Smith v. Faris-Kesl Construction Co.

150 P. 25, 27 Idaho 407, 1915 Ida. LEXIS 78
CourtIdaho Supreme Court
DecidedMarch 27, 1915
StatusPublished
Cited by74 cases

This text of 150 P. 25 (Smith v. Faris-Kesl Construction Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Faris-Kesl Construction Co., 150 P. 25, 27 Idaho 407, 1915 Ida. LEXIS 78 (Idaho 1915).

Opinions

MORGAN, J.

— This action was commenced to foreclose a mechanic’s lien claimed by the respondent against the main ditch and canal of the Canyon Canal Company, Limited, for work and labor done and performed by respondent as a subcontractor in the construction thereof. The appellant, Faris-Kesl Construction Company, was the original contractor and was made a defendant with a view to obtaining a personal judgment against it.

Subsequent to the commencement of the action and prior to the trial in the district court, the appellant, Emmett Irrigation District, became the successor in interest to the said Canyon Canal Company and was substituted for it as a defendant.

It is alleged in the- complaint that the amount of excavating, grading, filling and clearing of land done and completed [415]*415by respondent under said contract was as follows: Embankment, 15,118 cubic yards; earth excavation, 37,450 cubic yards; gravel excavation, 5,670 cubic yards; loose rock excavation, 41,361 cubic yards; solid rock excavation, 35,959 cubic yards; clearing of sage-brush, 25.09 acres. That the amount of the contract price for such labor was $48,198.38, and that no part thereof has been paid except $30,641.87, and that there is now due under the terms of said contract the sum of $17,581.51, in which amount, together with interest thereon, costs and attorneys’ fees, the respondent asked for judgment; also that the lien be foreclosed and the canal be sold to satisfy said judgment.

The appellant construction company in its amended answer admitted the execution of the contract and denied, among other things, that the excavating or grading or filling or clearing of land done or completed under said contract were in the amounts alleged in the complaint or were in any other amount or amounts than as follows: Embankment, 15,118 cubic yards; earth excavation, 65,479 cubic yards; gravel excavation, 6,352 cubic yards; loose rock excavation, 24,468 cubic yards; solid rock excavation, 23,361 cubic yards; clearing of sage-brush, 29.95 acres; force account, $15.00. Said appellant also denied that the amount of the contract price for said labor performed by respondent under said contract was $48,198.38, or any other amount or sum other than the sum of $36,037.82, and denied that the amount paid to respondent was the sum of $30,641.87, and alleged the fact to be that said appellant had paid to said respondent the sum of $33,856.26, and denied that there was due or owing to the respondent under said contract the sum of $17,581.51 or any other sum or amount or at all except the sum of $5,386.02. Upon the trial of this cause in the district court the parties stipulated that the appellant construction company, had paid to the respondent, upon the contract and for work performed by him thereunder, the sum of $30,720.25.

A number of other issues were presented by said complaint and amended answer and the appellant, Emmett Irrigation District, also answered, adopting the allegations of the appel[416]*416lant construction company heretofore referred to, except as to the ownership of the property, and presenting additional issues which will, in so far as necessary to a determination of the questions presented by this appeal, be hereinafter discussed.

' The trial court found the amount of excavating, grading, filling and clearing of land done and completed by respondent under said contract to be as follows:

Clearing of sage-brush, 29.95 acres......$ 119.80
Embankment, 15,118 yards at 110 per yard .................................. 1,662.98
Earth excavation, 51,056 yards at 11^ per yard............................. 5,616.16
Gravel excavation, 5,931 yards at 150 per yard............................. 889.65
Loose rock excavation, 32,687 yards at 2>5‡ per yard.......................... 11,440.45
Solid rock excavation, 29,986 yards at 750 per yard.......................... 22,489.50

That respondent was entitled to receive under the terms of said contract the sum of $42,218.54; that he had received $30,720.25 thereof, and that there was a balance due and unpaid thereon of $11,498.29, together with interest thereon at the rate of 7% per annum, which interest up to April 9, 1913, amounted to $5,231.72. The trial court also found $900 to be a reasonable amount to be allowed to respondent as attorneys’ fees for the foreclosure of the lien, and, as a conclusion of law, found that respondent was entitled to recover from Faris-Kesl Construction Company said sums of money; also that respondent was entitled to a lien upon the property described in his complaint for the sum of $17,630, and that he was entitled to a decree foreclosing the same. Said lien to be subject and subordinate only to the lien of the first mortgage bonds in the amount of $350,000, secured by a trust deed executed by Canyon Canal Company to the American Trust & Savings Bank, dated June 15, 1905, and that if any deficiency should arise upon the sale the respondent should have a judgment against Faris-Kesl Construction Company for the [417]*417amount of such deficiency. Judgment and decree were entered in accordance with the findings of fact and conclusions of law, from which judgment and decree appeals have been taken by Faris-Kesl Construction Company and Emmett Irrigation District. An appeal was also taken by said appellants from an order denying their motion to strike from the files respondent’s memorandum of costs and disbursements in said ease. All of said appeals were heard together.

It will be observed that no great difference exists between the parties as to the amount of material handled by respondent in the construction of said canal, but that one of the principal differences between them grows out of the classification of the materials so handled. The evidence consisted of the testimony of a number of expert witnesses who gave the results of their estimates of the amount of earth, gravel, loose rock and solid rock removed. There is a broad discrepancy between the testimony of the witnesses for the appellants and those for the respondent upon this point, and the trial court did not adopt the estimates of either of them, but found, with respect to each class of material, more than estimated by the witnesses for one party and less than estimated by those for the other. This is assigned as error by the appellant, Faris-Kesl Construction Company, and it is 'urged that the findings of the trial court- were arbitrary, that no witness testified to such amounts, and that the court should have adopted the estimates of some of the witnesses as to the classification.

Certain cases were cited in support of this contention by said appellant, but they do not appear to be in point, in that in each of the cases cited the facts are susceptible of definite proof, while in this case the proof upon this point consists entirely of the testimony of expert witnesses to their estimates and the results thereof. It cannot be claimed for this class of testimony that it is accurate; the most that can be said for it is that it is approximate, and this is the best evidence of which a case of this nature is susceptible, for the classification of the different kinds of material removed from [418]*418a canal may be, and in this case was, the subject of difference of opinion between expert witnesses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montierth v. Dorssers
539 P.3d 578 (Idaho Supreme Court, 2023)
Benz v. D.L. Evans Bank
268 P.3d 1167 (Idaho Supreme Court, 2012)
Oldcastle Precast, Inc. v. Parktowne Construction, Inc.
128 P.3d 913 (Idaho Supreme Court, 2005)
Electrical Wholesale Supply Co. v. Nielson
41 P.3d 242 (Idaho Supreme Court, 2001)
Billman v. Equities Corporation
743 F.2d 1021 (Third Circuit, 1984)
Billman v. V.I. Equities Corp.
743 F.2d 1021 (Third Circuit, 1984)
Meridian Bowling Lanes, Inc. v. Meridian Athletic Ass'n
670 P.2d 1294 (Idaho Supreme Court, 1983)
Collins v. Stockwell
671 P.2d 415 (Court of Appeals of Arizona, 1983)
Acoustic Specialties, Inc. v. Wright
651 P.2d 529 (Idaho Supreme Court, 1982)
Hogan v. Hermann
623 P.2d 900 (Idaho Supreme Court, 1980)
Accessory Sales, Inc. v. Bedient
523 P.2d 38 (Idaho Supreme Court, 1974)
Finucane v. Village of Hayden
384 P.2d 236 (Idaho Supreme Court, 1963)
Page v. Noland
379 P.2d 661 (Idaho Supreme Court, 1963)
Mountain Home Irrigation District v. Duffy
319 P.2d 965 (Idaho Supreme Court, 1957)
Skillern v. Ward
317 P.2d 1050 (Idaho Supreme Court, 1957)
Ward v. Smith
86 S.E.2d 539 (West Virginia Supreme Court, 1955)
Guyman v. Anderson
271 P.2d 1020 (Idaho Supreme Court, 1954)
Aviation Industries v. East and West Ins. Co.
211 P.2d 156 (Idaho Supreme Court, 1949)
Stilwell v. Weiser Iron Works, Inc.
157 P.2d 86 (Idaho Supreme Court, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
150 P. 25, 27 Idaho 407, 1915 Ida. LEXIS 78, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-faris-kesl-construction-co-idaho-1915.