Barber v. Honorof

780 P.2d 89, 116 Idaho 767, 1989 Ida. LEXIS 108
CourtIdaho Supreme Court
DecidedJune 28, 1989
Docket17631
StatusPublished
Cited by38 cases

This text of 780 P.2d 89 (Barber v. Honorof) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barber v. Honorof, 780 P.2d 89, 116 Idaho 767, 1989 Ida. LEXIS 108 (Idaho 1989).

Opinion

HUNTLEY, Justice.

This is an appeal by Frank and Carol Honorof (Honorof) from a judgment in favor of Jeff Barber (Barber) in an action to foreclose a materialman’s lien. We affirm the judgment of the trial court insofar as it ordered the lien foreclosed, dismissed Honorof’s counterclaim, and denied Barber’s request for prejudgment interest. However, we reverse and remand this case to the district court to determine Barber’s reasonable attorney fees.

Background of the Appeal

This action arose out of a contract dispute between Barber and Honorof respecting certain concrete work performed at the Honorofs’ residence. Frank and Carol Honorof are the owners of a home near Priest River, Idaho. Jeff Barber is an individual concrete finisher conducting business in the state of Idaho. In June 1984, Honorof hired Barber to perform concrete work on a number of projects through the summer and into the fall of 1984. Barber completed these project: and was paid for his work.

In November 1984, Barber and Honorof entered into the agreement that would subsequently be the subject of this litigation. The agreement called for Barber to supervise, place the forms, set the rebar, level to grade and finish the concrete for the Honorofs’ driveway. Neither party disputes that a contract existed in which Barber would pour and finish the concrete for the driveway, or that Honorof would pay him for those efforts. However, there was no discussion or agreement between the parties as to how much Honorof would pay or what price Barber would charge for this work.

Barber began work on 9 November 1984. Honorof purchased and supplied all the concrete material for the job while Barber poured and finished it. He completed work on 27 November 1984, pouring and finishing a total of 10,034 square feet of concrete. Upon completion of the work Barber presented a bill for services performed which reflected a charge of $.90 per square foot. Honorof refused to pay, asserting that the bill was excessive and inconsistent with what Barber had charged for those projects he had earlier completed.

Barber filed a claim of lien on 29 November 1984 for $12,602.60, and on 28 December 1984, he filed a complaint in district court seeking foreclosure of the lien in the amount of $11,675.60. Soon thereafter, Honorof filed a counterclaim alleging the concrete Barber had poured and finished had deteriorated because he poured it during inclement weather and this constituted a failure to perform in a good and workmanlike fashion in violation of the Idaho Consumer Protection Act. At the conclusion of trial, the district court held that Barber was entitled to an $8,291.00 judgment and entered judgment of foreclosure of his materialman’s lien in that amount. Contemporaneous with this determination, the court dismissed Honorofs’ counterclaim and disallowed Barber’s request for prejudgment interest and attorney fees.

I.

Materialman’s Lien

The well-established rule in Idaho is that materialman lien statutes are to be liberally construed so as to effect their objects and to promote justice. Chief Industries Inc. v. Schwendiman, 99 Idaho 682, 685, 587 P.2d 823, 826 (1978); Ross v. Olson, 95 Idaho 915, 917, 523 P.2d 518, 520 (1974); Pierson v. Sewell, 97 Idaho 38, 41, 539 P.2d 590, 593 (1975). The purpose of *769 these statutes is to compensate persons who perform labor upon or furnish material to be used in construction, alteration or repair of a structure. Pierson at 41, 539 P.2d at 593; Boise Payette Lumber Co. v. Weaver, 40 Idaho 516, 234 P. 150 (1925). As a materialman’s lien is a creature of statute, at least a “substantial compliance” with the requirements of the lien statutes is necessary for creation of a valid lien. Chief Industries Inc. at 685, 587 P.2d at 826; Layrite Prod. Co. v. Lux, 86 Idaho 477, 388 P.2d 105 (1964).

The evidence shows that Barber’s claim of lien, which was filed pursuant to I.C. § 45-501 et. seq., accurately described the property which was subject to the lien, was filed within the statutorily required ninety-day period since the furnishing of the last item of material or labor, and accurately reflected the owners of the property subject to the lien as Frank and Carol Honorof. In our opinion, Barber has substantially complied with the statutory requirements to create a valid lien.

Honorof argues that the claim of lien had a fatally defective description as to the dollar amount of the lien, and, therefore, there can be no valid lien and no foreclosure proceedings based upon a defective notice of claim. They assert that Barber’s claim of lien is invalid because it claimed an amount owing of $12,602.60, whereas the complaint seeking foreclosure was filed in the amount of $11,675.60, and the judgment ultimately awarded by the trial court upon which foreclosure was ordered was for $8,291.00. However, they fail to cite any legal authority to support this theory.

The fact that the amount on the notice of claim and the amount prayed for in the foreclosure complaint differ is not enough to render the lien invalid. The record shows that Barber contacted Honorof and made him aware that the $12,-602.60 figure on the notice of claim was an error and attempted to correct this by filing the complaint seeking foreclosure in the amount of $11,675.60, a figure Barber believed to be correct. When this case went to trial, however, it was held that $11,675.60 was not reasonable. The court felt that fair and reasonable compensation for the work performed was Barber’s out-of-pocket expenses plus a reasonable hourly rate, not $.90 per square foot as he had charged; thus, he was awarded $8,291.00, instead of the $11,675.60 claimed. Whereas the general purpose of I.C. § 45-501 et seq. is to compensate persons who perform labor and/or furnish materials for construction projects, the specific purpose of the claim of lien is to give notice and to provide the contractor with security until he is able to be compensated for his services. Compare Guyman v. Anderson, 75 Idaho 294, 271 P.2d 1020 (1954) (stating that “the lien is not provided as a penalty, but rather as security”).

As stated earlier, substantial compliance with the lien statutes is all that is required, not absolute accuracy. Chief Industries, Inc. v. Schwendiman, 99 Idaho 682, 685, 587 P.2d 823, 826 (1978). That is not to say that contractors are free to abuse the statutes by claiming an amount known to greatly exceed that which is truly owing. Such is not the case here, as Barber made a good faith effort to comply with the lien statutes. Therefore, in the absence of oppression or some other circumstances which would justify a court of equity denying foreclosure, there is no reason it should not be granted, even though Barber failed to establish his right to the full $11,675.60 and was ultimately awarded a lesser amount.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christopher W. James Trust v. Tacke
467 P.3d 389 (Idaho Supreme Court, 2020)
Michael L. Kelly v. Pamela Wagner
393 P.3d 566 (Idaho Supreme Court, 2017)
ACI Northwest, Inc. v. Monument Heights, LLC
342 P.3d 618 (Idaho Supreme Court, 2015)
Perception Construction Management, Inc. v. Bell
254 P.3d 1246 (Idaho Supreme Court, 2011)
Ross v. Ross
178 P.3d 639 (Idaho Court of Appeals, 2007)
Haselwood v. Bremerton Ice Arena, Inc.
137 Wash. App. 872 (Court of Appeals of Washington, 2007)
Franklin Building Supply Co. v. Sumpter
87 P.3d 955 (Idaho Supreme Court, 2004)
State, Department of Health & Welfare v. Roe
72 P.3d 858 (Idaho Supreme Court, 2003)
Sainsbury Const. Co., Inc. v. Quinn
47 P.3d 772 (Idaho Court of Appeals, 2002)
Electrical Wholesale Supply Co. v. Nielson
41 P.3d 242 (Idaho Supreme Court, 2001)
Poison Creek Publishing, Inc. v. Central Idaho Publishing, Inc.
3 P.3d 1254 (Idaho Court of Appeals, 2000)
Bouten Construction Co. v. H.F. Magnuson Co.
992 P.2d 751 (Idaho Supreme Court, 1999)
Hart v. Deary High School
887 P.2d 1057 (Idaho Supreme Court, 1994)
Olsen v. Frank
873 P.2d 1340 (Idaho Court of Appeals, 1994)
Mulch v. Mulch
867 P.2d 967 (Idaho Supreme Court, 1994)
Ervin Construction Co. v. Van Orden
874 P.2d 506 (Idaho Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
780 P.2d 89, 116 Idaho 767, 1989 Ida. LEXIS 108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barber-v-honorof-idaho-1989.