Foster v. McKeown

61 N.E. 514, 192 Ill. 339
CourtIllinois Supreme Court
DecidedOctober 24, 1901
StatusPublished
Cited by21 cases

This text of 61 N.E. 514 (Foster v. McKeown) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foster v. McKeown, 61 N.E. 514, 192 Ill. 339 (Ill. 1901).

Opinion

Mr. Justice Ricks

delivered the opinion of the court:

Appellees insist that this appeal should be dismissed because the judgment appealed from and the amount involved were less than. $1000. As this goes to the jurisdiction of the court it should be first disposed of. ■

Appellees filed their declaration under the common counts, with an ad damnum of $1000, and obtained a judgment for $994.83. Appellant, in addition to the general issue, filed a plea of set-off, claiming $600 for damages for delay in the completion of the work, under the contract, $150 for moneys expended in removing rubbish and material left by appellees on the premises and to be removed by them under the contract, and for $200 for amount allowed carpenters for delay caused by failure of appellees to complete their work within the specified time.

The contract provides that there should be $10 a day allowed as liquidated damages to the owner for every day after the 11th day of June that the work should remain unfinished. The contract further provides that if the contractors (appellees) should delay the progress of the work so as to cause any damage for which the owner would become liable, the contractors should make good to the owner such damages, to be determined by the architect, etc. Evidence was offered in the trial court by appellant touching all these items, and this court can not say that such counter-claim was made in bad faith or was fictitious, and for the mere purpose of making a possible amount by which a final appeal might reach this court. If the contract and the rights of the parties under it were as contended for by appellant, then appellant would be entitled to a substantial portion, if not all, of the set-off claimed.

The errors assigned by appellant on the record are very general, simply being that the Appellate Court erred in affirming the judgment rendered by the circuit court,' and in not reversing it. In the brief and argument of appellant four grounds of error are insisted upon and reversal of the affirming order asked: First, that the trial court erred in refusing to give a peremptory instruction at the close of the plaintiffs’ evidence and at the close of all the evidence, to find for- appellant; second, that the court erred in sustaining the judgment below, because appellees produced no certificate of the architect for final payment, on the trial, as required by the contract; third, in admitting in evidence a paper purporting to be a statement of the account for extra work; and fourth, in refusing appellant’s first refused instruction.

The contention of appellant as to the first ground of error is, that the contract being in writing and the provision being that the payment should be made upon the production of the certificate of the architect and there being no certificate produced, the evidence was not admissible under the common counts, but that appellees should have filed a special count setting up the contract and showing an excuse for failure to produce the architect’s certificate, and that appellees, in the absence of a special count, could not, under the common counts, show an excuse for the absence or non-issuance of the architect’s certificate, and that therefore the instructions to find for appellant should have been given. The rule is well established in this State, that if there is evidence in the record, at the close of the plaintiff’s case, tending to prove the facts in support of his declaration, or at the close of all the testimony, if the evidence, with all the inferences which the jury can justifiably draw from it, is sufficient to support a verdict, then in each of such cases the peremptory instruction should be refused and the jury be given the case. Foster v. Wadsworth-Howland Co. 168 Ill. 514.) The application of these rules to this case involves a consideration of the rule of pleading and the construction of the contract in question, and a review of thé facts.

As the first and second grounds of error involve much of the same matter they will be treated together.

“With respect to debts for work and labor, or other personal services, it is a rule that however special the agreement was, yet if it was not under seal and the terms of it have been performed on the plaintiff’s part, and the remuneration was to be in money, it is not necessary to declare specially, and the common indebitatus count is sufficient.” (1 Chi tty’s Pl. 303.) This rule of pleading was early recognized in this State. In Throop v. Sherwood, 4 Gilm. 92, this court says (p. 98): “It is a well settled principle that while a contract continues executory the plaintiff must declare specially, but when it has been fully performed on his part, and nothing remains to be done under it but the payment of the compensation in money by the defendant, which is nothing more than the law will imply against him, the plaintiff may declare specially on the original contract, or generally in indebitatus assumpsit, at his election.” Since that time, at least, the rule has obtained and by a long line of cases has been repeated and affirmed. Sands v. Potter, 165 Ill. 397; Shepard v. Mills, 173 id. 223.

But appellant insists that this case does not come within the rule above announced, for the reason that something remained to be done under the contract,—that is, that it remained for appellees to procure the certificate of the architect,—and therefore the declaration should have been special.

The cases of Adlard v. Muldoon, 45 Ill. 193, Taylor v. Renn, 79 id. 181, Fowler v. Deakman, 84 id. 130, Shepard v. Mills, 173 id. 223, and Catholic Bishop of Chicago v. Bauer, 62 id. 188, are all cases where the common counts are relied on, and all but the case of the Catholic Bishop were building contracts, and involved questions striking in their similarity to the case at bar. In the Adlard case the court says: “The contract was properly admitted, but whether it had been performed or not was a question for the jury. A party has no right to recover under any contract until he has performed his part of the agreement,— and this is true in any form of action.” In the Catholic Bishop case the plaintiff was employed as superintendent of certain buildings to be erected. He performed all the service except to superintend the completion of St. Peter’s church, and was permitted to show he was discharged before the work was done. This court sustained the lower court. In Fowler v. Deakman, supra, there were special counts on the contract, and the common counts. The contractor had no certificate, and, as an excuse, in the special count charged collusion and fraud between the owner and the architect. The proof showed the architect refused to pass on the contractor’s bill for extras and certify the same for payment, but did not show fraud and collusion. This court, upon the question of variance between the proof and the special counts, said (p. 132): “If there were only the special counts in the declaration, then the objection would be well taken; but there are the common counts, and it has always been held in our practice that where a party has fully performed his part of a written contract, and nothing remains to be done but for the other party to pay the money due under the contract, a recovery may be had under the common counts; and it is usual, in declaring on the contract specially in such cases, for the purpose of avoiding a variance, to add the common counts.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hemingway v. Skinner Engineering Co.
254 N.E.2d 133 (Appellate Court of Illinois, 1969)
Ahmer v. Peters
149 N.E.2d 503 (Appellate Court of Illinois, 1958)
Cody v. Schwill
23 N.E.2d 223 (Appellate Court of Illinois, 1939)
Salomon-Waterton Co. v. Union Asbestos & Rubber Co.
263 Ill. App. 583 (Appellate Court of Illinois, 1931)
Cleary v. Illinois Central Railroad
226 Ill. App. 350 (Appellate Court of Illinois, 1922)
Stewart v. Spalding
23 Haw. 502 (Hawaii Supreme Court, 1916)
Connelly v. Wallin
181 Ill. App. 212 (Appellate Court of Illinois, 1913)
Amsler v. Bruner
173 Ill. App. 337 (Appellate Court of Illinois, 1912)
American Credit Indemnity Co. of New York v. Yamer
170 Ill. App. 350 (Appellate Court of Illinois, 1912)
Theis v. Svoboda
166 Ill. App. 20 (Appellate Court of Illinois, 1911)
Kleinschnittger v. Dorsey
152 Ill. App. 598 (Appellate Court of Illinois, 1910)
Caldwell & Drake v. Schmulbach
175 F. 429 (N.D. West Virginia, 1909)
Expanded Metal Fireproofing Co. v. Boyce
84 N.E. 275 (Illinois Supreme Court, 1908)
Bloomington Hotel Co. v. Garthwait
81 N.E. 714 (Illinois Supreme Court, 1907)
Oakes v. Barbre
127 Ill. App. 208 (Appellate Court of Illinois, 1906)
Bush v. Jones
144 F. 942 (Third Circuit, 1906)
Hart v. Carsley Manufacturing Co.
77 N.E. 897 (Illinois Supreme Court, 1906)
West Chicago Park Commissioners v. Schillinger
117 Ill. App. 525 (Appellate Court of Illinois, 1905)
Hart v. Carsley Manufacturing Co.
116 Ill. App. 159 (Appellate Court of Illinois, 1904)
Parker v. Brown House Co.
44 S.E. 807 (Supreme Court of Georgia, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
61 N.E. 514, 192 Ill. 339, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foster-v-mckeown-ill-1901.