City of Richmond v. Burton

78 S.E. 560, 115 Va. 206, 1913 Va. LEXIS 24
CourtSupreme Court of Virginia
DecidedJune 12, 1913
StatusPublished
Cited by1 cases

This text of 78 S.E. 560 (City of Richmond v. Burton) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Richmond v. Burton, 78 S.E. 560, 115 Va. 206, 1913 Va. LEXIS 24 (Va. 1913).

Opinion

*212 Keith, P.,

delivered the opinion of the court.

Burton brought suit against the city of Richmond to recover a balance alleged to be due for the excavation of a sewer, and recovered a judgment, which is now before us upon the petition of the city of Richmond to review certain rulings made during the trial of the case.

There appears to be no dispute as to the amount of excavation done, or the price charged. The payment of the demand was resisted by the city upon the ground that the additional work for which the claim is made was never authorized by the city or its agents, and that the officers of the city under whose supervision the work is alleged to have been done had no authority to make any change in or departure from the plans and specifications set out in the contract between the city and Burton.

In the early stages of the work the contractor seems to have conformed substantially to the plans and specifications set out in the contract, and to the profile furnished him by the city engineer, but as the work progressed it was found that material was of such a nature that the sides of the trench would give way and slough off into the ditch, and that to prevent this it was necessary to put in ribs of timber and fill in the place where the sloughing had taken place with bricks, and for the material and work thus made necessary the city made payment without objection. In consequence of this condition of things Burton approached the assistant city engineer in charge of the work for the city, and called his attention to the trouble and expressed the opinion that if the trench were made wider and the weight taken off the sides by giving the banks a slope instead of having them perpendicular, it would be to the advantage of all parties concerned. The assistant city engineer acquiesced in this suggestion, and in consequence thereof the lines of the ditch were staked off much wider *213 than the original plans, specifications and profile called for, and the inspector under whose supervision the stakes were set kept a measurement of the additional excavation thus rendered necessary.

These are the facts which the evidence tends to prove on behalf of the defendant in error. They are controverted by the plaintiff in error, but must be accepted by us, the verdict of the jury having found them to be true.

The view of the plaintiff in error is that the change was made and the additional work done as a matter of convenience to the contractors, as they were thereby enabled to use machinery to a greater advantage in the excavation of the trench; but there is evidence tending to show that by the method adopted the city ivas saved a considerable sum of money as the ribbing with timber was no longer necessary and the use of so many brick was not required.

After the evidence was introduced to the jury the court gave certain instructions. The first to which we shall call attention ivas asked for by the defendant, and is predicated upon that provision in the contract which declares that the city engineer shall decide all questions and disputes of every nature relative to the construction, prosecution and fulfillment of the contracts, and as to the character, quality, amount and value of the work done and materials furnished, and that his decision upon all such points was to. be final and conclusive upon both parties, and they must abide by his decision, although it be erroneous, unless it be clearly proved by a preponderance of the evidence that such decision Avas fraudulently made of that such a gross mistake was made thereby as necessarily to imply bad faith on his part, or a plain failure to exercise an honest judgment.

To the giving of this instruction the plaintiff excepted, but we are of opinion that it correctly states the law as it prevails in this court and in other jurisdictions, and could *214 not be tbe subject of an assignment of error in any event as the judgment of tbe circuit court was for the plaintiff, and we, therefore, mention tbe instruction merely as tending to show that tbe case was properly submitted to the jury-

Tbe city of Richmond offered two instructions which were refused, in which tbe court was asked to construe tbe contract between Burton and tbe city, and tell tbe jury that no one of tbe assistants of tbe city engineer, or inspectors, upon tbe work bad any right to make any change or departure from tbe plans and specifications set out in the contract, even though tbe jury believed from tbe evidence that one of tbe assistant engineers or inspectors laid off tbe line of tbe ditch to be dug, and increased tbe dimensions thereof, which caused tbe cutting of tbe trench for. tbe sewers of larger dimensions than those prescribed in tbe iilans and specifications, yet such act on their part did not bind tbe defendant, tbe city of Richmond, and as a consequence tbe plaintiff is not entitled to recover in this action for tbe excess of excavation outside of that called for by tbe specifications.

Tbe court also gave an instruction of its own motion, tbe first branch of which pertains to tbe duty of tbe city engineer under tbe contract to settle all questions of dispute as to tbe character, quality, amount and value of tbe work to be done and material furnished, and which declares bis decision on all such points to be final and conclusive. It is conceded to be substantially a reiteration of tbe instruction upon tbe same subject already referred, to as having been given at tbe instance of tbe plaintiff in error, and need not be further noticed. Tbe second branch of tbe court’s instruction is tbe converse of tbe principle announced in tbe instructions asked for by tbe city and refused by tbe court, and tells tbe jury that if it was found necessary in tbe excavation to increase tbe dimen *215 sions greater than those shown upon the plans, and that the line of the trench Avas widened by the city engineer or his assistant, and that as so widened the plaintiff dng th'e trench as directed, then they should find for the plaintiff for such extra amount of excavation as they believed from the evidence was dug, and assess his damages at the same rate per cubic yard as was agreed upon in the proposal; the contention of the city being that the contract between the city and Burton constitutes the law of the case; that there could be no departure from it except as authorized by the contract itself; and that in all cases where a claim is made under a contract for extra work, it is incumbent upon the contractor to show that the amount of extra expense had been ascertained and the price and cost thereof agreed upon in writing between the city engineer and the contractor before the commencement of the work, while upon the part of the contractor the contention is that reading the contract as a whole the officers of the city in charge of the work were authorized to deviate from the plans and specifications set out in the contract, and that for the additional Avork authorized by the assistant engineer the city was responsible. Upon the decision of this question the determination of this controversy must depend.

We do not think that it can be successfully contended that the work here sued for Avas not done with the knowledge and approbation of the assistant engineer for the city.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richmond College v. Scott-Nuckols Co.
98 S.E. 1 (Supreme Court of Virginia, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
78 S.E. 560, 115 Va. 206, 1913 Va. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-richmond-v-burton-va-1913.