Cornell & Co. v. Steele

64 S.E. 1038, 109 Va. 589, 1909 Va. LEXIS 68
CourtSupreme Court of Virginia
DecidedJune 10, 1909
StatusPublished
Cited by4 cases

This text of 64 S.E. 1038 (Cornell & Co. v. Steele) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cornell & Co. v. Steele, 64 S.E. 1038, 109 Va. 589, 1909 Va. LEXIS 68 (Va. 1909).

Opinion

Cardwell, J.,

delivered the opinion of the court.

This action was brought by W. I. Steele to recover of J. iST. H. Cornell and Company, a foreign corporation, and J. H. Eine, [590]*590a- balance of $7,511.05, alleged to be due Steele from the defendants upon certain work which Steele sub-contracted with Cornell and Company, general contractors with the Virginia Air Line Eailway Company, to do on the Virginia Air Line Eailway, to be constructed by the general contractor from Lindsay, on the C. & O. Eailway in Albemarle county, to a point on James river, about twenty miles distant, the plaintiff, Steele, undertaking by his sub-contract the construction of four miles of this road within a stated period and according to specifications as to the execution of the work. That Steele performed his part of this contract truly and faithfully seems not to have been questioned, and the controversy arises out of the classification of the material taken out and removed by him, made by Cornell and Company’s chief engineer in charge of the work.

The contract, which was in evidence at the trial of this cause, shows the price of the excavation of the several kinds of material, to be taken out and removed by Steele, viz., earth, loose rock and solid rock, gives the definition of these several classes of material, and provides for monthly payments as the work progressed and for a final estimate on the completion and acceptance of the work; and the contract also provides that the decision of the chief engineer of the general contractor on all questions arising under the contract shall be final as between the parties.

J. H, Tine, who made the estimates on Steele’s work, was the chief engineer of the general contractor, and also its vice-president, and as Steele progressed with his work he received monthly .payments upon the estimates made by Line; but, as we shall see later, protested all along that these estimates were incorrect. On the completion of Steele’s contract in January, 1908, Line made a final estimate showing that the general contractor, Cornell and Company, owed Steele $1,775.73, to which Steele objected, alleging that this estimate was based upon an erroneous classification of material excavated and removed, and thereupon Cornell'and Company had the estimate reconsidered and [591]*591the work re-examined, but insisted that the action of its chief engineer was correct and would not be corrected, and so informed Steele. Whereupon, Steele selected one James Dickey, a competent engineer and an expert,, to go over the work and make an estimate of it according to the provisions of the contract, and Dickey’s estimate varied materially from that of Dine, the chief difference arising from the classification of material, the difference in the total quantity of material moved, or yardage, caused by certain measurements adopted by Dickey and not allowed by Dine being comparatively slight. Omitting the items of these estimates as to which Dickey and Dine agreed, the latter’s final estimate allowed Steele for 42,113.1 cubic yards of earth, $9,896.58; 10,174.8 cubic yards of loose rock, $3,856.42; and 586.9 cubic yards of solid rock, $398.23;. total, $14,155.13; while in Dickey’s estimate these several items appear as follows: 30,011.1 cubic yards of earth, $7,052.60; 15,559.5 cubic yards of loose rock, $5,912.61; and 10,017.8 cubic yards of solid rock, $7,012.46; total, $19,977.67. The disclosures made by these estimates caused Steele to realize that despite his rigid economy and efficient work, he would sustain a loss of over $3,500 if Dine’s estimate of his work was to be adhered to; and thereupon he brought this suit for $7,511.05, the amount of the difference between the final estimate made by Dine and that made by Dickey.

At the trial of the cause, it was submitted to the jury upon four instructions given by the court, to which neither party made objection, and the jury rendered its verdict for the plaintiff, assessing his damages at $3,600, and upon the verdict the court entered the judgment to which this writ of error was awarded.

The instructions of the trial court, in sum and substance, rightly told the jury that, notwithstanding the provision in the contract between the parties that the final estimate of the chief engineer of the general contractor, Cornell and Company, was to be final and conclusive on both parties, if they believed from the [592]*592evidence Chief Engineer Eine made such error of judgment or mistake in the estimates and classification of the work made by him as amounted to a mistake so gross as necessarily to imply bad faith and amount to a fraud upon the rights of the plaintiff, they should find for the plaintiff, even though they believed that said engineer had no intention to commit a fraud or to act in bad faith; and further told the jury, that if they believed from the evidence that the estimates or classifications by the company’s engineer were not binding on the plaintiff because of gross error or mistake, amounting to a fraud, then they should make such classification of the material removed as they deemed proper, under the evidence and according to the provisions, of the contract, and assess'the plaintiff’s damages according to that classification at the prices specified in the contract, subject to proper credits.

The contract between the parties is explicit as to the classification of the material that was to be removed and the prices to be paid therefor, solid rock being recognized as the most expensive material, and therefore a higher price for its removal was fixed than for the removal of earth or loose rock. It will, therefore, be seen that the subject of classification of the work done by defendant in error was the crucial point in the case, for the determination of the jury, and we deem it only necessary to refer briefly to the evidence to show that it was sufficient to warrant the jury in regarding the estimate made by Eine so grossly erroneous as to amount to a fraud upon the rights of defendant in error.

The material classified as solid rock by defendant in error and Dickey, and disallowed by Eine, is clearly and unmistakably proven to be the same material, of the same nature and character of rock as that allowed defendant in error and classified by Eine as solid rock to the extent of 569 cubic yards. In other words, the evidence shows that the rock, classified as solid rock by defendant in error and by Dickey, was of the identical kind, character and formation as the 569 yards of solid rock [593]*593allowed by the estimates made by Fine, and that the arbitrary rejection by him of over 9,000 cubic yards of this solid rock removed by defendant in error, and classifying the same with other material far less expensive to remove, was an error of judgment or mistake so gross as to amount to a fraud upon defendant in error’s rights; and if the jury believed in the truth and correctness of this evidence, it was of itself sufficient to sustain its finding in his favor. Mills & Fairfax v. N. & W. Ry. Co., 90 Va. 523, 19 S. E. 171; Id. 91 Va. 613, 22 S. E. 556.

In the report of that case last mentioned, the syllabus in part is as follows: “Whether the plaintiff was entitled to recover the higher or the lower of the two prices fixed by the contract for different classes of work, or whether he had waived or abandoned his right to recover the higher price, were questions of fact which were properly left to the determination of the jury, under instructions which correctly propounded the law, and gave them great latitude in the range of their inquiry.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Virginia Railway & Power Co.
131 S.E. 440 (Supreme Court of Virginia, 1926)
Roanoke Railway & Electric Co. v. Loving
119 S.E. 82 (Supreme Court of Virginia, 1923)
Richmond College v. Scott-Nuckols Co.
98 S.E. 1 (Supreme Court of Virginia, 1919)
Johnson & Grommet Bros. v. Bunn & Monteiro
76 S.E. 310 (Supreme Court of Virginia, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
64 S.E. 1038, 109 Va. 589, 1909 Va. LEXIS 68, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cornell-co-v-steele-va-1909.