American Bank v. Wadsworth Golf Construction Co.

307 P.3d 1212, 155 Idaho 186, 2013 WL 4398861, 2013 Ida. LEXIS 254
CourtIdaho Supreme Court
DecidedAugust 16, 2013
Docket39415
StatusPublished
Cited by10 cases

This text of 307 P.3d 1212 (American Bank v. Wadsworth Golf Construction Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Bank v. Wadsworth Golf Construction Co., 307 P.3d 1212, 155 Idaho 186, 2013 WL 4398861, 2013 Ida. LEXIS 254 (Idaho 2013).

Opinion

HORTON, Justice.

This appeal relates to a mechanic’s lien filed against the Black Rock North Development in Coeur d’Alene, Idaho, arising from an uncompleted golf course community development. American Bank (the Bank) was the lender to BRN Development, Inc. (BRN). BRN hired Wadsworth Golf Construction Company of the Southwest (Wadsworth) to construct a golf course. BRN failed to pay Wadsworth for a portion of the work it performed, and Wadsworth filed a mechanic’s lien against the property. BRN defaulted on the loan, and the Bank initiated foreclosure proceedings. Wadsworth’s claim of lien was subordinate to the Bank’s mortgage interest in the property. In order to proceed with a foreclosure sale, the Bank posted a lien release bond in order to secure the district court’s order releasing Wadsworth’s lien. The Bank’s credit bid was sufficient to make it the successful bidder at the foreclosure sale.

The district court ruled that priority of the parties’ claims against the property was irrelevant once the property was replaced by the lien release bond as security for Wads-worth’s claim and the Bank (by way of the bond) was responsible for payment of Wads-worth’s lien claim.

The Bank appeals the decision of the district court, arguing that Wadsworth should have been prevented from recovering against the lien release bond because its interest would have been extinguished if it had attempted to foreclose its mechanic’s lien and the bond merely served as substitute security in place of the property. The Bank further argues that Wadsworth should have been barred from recovery because it was not registered under the Idaho Contractor’s Registration Act (ICRA) at all times it worked on the project and it hired subcontractors who were likewise unregistered. Wadsworth cross-appeals, arguing the district court erred in holding that Wadsworth waived its right to file a lien for the unpaid retainage on the contract. Wadsworth also argues that it is entitled to additional attorney’s fees for the proceedings in district court and attorney fees on appeal.

I. FACTUAL AND PROCEDURAL BACKGROUND

BRN planned to develop a high-end residential golf course community. The golf course, a central feature of the development, was situated on two hundred acres in the thousand-acre development. BRN entered into a financing agreement with the Bank in which the Bank agreed to loan BRN $15,000,000 for the development of the project. The Bank recorded its mortgage on February 6, 2007. The loan documents specified that the Bank had a first priority mortgage on the property and required BRN to certify that it had received lien waivers from any person or entity that had provided labor or materials on the project before loan funds for progress payments would be disbursed.

BRN then hired Wadsworth to construct the golf course. Wadsworth began work in *189 2006, shaping two holes of the course from October through December before it was forced to suspend work due to weather conditions. This work was done before a final contract was executed, as Wadsworth relied on a conditional letter of intent as it negotiated the final contract with BRN. Wadsworth was not registered under the ICRA at this time. Wadsworth registered under the ICRA on January 9, 2007, prior to its executing the final contract with BRN on January 27, 2007. The final contract provided that Wadsworth would be paid $9,796,938 for its work on the golf course construction.

Under the contract, Wadsworth was entitled to monthly progress payments for work performed and materials supplied. The contract specified that five percent of the progress payments would be withheld as retain-age to ensure Wadsworth’s completion of any required warranty work. In order to receive these monthly progress payments, Wads-worth was required to submit “in a form satisfactory to [BRN], partial lien releases____” The contract incorporated several documents by reference that were attached as exhibits. One of these documents was entitled “Exhibit ‘B’: Conditional Lien Waiver, Release, and Subordination” (the BRN Release). The BRN Release waived any right to lien the property for work performed or materials furnished through the date of receipt of the progress payment. During the course of its work on the project, Wadsworth submitted twenty-five progress payment applications to BRN. All but six of those applications were accompanied by a partial lien release in a form prepared by Wadsworth (the Wadsworth Release), rather than the BRN Release. The most significant difference between those forms was that the Wadsworth Release did not waive Wads-worth’s right to lien for unpaid retainage while the BRN Release did.

BRN defaulted on its loan. Prior to the default, BRN’s last progress payment to Wadsworth covered all work performed and materials supplied through July 31, 2008. The last lien release executed by Wadsworth covered work through August 31, 2008, but Wadsworth did not receive a complete progress payment. Both of these payment applications were accompanied by a Wadsworth Release. Wadsworth’s last payment application that was accompanied by a BRN Release was submitted on March 10, 2008.

On January 6, 2009, Wadsworth filed a claim of lien, asserting that it had provided $2,329,439.72 worth of work and materials for which it was not paid. This sum included retainage that had been withheld since the beginning of the project totaling $343,985. On April 1, 2009, the Bank initiated a foreclosure action, naming Wadsworth as a defendant in order to establish the priority of its lien. Wadsworth counterclaimed, asserting that its mechanic’s lien was prior and superi- or to the mortgage. In order to clear the way for a foreclosure sale of the property, the Bank purchased a Release of Mechanic’s Lien Bond (the lien release bond). Upon the Bank’s motion, the district court released Wadsworth’s mechanic’s hen against the property in accordance with I.C. § 45-521.

Both parties moved for partial summary judgment. The Bank argued that it was entitled to judgment as a matter of law because its superior priority prevented Wads-worth from recovering against the lien release bond. The district court denied the Bank’s motion and granted Wadsworth’s motion. The district court concluded as a matter of law the issue of priority of the parties’ interests in the property was irrelevant to Wadsworth’s right of recovery against the lien release bond.

Following its order granting Wadsworth’s motion for partial summary judgment, the district court entered an order establishing the amount BRN owed the Bank and directing that the property be sold. At the May 19, 2011, foreclosure sale, the Bank was the highest bidder with its credit bid of $18,682,767.78. This sum represented the balance BRN owed the Bank, costs of sale, sheriffs fees and receiver’s fees. Thus, the sale left no surplus proceeds for junior lien-holders.

The district court conducted a two-day bench trial in early May of 2011 in order to determine the validity of Wadsworth’s lien and the amount Wadsworth was entitled to recover. In its Findings of Fact and Conclusions of Law entered after the foreclosure *190 sale, the district court held that Wadsworth’s lien was valid and awarded Wadsworth $1,845,697.78 in principal, $371,368.82 in prejudgment interest, and $208,417.47 in costs and attorney fees, for a total judgment of $2,425,484.07.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pizzuto v. IDOC
508 P.3d 293 (Idaho Supreme Court, 2022)
American Bank v. BRN Dev. & Taylor Eng.
358 P.3d 762 (Idaho Supreme Court, 2015)
Saint Alphonsus Regional Medical Center v. Elmore County
350 P.3d 1025 (Idaho Supreme Court, 2015)
2 Ton Plumbing, L.L.C. v. Thorgaard
2015 UT 29 (Utah Supreme Court, 2015)
Bonner County v. Cunningham
323 P.3d 1252 (Idaho Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
307 P.3d 1212, 155 Idaho 186, 2013 WL 4398861, 2013 Ida. LEXIS 254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-bank-v-wadsworth-golf-construction-co-idaho-2013.