Crouch v. . Gutmann

31 N.E. 271, 134 N.Y. 45, 4 Silv. Ct. App. 461, 45 N.Y. St. Rep. 470, 89 Sickels 45
CourtNew York Court of Appeals
DecidedMay 31, 1892
StatusPublished
Cited by58 cases

This text of 31 N.E. 271 (Crouch v. . Gutmann) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crouch v. . Gutmann, 31 N.E. 271, 134 N.Y. 45, 4 Silv. Ct. App. 461, 45 N.Y. St. Rep. 470, 89 Sickels 45 (N.Y. 1892).

Opinions

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 47

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 48

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 49

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 50 The acceptance of the order given by the Wadsworths to the plaintiffs upon the defendant was in terms conditional, and payment made dependent upon completion of the building and on the architect's certificate. And by the contract such certificate was made a condition precedent to the right to any payments upon the work. No such certificate was obtained by the Wadsworths or the plaintiffs in support of the demand for payment of the amount of the order or any portion of it, but upon application made to him November 29, 1887, by one of the plaintiffs for a final certificate on the work, the architect put his refusal in writing of that date as follows:

"Mr. F.P. CROUCH — Replying to your request for final certificate on the Gutmann contract, I regret that there are so many things which are imperfect that I am prevented from certifying to the satisfactory completion of the work under the contract. JAMES G. CUTLER, "Architect."

The parties to the contract, by it made the architect's certificate essential evidence of performance and of the right to payment founded upon it, and unless its production was in some manner waived, or its necessity otherwise overcome or obviated, the failure to obtain it constituted a bar to recovery by the plaintiffs. (Smith v. Brady, 17 N.Y. 173.) In support of his conclusions, the referee found that the contractor Stauchen substantially performed the work on his part, and that on his adjustment with the defendant there was deducted $199.55 for defective mason work, and $1,300 for delay from *Page 51 April 1 to August 8, 1887, in completing the work. And that the Wadsworths substantially performed the agreement on their part, though in some particulars their work was not first class, but there was no willful or intentional departure on their part from the terms of the contract; and that such defects did not pervade the whole work, and were "not so essential that the object which the parties intended to accomplish was not accomplished." He also found that the architect refused to give the plaintiffs a certificate for final estimate, and upon demand refused to give any certificate; and that his refusal to give any certificate was unjust and unreasonable. The latter may have been supported if the finding of substantial performance was warranted. Both propositions are challenged by the defendant's exceptions. Since the rule of exact or literal performance has been relaxed and recovery may be founded upon substantial performance, that term, in its practical application to building contracts, has perhaps necessarily become somewhat indefinite otherwise than that the builder must have in good faith intended to comply with the contract, and shall substantially have done so in the sense that the defects are not pervasive, do not constitute a deviation from the general plan contemplated for the work, and are not so essential that the object of the parties in making the contract and its purpose cannot, without difficulty, be accomplished by remedying them. Then slight defects caused by inadvertence or unintentional omissions are not necessarily in the way of recovery of the contract price, less the amount, by way of damages, requisite to indemnify the owner for the expense of conforming the work to that for which he contracted. And whether, having in view those guiding considerations, the contractor has proceeded in good faith, and the defects are slight in the sense applicable to them in their relation to the work as a whole, are usually questions of fact, and upon their determination is dependent the disposition of that of substantial performance. (Glacius v. Black, 50 N.Y. 145; Phillip v. Gallant, 62 id. 256; Woodward v. Fuller, 80 id. 312; Nolan v.Whitney, 88 id. 648.) *Page 52

In the present case the defective condition of the carpenter work from all causes, as described by the findings of the referee, were that the walls of the building settled to some extent, thereby affecting the carpenter work; that the base boards in many cases parted from the floor, that such shrinkage of the boards was without the fault of the Wadsworths or the material furnished, but was due to the settling of the walls and partially to the steam heat; that the materials furnished by them were according to the terms of the contract, except that of the shelving in closets and the maple flooring for the halls, part of which was second-class material. These facts have some evidence for their support.

The referee further found upon the subject of defects in the carpenter work, that when the Wadsworths stopped work in the latter part of July, 1887, there were defects in their work in the following respects: "In the bath-rooms, in the hardwood floors, pieced casings on windows in rear of building, defective hand-rail on front stairs, moulding in some portions of the building not properly smoothed before oiling, imperfect painting on the front of the building." And further, that on the defendant's three days' notice provided by the contract and given on July 30, 1887, to the contractor to provide materials and workmen to complete the work, the defendant employed to remedy the defects one Pike, a carpenter, whose work upon the building was "fixing the doors so they would latch and windows so they would slide, fixing covers on wash trays, fixing back stairs, being defects principally due in part to poor workmanship and in part to settling of the building. That the front of the building was repainted by men employed by Pike, the original job having been a poor one showing spots, and in some cases when Pike's repairing made it necessary, additional coats of oil were put on the building in the interior." And that the fair value of the labor and materials necessary to remedy and make good the defective and omitted work covered by the specifications performed by Pike and his painter was $439.29.

The referee then proceeded by his findings to state that the *Page 53 defective work covered by the specifications and not remedied by Pike consisted of "maple flooring in the halls in which some cases second-class material was used, and the floors themselves in some cases present an uneven surface caused by settling of the building. The window frames in rooms in the rear of the building were not set to correspond in height with the doors in said rear rooms, and the hand-rail on front stairs was patched, and there was defective work in the bath-rooms, window casings and closet shelves, but the said defects do not prevent the use of the building for the purposes intended." And that the fair value of the labor and materials necessary to remedy such defective work not remedied by Pike and his painter was $205. He also found that the Wadsworths failed to provide iron transom guards for rear doors and iron registers for front, for which deduction of $12 should be made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monus v. Colorado Baseball 1993, Inc.
103 F.3d 145 (Tenth Circuit, 1996)
Reale v. Linder
135 Misc. 2d 317 (Nassau County District Court, 1987)
Manshul Construction Corp. v. Dormitory Authority of New York
111 Misc. 2d 209 (New York Supreme Court, 1981)
Bellizzi v. Huntley Estates, Inc.
143 N.E.2d 802 (New York Court of Appeals, 1957)
Antonoff v. Basso
78 N.W.2d 604 (Michigan Supreme Court, 1956)
Creith Lumber, Inc. v. Cummins
163 Ohio St. (N.S.) 264 (Ohio Supreme Court, 1955)
Hazeltine Research, Inc. v. De Wald Radio Mfg. Corp.
194 Misc. 81 (New York Supreme Court, 1948)
Boljen v. Ellegaard
181 Misc. 326 (New York Supreme Court, 1943)
Nees v. Weaver
269 N.W. 266 (Wisconsin Supreme Court, 1936)
Moran Bros. Contracting Co. v. City of New York
154 Misc. 802 (City of New York Municipal Court, 1935)
Scott v. Crawford
9 Ohio Law. Abs. 146 (Ohio Court of Appeals, 1930)
Grand Rapids Show Case Co. v. Earle Rogers Co.
136 S.E. 602 (West Virginia Supreme Court, 1927)
Moss v. Best Knitting Mills
130 S.E. 635 (Supreme Court of North Carolina, 1925)
Jacob & Youngs, Inc. v. Kent
129 N.E. 889 (New York Court of Appeals, 1921)
Robinson v. Beaty
1919 OK 174 (Supreme Court of Oklahoma, 1919)
Richmond College v. Scott-Nuckols Co.
98 S.E. 1 (Supreme Court of Virginia, 1919)
Meulenbergh v. Coe
160 N.Y.S. 581 (New York Supreme Court, 1916)
Lindeberg v. Hodgens
89 Misc. 454 (Appellate Terms of the Supreme Court of New York, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
31 N.E. 271, 134 N.Y. 45, 4 Silv. Ct. App. 461, 45 N.Y. St. Rep. 470, 89 Sickels 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crouch-v-gutmann-ny-1892.