Richmond College v. Scott-Nuckols Co.

98 S.E. 1, 124 Va. 333, 1919 Va. LEXIS 128
CourtSupreme Court of Virginia
DecidedJanuary 16, 1919
StatusPublished
Cited by14 cases

This text of 98 S.E. 1 (Richmond College v. Scott-Nuckols Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richmond College v. Scott-Nuckols Co., 98 S.E. 1, 124 Va. 333, 1919 Va. LEXIS 128 (Va. 1919).

Opinion

Prentis, J.,

delivered the opinion of the court.

[336]*336Richmond College, hereinafter called the defendant, complains of a. verdict and judgment in favor of Scott-Nuckols Co., Incorporated, hereinafter called the contractor, for the balance claimed to be due for material and labor done in the construction of water and sewer lines laid under certain written contracts.

[1] There were three separate contracts. Contract No. 1 was dated March 6, 1914, and contract No. 3 September 15, 1914. There was another contract, generally referred to in the record as contract No. 2, which was dated July 13, 1914. One point of controversy arises out of the fact that although the action was based upon balances claimed to be due on contracts Nos. 1 and 3, the defendant filed a special plea of set-off and recoupment and claimed that the three contracts were dependent each upon the other, and that it had the right to set-off and recover for damages arising out of alleged defects in the construction done under contract No. 2 as well as for such alleged defective work done under the other two contracts. The construction under contract No. 2 had been completed, inspected, approved, and the whole work done thereunder paid for in full by the defendant before this suit was instituted, and the action, as above stated, is based upon balances claimed to be due under the other two contracts.

While all of the work was done in the construction of a sewer and water system upon the property of the defendant at Westhampton, the contracts were let at separate times, under different specifications and upon competitive bidding. They might just as well have been entered into with three separate contractors as with one, and no refer-' ence is made in either one of the contracts to either of the others. They were, therefore, clearly independent and not interdependent agreements. All that is hereafter said must be read in view of this conclusion, which was contested by the defendant in several different methods before the trial court as well as here.

[337]*337The specifications which constitute a part of contract No. 1 provide, among other things, that “The premises shall at all times be under charge and jurisdiction of the engineer, and he or his properly accredited agents or representatives shall have free and unobstructed access to the premises at all times, and the contractor shall provide adequate and safe means for the inspection of his work at any and all times.” They further provide that “the term ‘engineer’ shall mean a properly appointed member of the firm of Corneal & Johnson, or his successor duly appointed by the owners, or the assistants and duly authorized agents of the engineer.” As to payments, this is said: “Payments will be made as the work progresses, upon the certificate of the engineer that the work has been satisfactorily performed. Basis of payment to be eighty-five per cent, of the work satisfactorily performed, the remaining fifteen per cent, to be included in the final payment for the entire work which shall be. due and made within thirty days after the acceptance and approval of the work as a whole by the engineer and superintendent and the owners.”

There was, as is usual in such controversies, a sharp conflict in the evidence, which we shall not review, because by the mandate of the statute, under the demurrer to the evidence rule, the defendant is here admitting the truth of all of the contractor’s evidence and all proper inferences therefrom which conflict with its own evidence.

[2, 3] 1. The first assignment of error is that the court erred in overruling the demurrer to the declaration. The original declaration contains the common counts in assumpsit. The particulars of the claim and the amended declaration show that the contractor was claiming a balance of $238.29 for work done under contract No. 1 ($8,050.61 having been paid thereon), $1,139.46 under contract No. 3 ($1,000 having been paid thereon), and $10 for sand and [338]*338stone furnished. The demurrer was a general demurrer to the declaration and to each count thereof, and for specification states, “that the several matters and things set out in the contracts made a part of said amended declaration and shown to be conditions precedent to a right of action and recovery, are not alleged or averred in such manner as to give plaintiff the right to sue, nor are such other matters alleged as legally excuse the failure to allege and aver such conditions precedent.”

It is only necessary to say, as to this specification, what was said as to the sixth and seventh grounds of demurrer in the case of Newton v. White, 115 Va. 849. 80 S. E. 561, and that is that it is no more than an assertion that the declaration is insufficient in law. The rule which' would apply under section 3271 in cases where the plaintiff moves the court to require the defendant to state the grounds of demurrer, requires that they shall be stated specifically, and that no ground shall be considered other than those so stated. Va. & S. W. Ry. Co. v. Hollingsworth, 107 Va. 364, 58 S. E. 572. The demurrer was submitted without argument, and the defendant did not present to the lower court, either in its demurrer or in argument, the specific ground here relied upon. It was properly overruled, because under section 3272 of the Code, “no defect or imperfection in the declaration, whether it has heretofore been deemed mispleading or insufficient pleading or not, shall be regarded unless there shall be omitted something so essential to the action or defense that judgment according to law and the very right of the cause cannot be given.”

[4, 5] This declaration and the statement of the particulars of the claim clearly and sufficiently advised the defendant of the nature of the contractor’s claim, and although it does not in specific terms charge fraud or bad faith on the part of the architects who were required by the contracts and specifications to approve the work, it does so in [339]*339substance for in both of the special counts it is alleged that “the plaintiff repeatedly called upon the said architects to issue to it a certificate for said work, which they had approved,' but the said architects, without any just cause or right or excuse for so doing, wrongfully refused and failed to issue a certificate for said work” in accordance with the contracts; and further, that although the defendant took and accepted said work and has had the use and benefit thereof, “that the said architects have wrongfully and in gross disregard of the rights of the plaintiff refused to issue a certificate therefor.” Actual fraud is not the only excuse which may be shown for failure to produce the architect’s certificate, and it is well recognized that such a certificate is not necessary if it is capriciously or arbitrarily withheld. 6 R. C. L. 960; Bush v. Jones, 144 Fed. 942, 75 C. C. A. 582, note 6 L. R. A. (N. S.) 774; Crouch v. Gutmann, 134 N. Y. 45, 31 N. E. 271, 30 Am. St. Rep. 608, note; Edwards v. Hartshorn, 72 Kan. 19, 82 Pac. 520, note 1 L. R. A. (N. S.) 1051. If the refusal of the certificate is based upon false or fraudulent information, failure to produce it does not bar a recovery. Richmond v. Burton, 115 Va. 211, 78 S. E. 560. A general demurrer to such a declaration, under these conditions, should be overruled, and there is no merit in this assignment. B. & O. R. Co. v. Laffertys, 14 Gratt. (55 Va.) 478; N.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weilbacher v. Ring
296 P.3d 32 (Alaska Supreme Court, 2013)
David B. Ritter v. Sharon Ritter
Court of Appeals of Virginia, 2009
Sweeney Co. v. Engineers-Constructors, Inc.
823 F.2d 805 (Fourth Circuit, 1987)
United Masonry Inc. v. Riggs National Bank
357 S.E.2d 509 (Supreme Court of Virginia, 1987)
Chippenham Manor, Inc. v. Dervishian
201 S.E.2d 794 (Supreme Court of Virginia, 1974)
Odessky v. Monterey Wine Co.
49 S.E.2d 330 (Supreme Court of Virginia, 1948)
Ropp v. Stevens
154 S.E. 553 (Supreme Court of Virginia, 1930)
Transit Corp. v. Four Wheel Drive Auto Co.
145 S.E. 331 (Court of Appeals of Virginia, 1928)
Joseph H. Baker & Co. v. Hartman
124 S.E. 425 (Supreme Court of Virginia, 1924)
Watson v. Brunner
105 S.E. 97 (Supreme Court of Virginia, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
98 S.E. 1, 124 Va. 333, 1919 Va. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richmond-college-v-scott-nuckols-co-va-1919.