Bush v. Jones

144 F. 942, 75 C.C.A. 774, 1906 U.S. App. LEXIS 3914
CourtCourt of Appeals for the Third Circuit
DecidedMay 3, 1906
DocketNo. 40
StatusPublished
Cited by26 cases

This text of 144 F. 942 (Bush v. Jones) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bush v. Jones, 144 F. 942, 75 C.C.A. 774, 1906 U.S. App. LEXIS 3914 (3d Cir. 1906).

Opinion

ARCHBARD, District Judge.

This was an action in the court below for $3,065, the final payment upon a contract for the construction of a building, together with a bill of some $40 extras. The verdict was in favor of the contractors for $2,500, a material reduction, particularly if interest be counted; the jury necessarily finding, however, under the instructions of the court, that the contract was substantially, if not completely, performed. The chief subject of controversy was the condition of the cellar, which admittedly leaked badly, and that in the face of an apparent guaranty that it should not. The contractors also failed to produce at the trial a certificate of completion from the architect, as required by the contract. On both of [943]*943these grounds it was contended that the plaintiffs were not entitled to recover, and these are the questions to be disposed of here.

According to the specifications upon which the contract for the building was let, it was provided with regard to the concrete work and waterproofing of the cellar:

“The foundation shall be of broken stone (not slag) concrete made up as follows: 5 parts of broken stone, 2 parts Portland Gemeut, and 1 part of clean sharp screened gravel or bar sand; * * * all stone for concrete to be of approved quality. The outside of all foundation walls to be dashed with cement and sand, 1 part to 2 on the outside, and brought to a smooth surface, and the whole outside of the foundations, up to grade, to be coated with a thick coat of asphaltum pitch, put on with a, ‘mop.’ At a level indicated on the detail, there shall be a three-ply layer of felt, mopped with pitch, and extending 1' 0" on each side of the wall. This shall be turned tip on the outside, and carefully joined with the ‘mop’ coat of asphalt, until perfectly water-tight. On the side next the party lute on the west the foundation shall be divided by a one inch board from the bottom to a level of 1' 0" above the cellar bottom of the adjoining property; this board to be removed as the wall is built. The slot so formed is to be grouted in with asphaltum, thoroughly water-tight. The outside dashing or mopping will not occur on this wall. The layer of felt must occur on all other walls or piers, whether interior or exterior.' The cellar wall shall be 10" thick in all, the first 3" to be of concrete, smoothly dressed for the reception of asphaltum; then one inch of asphaltum perfectly joined with the felt layers above mentioned; then 5" of stone concrete; then one inch on top. The whole to be made perfectly water-tight and guaranteed.'’

It is claimed that the contractors by virtue of the last- provision were bound at all hazards to make a water-tight job; that being, in terms, what they had not only undertaken but guarantied to do. Rut to this we cannot accede. The guaranty was not absolute, but qualified. It extended to their own work only, and only so far as this was involved, to the result. The specifications, which were the work of the architect, and for which they could not be expected to assume responsibility, directed how the work should be done, and b} this they were controlled. So far as this was calculated to make a watertight cellar, they unquestionably guarantied that it would be such. But that is all. It was not as though they were left to their own judgment; that which they were to do, as appears above, being specified in detail. No doubt, if there was any margin of discretion — as, for instance, with regard to the thickness of the mop coat of asphalt on the outside of the foundations; or in the maimer of turning and joining the felt .therewith “until perfectly water-tight,” as it is said; or in grouting in “thoroughly” with asphalt the slot left for the purpose in the divided wall 'oil the west line — it would come within their guaranty to see that these things were effectively done; and if the wall would be water-tight or otherwise, according as the}’’ were or were not, they would be correspondingly liable; but outside of this, not. The owner having assumed to say by the specifications what was to be done, the contractors were relieved so far as they complied therewith. They guarantied, not the sufficiency of this to produce the desired result, but merely the effectiveness of what they themselves did under it. McKnight Flintic Stone Co. v. Mayor, 160 N. Y. 72, 54 N. E. 661; Filbert v. Philadelphia, 181 Pa. 545, 31 Atl. 545; Harlow v. Homestead Borough, 194 Pa. 57, 45 Atl. 87. It may [944]*944be that the court did not explain as fully as it ought the hearing of the guaranty; but, with this exception, there was no error committed with regard to it. Binding instructions on the strength of it could not, in our judgment, have been given, and the assignments of error based upon the refusal to do so must be overruled.

The other point raised is more serious. It was provided in the contract that the work should be paid for “only upon the certificates of the architect,” the final payment to be made within 30 days after its completion, and all payments to be due when certificates for them were issued. As already observed, the contractors produced at the trial no certificate of. completion, the evidence being that it had been demanded and refused; reliance being placed, in its absence, upon the showing made that the contract had been substantially complied with. The defendants, in view of this, specifically requested the court to charge that there could be no recovery if there was a failure to secure from the architects a certificate that the work was completed. This was refused, and the question reserved; the jury, instead,, being instructed as follows:

“It is said, also, that the plaintiffs did not comply with the contract in another important particular; that is to say, that they did not secure from the architect a final certificate of the completion of the work and the amount that was due. You have heard some slight testimony upon that subject, which shows that the architect refused the final certificate upon being asked for it; and, as I understand, he refused because the owner of the building was not satisfied. I intend to reserve the question as to the importance of the architect’s certificate in this case, and therefore I do not think that you need trouble yourselves any further about it”

As the result of this, the jury were allowed to find, as they did, in favor of the contractors, without the production of a certificate, and without any instructions as to its necessity or what would be sufficient to dispense with it; and by the subsequent entry of judgment on the verdict in favor of the plaintiffs, and the refusal of judgment non obstante on the reserved point, which was moved for, the court, in effect, held that, as a matter of- law, under the circumstances, the production of a certificate was not a prerequisite to a recovery, and that the refusal of it did’not have to be accounted for.

The law upon the subject of architects’ certificates is well settled. It is perfectly legitimate to provide in a building or working contract that payment of the several installments of the contract price shall only be made upon certificates or estimates by the architect or engineer in charge as to the extent and value of the work done or materials furnished, and that final payment shall not be demandable without a certificate of completion.. These are familiar provisions, universally recognized, and will be enforced. 30 Am. & Eng. Encycl. Law (2d Ed.) 1237.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sunbeam Construction Co. v. Fisci
2 Cal. App. 3d 181 (California Court of Appeal, 1969)
Clack v. State of California Ex Rel. Dept. Pub. Wks.
275 Cal. App. 2d 743 (California Court of Appeal, 1969)
Clack v. ST. OF CALIFORNIA EX REL. DEPT. PUB. WKS
275 Cal. App. 2d 743 (California Court of Appeal, 1969)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Kurland v. United Pacific Insurance
251 Cal. App. 2d 112 (California Court of Appeal, 1967)
Helm v. Speith
182 S.W.2d 635 (Court of Appeals of Kentucky (pre-1976), 1944)
Town of Milford v. O'Neil Bros., Inc.
8 Conn. Super. Ct. 403 (Connecticut Superior Court, 1940)
United States Ex Rel. Johnson v. Morley Const. Co.
17 F. Supp. 378 (W.D. New York, 1936)
Gillespie Land & Irrigation Co. v. Hamilton
29 P.2d 158 (Arizona Supreme Court, 1934)
State v. Commercial Casualty Insurance
248 N.W. 807 (Nebraska Supreme Court, 1933)
Warner Co. v. North City Trust Co.
166 A. 230 (Supreme Court of Pennsylvania, 1933)
L. W. Kinnear, Inc. v. City of Lincoln Park
244 N.W. 463 (Michigan Supreme Court, 1932)
Larson v. Tacoma School District No. 10
255 P. 113 (Washington Supreme Court, 1927)
Port of Seattle v. Puget Sound Sheet Metal Works
213 P. 467 (Washington Supreme Court, 1923)
Arnold v. Thompson & Spear Co.
279 F. 307 (D.C. Circuit, 1922)
Riddle v. Pelligreen Construction Co.
237 S.W. 827 (Missouri Court of Appeals, 1922)
State Bank v. Pew
195 P. 852 (Montana Supreme Court, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
144 F. 942, 75 C.C.A. 774, 1906 U.S. App. LEXIS 3914, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bush-v-jones-ca3-1906.