Hebert v. Dewey

77 N.E. 822, 191 Mass. 403, 1906 Mass. LEXIS 1293
CourtMassachusetts Supreme Judicial Court
DecidedApril 7, 1906
StatusPublished
Cited by42 cases

This text of 77 N.E. 822 (Hebert v. Dewey) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hebert v. Dewey, 77 N.E. 822, 191 Mass. 403, 1906 Mass. LEXIS 1293 (Mass. 1906).

Opinion

Knowlton, C. J.

The first of these actions was brought by the plaintiff’s intestate to recover upon a contract in writing for building a house for the defendant, and also for extra work done in connection with the contract. The second is a cross action, brought to recover damages for the non-performance of the contract, and also for money lent to the defendant, and money had and received by the defendant to the plaintiff’s use. In the opinion of the judge, it appeared at the close of the evidence that the matters relied on in the cross action were substantially the same as those set up in the answer and in the declaration in set-off in the first action. The defendant in that action was therefore ordered by the judge to elect, whether he would rely upon these matters as a defence under his answer, or would waive this part of his defence and stand upon his declaration in the cross action. He elected to take the benefit of them under his answer, and a verdict for the defendant was accordingly rendered in the cross action. Assuming the facts to be as held by the judge, this order was proper under the rules stated in Cox v. Wiley, 183 Mass. 410. The facts are not shown to be otherwise. The defendant now concedes that, if there was no error in other parts of the case, he was not aggrieved by the order to elect. The exception to this order is overruled.

The first important exception relates to the rulings and refusals to rule in regard to certificates, given to the plaintiff’s intestate by the architect, upon which payments were made by the defendant under the contract. The contract provided for three payments to be made at different stages in the progress of the work, and a fourth after the completion of it. Then followed this proviso: “ That in each case of the said payments, a certificate shall be obtained from and signed by said F. S. New man, architect, to the effect that the work is done in strict accordance with drawings and specifications, and that he considers the payment properly due; said certificate, however, in no way lessening the total and final responsibility of the contractor; neither shall it exempt the contractor from liability to replace work, if it be after-wards discovered to have been done ill, or not according to the drawings and specifications, either in execution or materials,” etc.

[408]*408The third certificate, in its substantive parts, is as follows:

“ This is to certify that under the terms of the contract dated, . . . Mr. Joseph Hebert, contractor for building your house, is entitled to the third payment amounting to twelve hundred dollars.” The first and second certificates were in the same form; but the architect refused to give the fourth and final certificate, and the plaintiff’s intestate never obtained it. At the trial the evidence was conflicting upon all the questions in issue, and there was much dispute as to whether the plaintiff’s intestate had performed the contract, or had done improper work and used improper materials in violation of it. The judge instructed the jury, in substance, that so far as the work and materials which had previously been supplied were known to the architect at the time of giving one of these certificates, the certificate would be conclusive upon the defendant as to the quality and fitness of the work and materials, and it would not afterwards be open to the architect or the owner to question it. He treated each of these certificates as a final determination, in favor of the contractor, that the contract had been properly performed up to that time, in all parts of which the architect had knowledge.

It is well settled that, in the absence of fraud, or such mistake as prevents him from exercising his judgment upon the case, the parties are bound by the certificate of an architect, made under the authority of a building contract like that now before us. His position is like that of an arbitrator, to determine the particular matter submitted to him. Palmer v. Clark, 106 Mass. 373, 389. Flint v. Gibson, 106 Mass. 391. Robbins v. Clark, 129 Mass. 145. National Contracting Co. v. Commonwealth, 183 Mass. 89. Norcross v. Wyman, 187 Mass. 25. White v. Abbott, 188 Mass. 99.

The only question of difficulty in this part of the case arises from the peculiar language of the contract as to the effect of the certificates. They are referred to as “ in no way lessening the total and final responsibility of the contractor,” etc. This language furnishes ground for an argument that the certificates given before the completion of the work were intended to be merely intermediate or progress certificates, for the benefit of the builder, given to enable him to obtain payments on account, during the progress of the work. Such certificates are not con-[409]*409elusive as to the final payment, nor upon a claim for damages, nor on a quantum meruit. 1 Hudson, Building Contracts, 288. Tharsis Sulphur & Copper Co. v. M’Elroy, 3 App. Cas. 1040. Ford v. St. Louis, Keokuk Northwestern Railroad, 54 Iowa, 723.

While the matter is not free from doubt, we are inclined to hold that these certificates were intended to be something more than progress certificates, and that they are to be held final in their determination of all matters which were then within the knowledge of the architect. In the first place, the contract makes no distinction in this particular between the certificates to be given before the work is completed and the final certificate. Then the special provision as to the effect is, that they shall not relieve the contractor from liability for inferior work, if it be afterwards discovered to have been done ill, . . . either in execution or materials,” etc. Inasmuch as the general rule would make such certificates conclusive, we are of opinion that they should be held to leave the claims open only as to deficiencies that are afterwards discovered, and that this exception of the defendant should be overruled.

The defendant contended that the plaintiff could not recover under the contract because her intestate failed to obtain from the architect a certificate that the final payment was due. The question is whether a sufficient justification was shown for this failure. The instruction to the jury on this point was as follows : “ If the defendant’s architect capriciously withheld the final certificate and capriciously led the contractor to believe that nothing more remained to be done to entitle him to such certificate, the contractor is thereby relieved from his obligation to secure the certificate.” This was in accordance with the plaintiff’s request, except that the judge left out the word “ fraudulently ” which was used in the request with “ capriciously.” The law bearing upon this part of the case has not been definitely settled in this Commonwealth. There is a class of cases arising under policies of insurance and other similar contracts, in which it is held that the procurement of the certificate, called for by the contract, is a condition precedent to the plaintiff’s recovery. Johnson v. Phoenix Ins. Co. 112 Mass. 49. Audette v. L’Union St. Joseph, 178 Mass. 113, and cases there cited. The reason why it is not open to the plaintiff in these [410]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daly Sons v. City of West Haven, No. Cv96 0053211s (Feb. 13, 1997)
1997 Conn. Super. Ct. 832 (Connecticut Superior Court, 1997)
Grenier v. Compratt Construction Co.
454 A.2d 1289 (Supreme Court of Connecticut, 1983)
ALBRE MARBLE & TILE CO. INC. v. Goverman
233 N.E.2d 533 (Massachusetts Supreme Judicial Court, 1968)
Schroeder v. Federal Insurance
179 N.E.2d 328 (Massachusetts Supreme Judicial Court, 1962)
Wessinger v. H. Werner Sons Co.
162 N.E.2d 834 (Massachusetts Supreme Judicial Court, 1959)
Louis M. Herman Co. Inc. v. Gallagher Electrical Co.
138 N.E.2d 120 (Massachusetts Supreme Judicial Court, 1956)
M. Ahern Co. v. John Bowen Co. Inc.
133 N.E.2d 484 (Massachusetts Supreme Judicial Court, 1956)
Abbot Lumber & Building Supply Co. v. Cushing Construction Co.
112 N.E.2d 245 (Massachusetts Supreme Judicial Court, 1953)
Derderian v. UNION MARKET NATIONAL BANK
95 N.E.2d 552 (Massachusetts Supreme Judicial Court, 1950)
Halvorson v. Blue Mountain Prune Growers Cooperative
217 P.2d 254 (Oregon Supreme Court, 1950)
Halvorson v. Blue Mt. Prune Growers Co-Op.
217 P.2d 254 (Oregon Supreme Court, 1949)
Benjamin Foster Co. v. Commonwealth
61 N.E.2d 147 (Massachusetts Supreme Judicial Court, 1945)
Sikora v. Hogan
51 N.E.2d 970 (Massachusetts Supreme Judicial Court, 1943)
Lander v. Samuel Heller Leather Co.
50 N.E.2d 962 (Massachusetts Supreme Judicial Court, 1943)
Davis v. Newburyport Five Cents Savings Bank
41 N.E.2d 188 (Massachusetts Supreme Judicial Court, 1942)
McLeod v. I. J. Fox, Inc.
4 Mass. App. Div. 269 (Mass. Dist. Ct., App. Div., 1939)
Wolbarsht v. Donnelly
20 N.E.2d 415 (Massachusetts Supreme Judicial Court, 1939)
School District No. 1 v. Howard
52 P.2d 421 (Wyoming Supreme Court, 1935)
Rooney v. County of Essex
198 N.E. 915 (Massachusetts Supreme Judicial Court, 1935)
Poorvu v. Weisberg
286 Mass. 526 (Massachusetts Supreme Judicial Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
77 N.E. 822, 191 Mass. 403, 1906 Mass. LEXIS 1293, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hebert-v-dewey-mass-1906.