Herrick v. Estate of Belknap

27 Vt. 673
CourtSupreme Court of Vermont
DecidedNovember 15, 1854
StatusPublished
Cited by50 cases

This text of 27 Vt. 673 (Herrick v. Estate of Belknap) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herrick v. Estate of Belknap, 27 Vt. 673 (Vt. 1854).

Opinion

The opinion of the court was delivered, at the April Term, 1855, by

Redfield, Ch. J.

This being a bill brought to obtain payment for work done on the Vermont Central Railroad, beyond, or aside of the estimates of the engineers; and the contract, by which the company let the work to Belknap,, and also that by which he under-let a portion of it to the plaintiff, containing a provision, in these words, “ and the engineer shall be the sole judge of the quality and “ quantity of the work, and from his decision there shall be no ap- peal,” the recovery can scarely be claimed upon any other but one of two grounds; 1, that the engineers, without the fault of the plaintiff, have failed to make an estimate within the fair import of the contract; or, 2, that having made one, it is so erroneous, as not to be binding upon the parties, under the contract.

We think there can be no question that this stipulation does bind the parties to abide the decision of the arbitrator named, as much as that of any other umpire or arbitrator. And, in one sense, the submission to the determination of the engineer is more obligatory than any ordinary submission, inasmuch as being upon consideration, it is not revocable, and the obligation upon the defendants to pay, does not, by the terms of the contract, arise, until the [680]*680estimates are made by the engineers. But, this being a peculiar species of contract, so far as the umpirage is concerned, that being referred to the agents and servants of one of the contracting parties, persons in the employ, under the control, and in the pay of that party, it seems, from necessary implication, to impose upon that party the obligation to employ competent, upright, trustworthy persons, in this service, — and to see to it, that they did this service in the proper time, and in the proper manner. And these estimates, when made, are, no doubt, entitled to the common presumption in their favor, omnia rite acta. But, being of a nature where perfect accuracy is attainable, or nearly so, and madé by a class of persons altogether in the interest and under the control of oiie of the contracting parties, it would impose, doubtless, some duty of watchfulness, as to the persons employed, and, also, in regard to abstaining from all attempts, mediately or immediately, at influencing them in their action in the premises. And, while it is undeniable that a full and fair decision of the engineer is as binding as any other award of an arbitrator, and practically, (on account of the vast extent of the work, and the vital necessity of the company and the contractors knowing, as they go along, how they stand, and closing their accounts from time to time, beyond the necessity of revision,) more emphatically entitled to exemption from reexamination, upon slight or factitious grounds. Still, it must be apparent that, in the matter of proof, the decision of such an arbitrator, when brought before a judicial tribunal for revision, as they are always liable to be, are exposed to more watchfulness, and carefulness of examination upon those points where, from the nature of the case, they are exposed to peculiar liability to infirmity. No fair mind, competent for such an examination, could fail to perceive this. But this surely will not justify any court in setting aside such a determination, upon any but the most unanswerable grounds. It must be obvious to all, that, the parties must have felt the necessity of such an umpirage, or they would not have provided for it, — and that, having provided for it, by the express stipulations of them contract, they must now abide by it, and not expect a court of equity to relieve them from the probable consequence of them contract, however disastrous it may possibly have proved, to them reasonable or unreasonable anticipations.

[681]*681I. We think it is not the fair interpretation of this contract, that all these estimates were to be made by the chief engineer. Contracts must be construed with reference to the subject matter, and made, as far as is consistent with the terms used, reasonable and just. One altogether unacquainted with the matter of such extensive works, from the word engineer being used, in the singular number, would, almost of necessity, conclude it must have had reference to the chief engineer alone, else the word would have been written in the plural, as applicable to the several resident or assistant engineers. But when we come to know that, practically, the chief engineer never does, and never can, make these estimates, or even verify those made by others, — that the thing is altogether impracticable, — we must conclude that the parties had reference to something which was usual, or, at least, possible, in such cases. And this, we find to be the estimate of the engineer having charge of the section, who is called the resident engineer. And this meets the terms of the contract, as well as by referring it exclusively to the action of the chief engineer.

We need, perhaps, spend no time upon the question, what would be the rights of the defendants, if no estimates of the plaintiff’s work had been made by the company’s engineer. For the plaintiff bases his claim upon no such state of facts, and he cannot expect to recover upon a case not made in his bill. If the plaintiffs work had failed to be estimated, through the fault of the engineer, or the company, or Belknap, it does not now occur to me that there would probably be any difficulty in obtaining a recovery, at law.

But, the case which the plaintiff makes, in his bill, is, that the estimates were made regularly, but made intentionally too low, and improperly made. 1. It is charged that the chief engineer, at no time, made the estimates, as he should have done, but allowed them to be made by one Collins, in the latter portion of the time the plaintiff worked, who is called a sub-engineer, in the bill. 2. That before March 24, the plaintiff supposed the estimates correct, “ but “from subsequent discoveries, is led to believe that these are some- “ what too small, and were not as accurately made as they should “ have been.” This could scarcely be regarded as any charge of fraud or mistake in these estimates, or as any ground of claim against Belknap. But, 3d, it is charged, or stated, that the esti[682]*682mates after this date, which are all set out, amounting to 44,416 yards of earth and 608 yards of rock excavation, are, in terms, “only about one-half what they should have been, were hasty, “ careless and incomplete, and operated as a great and gross fraud “'and damage upon and to your orator.” It is further charged, that these estimates were so made, by the connivance of Belknap, “ for his own relief,” in making monthly payments, and “ to embarrass the orator, and, cause his failure.” 4. There is a charge, too, in the bill, that the orator was not allowed to work at the most profitable portion of his section, but this is abandoned on trial. 5. In a supplement to the bill, or amendment, the plaintiff claims for removing loose rock, in the pit left by Barker & Haight, which he claims to have been 600 yards, at sixty cents. 6. That, contrary to his expectation when he entered into the contract, he was compelled to excavate about 300 yards of rock, under these loose stone, and near the grade of the road, which cost about twice as much as the ordinary rock excavation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Smith v. District Court of Osage County
1941 OK 128 (Supreme Court of Oklahoma, 1941)
Clifton, Applegate & Toole v. Big Lake Drain District No. 1
267 P. 207 (Montana Supreme Court, 1928)
Nishnabotna Drainage District No. 10 v. Lana Construction Co.
185 Iowa 368 (Supreme Court of Iowa, 1919)
Rialto Construction Co. v. Reed
118 P. 473 (California Court of Appeal, 1911)
Greer v. Andrew
65 S.E. 416 (Supreme Court of Georgia, 1909)
District of Columbia v. Brewer
32 App. D.C. 388 (D.C. Circuit, 1909)
Hottel v. Poudre Valley Reservoir Co.
41 Colo. 370 (Supreme Court of Colorado, 1907)
Cook v. Foley
152 F. 41 (Eighth Circuit, 1907)
Hebert v. Dewey
77 N.E. 822 (Massachusetts Supreme Judicial Court, 1906)
J. J. Moore & Co. v. Cornwall
144 F. 22 (Ninth Circuit, 1906)
Choctaw & M. R. Co. v. Newton
140 F. 225 (Eighth Circuit, 1905)
Cornwall v. J. J. Moore & Co.
125 F. 646 (N.D. California, 1903)
O'Brien v. Champlain Construction Co.
107 F. 338 (U.S. Circuit Court for the District of Vermont, 1901)
Spaulding v. Coeur D'Alene Railway & Navigation Co.
51 P. 408 (Idaho Supreme Court, 1897)
In re Wells's Estate
69 Vt. 388 (Supreme Court of Vermont, 1897)
Sherman v. Estey Organ Co.
69 Vt. 355 (Supreme Court of Vermont, 1897)
Moran v. Schmitt
67 N.W. 323 (Michigan Supreme Court, 1896)
Norfolk & Western Railroad v. Mills & Fairfax
22 S.E. 556 (Supreme Court of Virginia, 1895)
Mundy v. Louisville & N. R.
67 F. 633 (Sixth Circuit, 1895)
John A. Tolman Co. v. Bowerman
60 N.W. 751 (South Dakota Supreme Court, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
27 Vt. 673, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herrick-v-estate-of-belknap-vt-1854.