Spaulding v. Coeur D'Alene Railway & Navigation Co.

51 P. 408, 5 Idaho 528, 1897 Ida. LEXIS 53
CourtIdaho Supreme Court
DecidedNovember 26, 1897
StatusPublished
Cited by17 cases

This text of 51 P. 408 (Spaulding v. Coeur D'Alene Railway & Navigation Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spaulding v. Coeur D'Alene Railway & Navigation Co., 51 P. 408, 5 Idaho 528, 1897 Ida. LEXIS 53 (Idaho 1897).

Opinion

SULLIYAN, C. J.

The appellant, the Coeur D'Alene Eailway and Navigation Company (a corporation), entered in[531]*531to a contract with William L. Spaulding, the respondent, on the ninth day of August, 1886, by the terms of which respondent agreed to construct a line of railway from Old Mission, in Kootenai county, to Wardner Junction, in Shoshone county — a distance of about fourteen miles. The work of grading was to be completed, under the terms of said contract, by the tenth day of October, 1886. Work was commenced about the 20th of August — a few days after said contract was entered into. Prior to entering into said contract, appellant’s chief engineer furnished an approximate estimate, upon which bids were offered. In said estimate, the quantity of solid rock to be removed was placed at eight thousand cubic yards. In the final estimate made by appellant’s engineer, the trial court allowed respondent for eighteen thousand yards of solid rock. The approximate estimate of the cost of said road, upon which the rival contractors made their bids, was $35,000, while it is admitted by appellant’s engineers that said road cost over $73,528.98. These facts are stated to show that the work in constructing said road, and its cost, were more than double the estimates made by appellant’s chief engineer. Tinder the terms of said agreement, respondent was to receive nineteen and one-third cents per cubic yard for all earth work, fifty-five cents per cubic yard for all loose rock work, one dollar and twenty-five cents per cubic yard for all solid rock work, and for laying track, including surfacing roadbed and laying ties, $300 per mile, and to have said work all done by October 15, 1886. Also, approximate estimates of the work done under the contract were to be made at the end of each calendar month by the chief engineer of the company, or his assistants, and payments thereon to be made on the fifteenth day of the next ensuing month, less previous payments, and less fifteen per cent of the amount of each monthly estimate, until the completion of the contract. Under the specifications attached to said contract, it is stipulated that grading shall include earth, loose rock, and solid rock; and the terms “loose rock” and “solid rock” and “earth” are defined. “Earth” is defined as follows: “All materials, of whatever nature, including boulders measuring less than one cubic foot, and loose sand rock, slate and shale, which can be excavated with picks, shall be estimated and eon-[532]*532sidered earth, and under tbe bead of Excavation’ or ‘embankment/ as the case may be.” The August estimate was made and received by Spaulding* and payment thereon made on the 15th of September. The September estimate was also made, and payment thereunder was made on the 15th of October. The work was not completed by the 15th of said month, as stipulated in the contract. In fact, it was not completed prior to December 24, 1886, at which time Mr. Spaulding quit the work. The track had been laid, and cars run over said line of road, but all of the work stipulated to be done under said contract had not been done. No monthly or other estimates were furnished the contractor after the September estimate. The suit was not brought on the contract, but on a quantum meruit. The complaint alleges numerous violations of the contract, such as the failure to make monthly estimates and payments; to clear the right of way of timber, brush, and stumps as rapidly as it should have been done; to furnish grade and finishing stakes when needed; to supply the track layers with iron — all of which, it is alleged, caused great delay in the construction of said road, and made it impossible for respondent to complete said road within the time stipulated in said contract, or before the fall and winter storms set in, and which storms greatly retarded said work. It also alleges that the engineer of appellant was incompetent and unfair, and that his estimates and classifications were unjust, incorrect and unreliable. The answer denies the allegations of the complaint, and sets up a counterclaim, and demands judgment for $21,411.85. The cause was tried by the court, and judgment entered in favor of the plaintiff. This appeal is from the judgment and the order overruling the motion for a new trial. Six errors are assigned. They will be taken up and disposed of in their order:

1. The first is that the court erred in finding that the contract was as set forth in the third finding of fact. The point made is that the contract had certain specifications attached to it, which constituted an essential part of it, and were not included in said finding. The error is harmless. If the contract-had been omitted from the finding of facts altogether, the case [533]*533could not be affected thereby. ■ This action is not brought on said contract.

2. The second error specified is as follows: “The court erred in its finding that defendant’s failure to furnish relief under a November estimate was not due to the fault, negligence, or connivance of plaintiff.” This finding is clearly sustained by the evidence. The evidence also shows that defendant’s failure to furnish.said estimates, and to make payment thereunder, resulted very disastrously to the plaintiff. The plaintiff in no manner prevented the defendant from performing the matters and things it had stipulated to do.

3. “The court erred in finding the total estimates and classifications made by plaintiff’s engineers are right.” We have reviewed the evidence upon the points involved in this finding, and think the finding fully sustained. The engineers who made the estimates are shown to be very competent in their line of work, and plaintiff should not be required to suffer because there was some conflict of testimony touching the ability of the engineers to make accurate estimates. If the estimates were not correct, the defendant should have shown it. If its engineers had made accurate estimates of the work done by the respondent — and it is reasonable to presume they did — it certainly was in a position to show with accuracy the amount of the various classes of material removed, the fills made, and the other work done by the appellant. Instead of putting their engineers on the witness-stand for that purpose, its main effort appears to have been directed to show that work had been done on the road after plaintiff quit the job, and, because of such work having been done, respondent’s engineers could not estimate to a certainty the exact number of yards of grading done by respondent. The rule is well established that if the party possesses peculiar knowledge of evidentiary facts, which the other party claims would, if brought forward, tend to sustain his' claim, and if the party so possessed fails to bring forward the facts which it is shown can be produced by him alone, a presumption arises in favor of his adversary’s claim. (5 Am. & Eng. Eney. of Law, 2d ed., 41, and authorities there cited.)

[534]*5344. “The court erred in finding that the estimates and classifications made by appellant’s engineers were wrong.” It appears from the evidence that the estimates and classifications made by appellant’s engineers were incorrect and unjust. The evidence shows that the chief engineer of appellant was partial and incompetent, was wrong in his estimates and unjust in his classifications, and was influenced and controlled by appellant’s president and agents to such an extent as to make him totally unfit to act as an impartial umpire between the parties to said contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pickerd v. Dahl
127 P.2d 759 (Idaho Supreme Court, 1942)
Pierson v. Pierson
115 P.2d 742 (Idaho Supreme Court, 1941)
Idaho Power Co. v. City of Buhl
111 P.2d 1088 (Idaho Supreme Court, 1941)
State v. Snoderly
101 P.2d 9 (Idaho Supreme Court, 1940)
Hansen v. Independent School District No. 1
98 P.2d 959 (Idaho Supreme Court, 1939)
Weeter v. Reynolds
284 P. 257 (Idaho Supreme Court, 1930)
Walbridge-Aldinger Co. v. Rudd
26 F.2d 636 (Eighth Circuit, 1928)
Elson v. Jones
245 P. 95 (Idaho Supreme Court, 1926)
Choate v. North Fork Highway District
228 P. 885 (Idaho Supreme Court, 1924)
Griffith v. Dowd
158 N.W. 420 (Supreme Court of Minnesota, 1916)
Smith v. Faris-Kesl Construction Co.
150 P. 25 (Idaho Supreme Court, 1915)
Northern Pacific Railway Co. v. Boyd
228 U.S. 482 (Supreme Court, 1913)
Northern Pac. Ry. Co. v. Boyd
177 F. 804 (Ninth Circuit, 1910)
Boyd v. Northern Pac. Ry. Co.
170 F. 779 (U.S. Circuit Court for the District of Eastern Washington, 1909)
Nelson Bennett Co. v. Twin Falls Land & Water Co.
93 P. 789 (Idaho Supreme Court, 1908)
Spaulding v. Coeur D'Alene Railway & Navigation Co.
59 P. 426 (Idaho Supreme Court, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
51 P. 408, 5 Idaho 528, 1897 Ida. LEXIS 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spaulding-v-coeur-dalene-railway-navigation-co-idaho-1897.