Meulenbergh v. Coe

160 N.Y.S. 581
CourtNew York Supreme Court
DecidedMay 15, 1916
StatusPublished

This text of 160 N.Y.S. 581 (Meulenbergh v. Coe) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meulenbergh v. Coe, 160 N.Y.S. 581 (N.Y. Super. Ct. 1916).

Opinion

GIEGERICH, J.

The action is to foreclose a mechanic’s lien. The owner of the property, the defendant Coe, has made default in appearing and answering. The defendant Bilquez, the lessee of the premises, is the only one who defends the action. Various lienors have appeared and made proof of their respective claims. On or about May 10, 1915, the plaintiff and the said defendant Bilquez entered into a contract for the “erection, alteration, shoring, and repairing of work in general, in houses Nos. 158-160 W. Forty-Fifth street, New York City, of all excavation, concrete foundations, walls, walks and flooring, shoring of front walls, ripping of partitions, building new partitions, building new front, new marquis, new iron stair, new cellar and service stairs, new chimney, new addition for service stairs, new plumbing and fixtures, [583]*583new electric work and repairs, painting and papering, metal work, plaster work, etc., and as may be necessary.” The work consisted of altering the buildings in question for the purposes of a restaurant, café and furnished room house to be conducted by the said defendant. The work was done under what is known as a percentage contract, the contract, among other things, providing:

“All payments shall be made to the contractor between the 1st and 5th of each month during the work. The contractor shall receive 10 per cent, of the cost of labor, material, superintendence and expenses by himself, and he shall receive 5 per cent of the cost of all and any work done by his or other subcontractors. Monthly payments shall amount to 60 per cent, of the work done by all contractors and himself during that month.”

[ 1 ] The written contract is silent as to the cost of the work, but the defendant contends that it was not to exceed $10,500, which the plaintiff denies. In support of his contention the defendant quotes the letter of the plaintiff to him. Such letter was received by the defendant on May 15, 1915, and reads as follows:

“It is understood and agreed between both parties in this contemplated contract that the work contemplated on at this time is not to exceed a figure of S10.500.”

The evidence satisfies me that the letter in question was sent to the defendant in order that he might procure a bond of a surety company which had theretofore refused to issue one, owing to the uncertainty of the cost of the work, and that the plaintiff was requested to examine the building with a view of getting an approximate idea of what the job would cost if certain features of the work shown on the plans were eliminated. In this connection the plaintiff testified—which testimony I believe—that:

“Mr. Bilquez said he had not been able to obtain a bond from any bonding company owing to the peculiar conditions of the contract; that the job was to be on a percentage basis, and the bonding company could not tell whether the job would cost $1 or §10,000, so he asked me to go to the building and get an approximate idea of what the job would cost. I offered to write Mr. Bilquez that if certain things which he had spoken of were to be omitted from the plans, and other changes which he contemplated would be made, the job probably would be cheaper. ‘Can you write that to the bonding company?’ and I wrote this letter to Mr. Bilquez. He then took it to the bonding company or the brokers to obtain a bond. We started work after he Obtained a bond.”

The defendant concedes that at the time of the receipt of that letter the parties contemplated the performance of some work in addition to that called for by the contract. The specifications expressly provide for additional work in the following language:

“The owner reserves the right at any time to make any addition or deviation from work contemplated or any part or parts thereof as covered by plans and specifications."

The evidence shows that during the performance of the work various changes were made in the plans and specifications, and additions were made thereto with the consent of the defendant, which greatly enhanced the cost of the work. All this goes to show that the parties did not agree [584]*584upon a maximum, price for the work, and after consideration of all the evidence I am of the opinion that the contention of the defendant that the cost of the work was not to exceed $10,500 is not supported by the evidence.

The defendant maintains that the work was not completed until some time in October, 1915, or less than 90 days prior to the commencement of the action. I do not agree with such contention, but find, on the contrary, that the plaintiff substantially completed the work required of him on August 30, 1915, and that on said date the defendant accepted the work, and received from the plaintiff the keys of the premises and went into possession, and has ever since remained in possession thereof.

[2] It is further claimed by the defendant that the plaintiff entirely omitted to put in a 6-inch plaster partition inclosing the stairs in the basement, which he claims that, according to the plans, the plaintiff was required to do. New plans in place of those filed in May, 1915, were filed on October 4, 1915, and approved by the building department. It is claimed by the defendant that partitions are shown on such new plans. It appears that the work has been approved by the proper departments without the partition in question, and the architect does not remember whether he ever called the plaintiff’s attention to the omission of such ■ partition. Although an effort was made upon the trial by the defendant to prove the cost of the erection of a partition of the character mentioned, he failed to do so. The plaintiff’s main and reply briefs do not make any mention of this point, and I have been unable to discover any direct testimony in behalf of the plaintiff in the stenographer’s minutes with respect thereto. Even if the plaintiff was under obligation but has omitted to erect such partition, I think, in view of the circumstances, the omission must be held to be immaterial and of such a slight or unsubstantial character as not to affect the plaintiff’s right of recovery. Nolan v. Whitney, 88 N. Y. 648; Crouch v. Gutmann, 134 N. Y. 45, 31 N. E. 271, 30 Am. St. Rep. 608; 6 Cyc. 57. All the more should it be so held in this case, where the work, if done, would have been done at the defendant’s expense, and the plaintiff has not gained by the omission, but has lost the commission that he might have earned. The defendant further urges that the coal chute was never properly finished, although, as claimed, alterations were made <on it some time after October 6, 1915. This is denied by the plaintiff, and I am inclined to give credence to his contention that the coal chute was properly finished on August 30, 1915, and that if any work was thereafter performed on it, it was done only to satisfy the defendant.

[3] The defendant claims, furthermore, that the plaintiff failed, until October, 1915, to procure the dismissal of so-called violations filed by the building department, and that work necessary to remove a violation filed by the department of water supply, gas, and electricity in connection with the water meter was not done until October, 1915.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mahley v. . German Bank
67 N.E. 117 (New York Court of Appeals, 1903)
Crouch v. . Gutmann
31 N.E. 271 (New York Court of Appeals, 1892)
Bowery National Bank v. Mayor of New York
63 N.Y. 336 (New York Court of Appeals, 1875)
Toop v. . Smith
73 N.E. 1113 (New York Court of Appeals, 1905)
Waters v. Goldberg
124 A.D. 511 (Appellate Division of the Supreme Court of New York, 1908)
Ball v. Doherty
144 A.D. 277 (Appellate Division of the Supreme Court of New York, 1911)
Fanning v. Terre
152 A.D. 718 (Appellate Division of the Supreme Court of New York, 1912)
Nolan v. Whitney
88 N.Y. 648 (New York Court of Appeals, 1882)

Cite This Page — Counsel Stack

Bluebook (online)
160 N.Y.S. 581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meulenbergh-v-coe-nysupct-1916.