2014)
Magleby v. Kevin
296 P.3d 400 (Idaho Supreme Court, 2013)
Stonebrook Constraction, LLC v. Chase Home Finance, LLC
277 P.3d 374 (Idaho Supreme Court, 2012)
BMC West Corp. v. Horkley
174 P.3d 399 (Idaho Supreme Court, 2007)
Butler Contracting, Inc. v. Court Street, LLC
631 S.E.2d 252 (Supreme Court of South Carolina, 2006)
Read v. Harvey
112 P.3d 785 (Idaho Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
87 P.3d 955, 139 Idaho 846, 2004 Ida. LEXIS 37, Counsel Stack Legal Research, https://law.counselstack.com/opinion/franklin-building-supply-co-v-sumpter-idaho-2004.