Datum Construction, LLC v. Re Investment Co.

CourtIdaho Supreme Court
DecidedDecember 18, 2023
Docket49708
StatusPublished

This text of Datum Construction, LLC v. Re Investment Co. (Datum Construction, LLC v. Re Investment Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Datum Construction, LLC v. Re Investment Co., (Idaho 2023).

Opinion

IN THE SUPREME COURT OF THE STATE OF IDAHO

Docket No. 49708

In the Matter of Petition for Release of ) Mechanic’s Lien. ) ) DATUM CONSTRUCTION, LLC, an Idaho ) limited liability company, ) Boise, June 2023 Term ) Petitioner-Respondent, ) Opinion filed: December 18, 2023 ) v. ) Melanie Gagnepain, Clerk ) RE INVESTMENT CO., LLC dba PRO ) RENTALS & SALES, ) ) Claimant-Appellant. ) )

Appeal from the District Court of the Fourth Judicial District of the State of Idaho, Ada County. Michael Reardon, District Judge.

The decision of the district court is reversed; its judgment is vacated.

Hahn Law Office, Idaho Falls, for Appellant. Frederick J. Hahn, III argued.

McConnell Wagner Sykes & Stacey, PLLC, Boise, for Respondent. Arnie Wagner argued.

BEVAN, Chief Justice. This appeal concerns the release of a mechanic’s lien bond following the district court’s finding that a foreclosure action had not been filed within six months under Idaho Code section 45-521. RE Investment Co., LLC, dba Pro Rentals & Sales (“Pro Rentals”) appeals from the district court’s judgment releasing the bond filed with the district court by Datum Construction, LLC (“Datum”). Pro Rentals argues that the district court erred in concluding that the bond should be released because Pro Rentals had not commenced an action to recover against the bond within six months. For the reasons discussed below, we reverse the district court’s decision.

1 I. FACTUAL AND PROCEDURAL BACKGROUND Datum was the general contractor on a commercial construction project in Star, Idaho. Datum subcontracted a portion of the work on that project to Elmore Welding and Steel. Elmore Welding and Steel then rented equipment for the project from Pro Rentals but failed to pay Pro Rentals for its use of the equipment. On March 31, 2021, Pro Rentals recorded a claim of lien in the amount of $38,997.91 with the Ada County Recorder on the Star project for the materials rented to Elmore Welding and Steel. On May 7, 2021, Datum purchased a bond from Harco National Insurance Company in the amount of $58,496.87, which was one and a half times the amount stated in the lien. Four days later, Datum petitioned to file the bond with the district court and release the lien under Idaho Code section 45-521. A copy of that petition was served on Pro Rentals. On May 26, 2021, the district court held a hearing on Datum’s petition. Pro Rentals did not appear at the hearing or otherwise oppose Datum’s petition. Later that same day, the district court issued an order releasing Pro Rentals’ lien, finding that the lien was released of record for all purposes and that the bond was subject to the claims that would otherwise constitute the claim of lien. On June 29, 2021, Pro Rentals moved to enforce liability of surety. Datum opposed Pro Rentals’ motion; however, Pro Rentals did not notice the motion for a hearing, and the district court did not issue an order on the motion. On October 8, 2021, Datum moved to release the bond, arguing that Pro Rentals had failed to begin proceedings to enforce its claim of lien within six months. A few hours later, Pro Rentals filed a motion for a thirty-day setting.1 Pro Rentals argued that the six-month limitation period applicable to mechanic’s liens did not apply to Pro Rentals’ claim against the bond. The district court issued an order granting Datum’s motion to release the bond, concluding that the bond served as substitute security for the property and did not otherwise alter the rights or obligations of the parties. Pro Rentals was thus required to enforce its claim of lien within the six- month period outlined in Idaho Code section 45-510. The district court found Pro Rentals had not done so, granted Datum’s motion, and entered a judgment releasing the bond. Pro Rentals timely appealed.

1 Idaho Code section 45-522 provides preferential settings for a lien claimant “against the lien claimant’s debtor and to join therein the surety on the bond[,]” within “thirty (30) days of” filing a demand for a thirty-day setting.

2 II. STANDARD OF REVIEW “This Court exercises free review over questions of law.” Chester v. Wild Idaho Adventures RV Park, LLC, 171 Idaho 212, 222, 519 P.3d 1152, 1162 (2022) (citing Latvala v. Green Enters., Inc., 168 Idaho 686, 695, 485 P.3d 1129, 1138 (2021)). “Interpretation of a statute is a question of law.” Id. (quoting Idaho Dep’t of Health & Welfare v. McCormick, 153 Idaho 468, 470, 283 P.3d 785, 787 (2012)). III. ANALYSIS A. The district court erred in construing Idaho Code section 45-510 to create a six-month statute of limitations to file an action on a bond. This case requires us to interpret two aspects of Idaho’s mechanic’s lien statutes. Idaho Code section 45-510(1) provides that no mechanic’s lien will bind any property for more than six months after it is filed unless proceedings have been commenced with the proper court within that time to enforce the lien. Idaho Code section 45-518 permits a mechanic’s lien to be released upon the posting of a surety bond in the manner provided in sections 45-519 through 45-524. In this case, Datum posted the bond, and the district court released the lien. Datum later moved the district court to release the bond when Pro Rentals did not commence an action within six months of filing the lien. Relying on this Court’s decision in American Bank v. Wadsworth Golf Construction Co. of the Southwest, 155 Idaho 186, 307 P.3d 1212 (2013), the district court granted Datum’s motion, applying the six-month statute of limitations set forth under Idaho Code section 45-510. 1. Idaho Code section 45-510 is inapplicable to this dispute because Pro Rentals’ lien was released for all purposes. This matter requires us to apply statutory construction to various sections of Chapter 5, Title 45 of the Idaho Code. Two separate parts of this chapter are at play: the Idaho mechanic’s lien provisions found in Idaho Code sections 45-510 through 45-517, and the Idaho mechanic’s lien bond provisions (also known as the “bond around” provisions) found at Idaho Code sections 45-518 through 45-524. The mechanic’s lien provisions were originally adopted as part of Idaho’s General Laws in 1893. The mechanic’s lien bond provisions were added by the Idaho Legislature in 1993. See Act of Apr. 1, 1993, ch. 378, 1993 IDAHO SESS. LAWS 1386–92.2 Datum argues that Idaho Code section 45-510 applied to limit Pro Rentals’ claims against the bond. Datum maintained below and on appeal that section 45-510 creates a statute of limitations within which Pro Rentals had to file a foreclosure action. We disagree. If it were the legislature's intent that

3 Idaho Code section 45-510 should be the statute of limitations for the bond around statute, it should have done so with more clarity. “The interpretation of a statute must begin with the literal words of the statute; those words must be given their plain, usual, and ordinary meaning; and the statute must be construed as a whole.” Verska v. Saint Alphonsus Reg’l Med. Ctr., 151 Idaho 889, 893, 265 P.3d 502, 506 (2011). “If the statute is not ambiguous, this Court does not construe it, but simply follows the law as written.” Id. (quoting State v. Schwartz, 139 Idaho 360, 362, 79 P.3d 719, 721 (2003)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Verska v. Saint Alphonsus Regional Medical Center
265 P.3d 502 (Idaho Supreme Court, 2011)
KGF DEVELOPMENT, LLC v. City of Ketchum
236 P.3d 1284 (Idaho Supreme Court, 2010)
Idaho Department of Health & Welfare v. McCormick
283 P.3d 785 (Idaho Supreme Court, 2012)
American Bank v. Wadsworth Golf Construction Co.
307 P.3d 1212 (Idaho Supreme Court, 2013)
Barber v. Honorof
780 P.2d 89 (Idaho Supreme Court, 1989)
Kepler v. Slade
896 P.2d 482 (New Mexico Supreme Court, 1995)
Metropolitan Life Insurance v. First Security Bank
491 P.2d 1261 (Idaho Supreme Court, 1971)
Willes v. Palmer
298 P.2d 972 (Idaho Supreme Court, 1956)
RTC v. Berman Industries
637 A.2d 1297 (New Jersey Superior Court App Division, 1993)
Central Penn Nat'l Bank v. Stonebridge Ltd.
448 A.2d 498 (New Jersey Superior Court App Division, 1982)
BMC West Corp. v. Horkley
174 P.3d 399 (Idaho Supreme Court, 2007)
State v. Schwartz
79 P.3d 719 (Idaho Supreme Court, 2003)
Hamilton Ex Rel. Hamilton v. Reeder Flying Service
21 P.3d 890 (Idaho Supreme Court, 2001)
Franklin Building Supply Co. v. Sumpter
87 P.3d 955 (Idaho Supreme Court, 2004)
L & W SUPPLY CORP. v. Chartrand Family Trust
40 P.3d 96 (Idaho Supreme Court, 2002)
Johnson v. Boundary School Dist. No. 101
63 P.3d 457 (Idaho Supreme Court, 2003)
Saint Alphonsus Regional Medical Center v. Elmore County
350 P.3d 1025 (Idaho Supreme Court, 2015)
ACI Northwest, Inc. v. Monument Heights, LLC
342 P.3d 618 (Idaho Supreme Court, 2015)
Seafoam Mines Corp. v. Vaughn
53 P.2d 1166 (Idaho Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
Datum Construction, LLC v. Re Investment Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/datum-construction-llc-v-re-investment-co-idaho-2023.