Pierson v. Sewell

539 P.2d 590, 97 Idaho 38, 1975 Ida. LEXIS 357
CourtIdaho Supreme Court
DecidedAugust 8, 1975
Docket11431
StatusPublished
Cited by49 cases

This text of 539 P.2d 590 (Pierson v. Sewell) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pierson v. Sewell, 539 P.2d 590, 97 Idaho 38, 1975 Ida. LEXIS 357 (Idaho 1975).

Opinions

McQUADE, Chief Justice.

This is an action to foreclose a mechanic’s lien. We affirm the judgment of the trial court insofar as it ordered the lien foreclosed. We find that the lien was timely filed and that the lien waiver signed by respondent was of no force or effect. However, we reverse the award of a deficiency judgment against appellants in the event that the proceeds of the foreclosure sale fail to satisfy respondent’s claim, and also reverse that portion of the decree granting respondent a personal judgment against appellants for the amount due for materials and labor supplied.

Appellants are the owners of real property in Blaine County. Respondent, working as a subcontractor, furnished labor and materials beginning in October 1971, in connection with the installation of a heating system in a dwelling being constructed on appellants’ property. The trial court found this work was done on a time and materials basis, computed by the lineal foot as the heating ducts were installed, this being customary in the trade.

During the construction of the dwelling, the general contractor, Butler Brothers, experienced financial difficulties. Subsequently, appellant Max Sewell had further progress payments to the general contractor withheld. In January 1972, Max Sew-ell requested from the various subcontractors, including respondent, lien waivers so that the lending institution would release the necessary funds. Each subcontractor executed a lien waiver. Respondent gave his lien waiver to appellant on January 13, 1972. The lending institution then disbursed the proceeds of the construction loan to the various subcontractors working on the dwelling with the exception of respondent. All the subcontractors were paid in full with the exception of respondent, who received nothing from the funds released by the lending institution. Respondent filed a notice of lien on March 9, 1972.

Several days after filing his notice of claim, respondent brought this cause of action to foreclose the lien. The trial court found that upon appellants’ discovery of the prime contractor’s financial difficulties, appellant Max Sewell assumed Butler Brothers’ obligations arising from the construction of the dwelling. The trial court found that Sewell requested a lien waiver from respondent, the consideration for which was to be payment in full. The trial court also found that the notice of claim of lien was filed in accord with statute and that it had not been cancelled or otherwise discharged and that $2,195.85 was due respondent for the work performed and the materials furnished. The trial court ordered the lien foreclosed to satisfy respondent’s claim, his attorney’s fees in the sum of $750.00 plus costs in the amount of $203.15. The court held appellants liable for any deficiency if the proceeds of the foreclosure sale were insuffi[41]*41cient to cover the amount due, plus attorney’s fees and costs. The trial court also allowed recovery of a personal judgment against appellants for the total amount awarded.

Appellant urges eleven assignments of error which can be summarized into three main issues:

(1) Did respondent file a valid and timely notice of claim of lien as a prerequisite for instituting this action;

(2) Did respondent waive his right to a claim of lien by execution of the lien waiver on January 13, 1972; and

(3) Are appellants subject to a personal judgment for the amount awarded?

Many of appellants’ assignments of error deal with factual findings made by the trial court. We re-affirm the rule many times stated, that the credibility of, and weight given to, the evidence presented at trial is exclusively the province of the trial judge when the court acts as finder of fact. Ivie v. Peck.1 It follows that findings of fact supported by substantial, competent, although conflicting, evidence will not be disturbed on appeal. Id.2

Mechanic’s and other related liens are creatures of statute, and statutory requirements must be substantially complied with in order to perfect a valid lien. Boone v. P. & B. Logging Company.3 Yet, these lien statutes are to be liberally construed: “The provisions of our mechanics’ and laborers’ lien law, as well as all other lien statutes, must be liberally construed with a view to effect their objects and promote justice.” Seafoam Mines Corp. v. Vaughn,4 The purpose of these statutes is to compensate persons who perform labor upon or furnish material to be used in the construction, alteration or repair of a building or structure. Boise Payette Lumber Co. v. Weaver.5

The evidence shows that respondent subcontractor contracted with the prime contractor, Butler Brothers, to install a heating system in the construction of appellants’ dwelling. As such, Pierson supplied materials and labor through his employees and, therefore, has by I.C. § 45-501 a right to a lien on the dwelling. To perfect that lien, a subcontractor, such as respondent, must file a notice of claim of lien within sixty days following the subcontractor’s cessation of labor or furnishing of materials. I.C. § 45-507.

Appellants first argue that the trial court erred in finding that respondent furnished labor and materials on January 14, 1972, in order to complete his subcontract in connection with the construction of appellants’ dwelling. They claim respondent’s employees completed their work on the dwelling in December 1971, and therefore, the lien was not timely filed. Upon examination of the record we find ample, competent, although conflicting evidence to support the trial court’s finding that respondent performed labor and supplied materials on January 14, 1972.

Assuming arguendo that respondent’s employees did furnish labor and materials on January 14, 1972, appellants argue that work was of a trivial nature not extending the time for the running of the lien. They argue that construction of the dwelling, including the heating system, was substantially completed in December, with the sixty-day period for filing a notice of claim [42]*42running from that time. Thus, the March 9, 1972, filing would be untimely.

We re-affirm the principle followed in Mitchell v. Flandro 6 that the sixty-day period for the filing of liens cannot be extended or revived by the furnishing of trivial labor or materials once the contract has been completed.

“Ordinarily, furnishing an article or performing a service trivial in character is not sufficient to extend the time for claiming a lien or to revive an expired lien, where the article is furnished or the service rendered after a substantial completion of the contract, and the article is not expressly required by the terms thereof.”"7

When additional material or labor is relied upon to extend the time for filing of the claim, the lien claimant must show that the materials or labor were actually used in constructing or repairing the structure, and that they were reasonably necessary to complete construction according to the terms of the contract.8

Evidence was presented to the effect that one of respondent’s employees spent a “good half day” installing registers, changing two air ducts and replacing the thermostat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ACI Northwest, Inc. v. Monument Heights, LLC
342 P.3d 618 (Idaho Supreme Court, 2015)
Terra-West, Inc. v. Idaho Mutual Trust, LLC
247 P.3d 620 (Idaho Supreme Court, 2010)
Evco Sound & Electronics, Inc. v. Seaboard Surety Co.
223 P.3d 740 (Idaho Supreme Court, 2009)
Franklin Building Supply Co. v. Sumpter
87 P.3d 955 (Idaho Supreme Court, 2004)
W.P. Barber Lumber Co. v. Celania
674 N.W.2d 62 (Supreme Court of Iowa, 2003)
L & W SUPPLY CORP. v. Chartrand Family Trust
40 P.3d 96 (Idaho Supreme Court, 2002)
Great Plains Equipment, Inc. v. Northwest Pipeline Corp.
979 P.2d 627 (Idaho Supreme Court, 1999)
Montane Resource Associates v. Greene
974 P.2d 510 (Idaho Supreme Court, 1999)
Bell v. Smith (In Re Smith)
232 B.R. 461 (D. Idaho, 1998)
Baker v. Boren
934 P.2d 951 (Idaho Court of Appeals, 1997)
Barth v. Canyon County
918 P.2d 576 (Idaho Supreme Court, 1996)
Inland Title Co. v. Comstock
779 P.2d 15 (Idaho Supreme Court, 1989)
Barber v. Honorof
780 P.2d 89 (Idaho Supreme Court, 1989)
Clement v. Farmers Insurance Exchange
766 P.2d 768 (Idaho Supreme Court, 1988)
Gilbert v. City of Caldwell
732 P.2d 355 (Idaho Court of Appeals, 1987)
Idaho Lumber, Inc. v. Buck
710 P.2d 647 (Idaho Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
539 P.2d 590, 97 Idaho 38, 1975 Ida. LEXIS 357, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pierson-v-sewell-idaho-1975.