KIDWELL, Justice.

L & W Supply Corporation d.b.a. Gem State Acoustical and Drywall Supply (Gem State) brought an action to foreclose a materialman’s lien against a home owned by the Chartrand Family Trust (Chartrand). The district court granted summary judgment for Chartrand and dismissed Gem State’s claim, finding that Gem State’s lien was invalid, because Gem State was too remote from Chartrand in order to enjoy the benefits of Idaho’s materialman’s lien statute, I.C. § 45-501. Gem State has appealed the grant of summary judgment. Chartrand has cross-appealed the district judge’s denial of its motion for attorney fees and costs. We agree that Gem State’s claim of lien was invalid and that Chartrand was entitled to an award of costs at trial.

I.

FACTS AND PROCEDURAL BACKGROUND

The following facts were adapted from the district court’s first “Memorandum Decision and Order on Summary Judgment Motions.” Chartrand hired a general contractor to build a steel-frame house near Salmon, Idaho. The general contractor engaged Total American, Inc. (Total American) to supply the steel framing materials for the home. Total American, in turn, engaged the appellant, Gem State, to supply the requisite materials. Gem State now seeks to enforce a lien against the property, under I.C. § 45-501.

In its early dealings with Total American, the general contractor requested a bid for a “complete steel package” to be used in the construction of the house. Total American’s *741 bid indicated that the company could provide a “complete framing package” to include “[engineered, detailed drawings for the required design criteria,” “[s]truetural CAD drawings depicting each components (sic) length and gauge in all load bearing walls as per the architectural plans provided,” “[c]ross sections throughout the structure showing connection locations and attachment procedures,” and “[t]echnieal assistance available by telephone/fax.” The bid further included all of the necessary steel components, including steel studs, clips and fasteners, and pre-cut materials for header and truss assemblies to be fabricated at the building site. Bill Ladd, Total American’s officer, negotiated with the general contractor, reviewed house plans provided by the general contractor, and developed a list of materials. Total American agreed to provide those materials to the general contractor.

In determining the necessary materials, Ladd used standard load tables provided by steel manufacturers. He created his own Computer Aided Drafting (CAD) drawings to identify load-bearing walls, floor systems, and components for the framing system. The general contractor participated in finalizing the drawings and made significant changes to the design. Ladd also created detailed instructions about assembly and conveyed those instructions to the general contractor. Neither Ladd nor Total American participated in any on-site construction. Total American charged the general contractor a flat, agreed-upon rate for its work in identifying components, assembling the materials, and preparing the instructions.

In August of 1998, Total American submitted its materials list to Gem State. Gem State was to supply the components and deliver them directly to the building site. Gem State did not have the materials in stock, but rather ordered the materials from its supplier, Knorr Steel Framing Systems (Knorr). Knorr caused the materials to be delivered to the job site on August 28, 1998, and the components were eventually incorporated into the structure of the house.

Shortly after the materials were delivered, Knorr billed Gem State, and Gem State billed Total American. Although Total American was paid by the general contractor, it failed to pay Gem State. Gem State filed a notice of a lien, under I.C. § 45-501(hereaf-ter “materialman’s lien”), against the Chart-rand property. On February 16, 1999, Gem State brought this action to foreclose the lien. In May of 1999, Gem State sent another invoice to Total American in the amount of $19,421.34. The invoice identified some late charges, but it did not notify Total American that a lien had been filed or that Gem State would require payment of its attorney fees. On June 9,1999, Total American submitted a check for the full amount of the invoice. On the check, Total American included a condition that acceptance of the check would constitute a full release by Gem State. On June 10, Gem State’s attorney contacted Total American and notified the company that the check did not satisfy the full amount of the lien. Gem State refused to grant a release or negotiate the check unless Total American agreed to pay Gem State’s attorney fees. Total American refused.

On October 14, 1999, the district judge denied Gem State’s and Chartrand’s cross-motions for summary judgment. After further discovery, the parties again filed cross-motions for summary judgment. On April 4, 2000, the district judge denied Gem State’s motion and granted Chartrand’s motion for -summary judgment, dismissing Gem State’s claim and declaring the lien void. On May 31, 2000, the district judge denied Chart-rand’s motion for attorney fees and costs. Gem State has appealed the grant of Chart-rand’s motion for summary judgment. Chartrand has cross-appealed, challenging the district judge’s denial of its motion for costs and attorney fees.

II.

STANDARD OF REVIEW

On appeal from the grant of a motion for summary judgment, this Court employs the same standard to be used by the district court originally ruling on the motion. Daugharty v. Post Falls Highway Dist., 134 Idaho 731, 733, 9 P.3d 534, 536 (2000). Summary judgment is proper “if the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” I.R.C.P. 56(c).

*742 When both parties file motions for summary judgment relying on the same facts, issues, and theories, essentially the parties stipulate that there is no genuine issue of material fact that would preclude the court from entering summary judgment. Daugharty, 134 Idaho at 733, 9 P.3d at 536. When the parties have so stipulated and when the trier of fact is to be the court, rather than a jury, the trial court is free to arrive at the most probable inferences based upon the evidence before it and grant summary judgment, despite the possibility of conflicting inferences. See Killinger v. Twin Falls Highway Dist., 135 Idaho 322, 324, 17 P.3d 266, 268 (2000); Brown v. Perkins, 129 Idaho 189, 191, 923 P.2d 434, 436 (1996); Riverside Dev. Co. v. Ritchie, 103 Idaho 515, 519, 650 P.2d 657, 661 (1982).

The parties both moved for summary judgment centering on whether Total American was an agent or a subcontractor, based on them respective interpretations of the facts and law relating to I.C. § 45-501, and the case was to be tried without a jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crow v. Crow
Idaho Court of Appeals, 2025
Jane Doe v. John Doe
560 P.3d 1140 (Idaho Court of Appeals, 2024)
State v. Head
Idaho Court of Appeals, 2023
Cannon v. Teel
Idaho Court of Appeals, 2023
Bettwieser v. Bettwieser
Idaho Court of Appeals, 2022
Peterson v. Gunderson
516 P.3d 1095 (Idaho Court of Appeals, 2022)
Watkins v. Idaho Transportation Department
Idaho Court of Appeals, 2022
Hepworth v. Hepworth
503 P.3d 216 (Idaho Court of Appeals, 2021)
Nicholson v. Bennett
Idaho Court of Appeals, 2020
State v. Kincaid, Jr.
443 P.3d 287 (Idaho Court of Appeals, 2019)
Ricks v. State of Idaho Contractors Bd.
Idaho Court of Appeals, 2018
Cuc Phuoc Ho v. State
Idaho Court of Appeals, 2017
Herrmann v. State, Idaho Transportation Department
403 P.3d 318 (Idaho Court of Appeals, 2017)
Joshua v. Hauser v. State
Idaho Court of Appeals, 2015
Stephen Boswell v. Amber Dawn Steele
348 P.3d 497 (Idaho Court of Appeals, 2015)
Keith A. Sims v. Dan S. Jacobson
342 P.3d 907 (Idaho Supreme Court, 2015)
ACI Northwest, Inc. v. Monument Heights, LLC
342 P.3d 618 (Idaho Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
40 P.3d 96, 136 Idaho 738, 2002 Ida. LEXIS 12, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-w-supply-corp-v-chartrand-family-trust-idaho-2002.