Cody v. Schwill

23 N.E.2d 223, 301 Ill. App. 560, 1939 Ill. App. LEXIS 653
CourtAppellate Court of Illinois
DecidedOctober 25, 1939
DocketGen. No. 40,681
StatusPublished

This text of 23 N.E.2d 223 (Cody v. Schwill) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cody v. Schwill, 23 N.E.2d 223, 301 Ill. App. 560, 1939 Ill. App. LEXIS 653 (Ill. Ct. App. 1939).

Opinion

Mr. Justice Hebel

delivered the opinion of the court.

This is an appeal by the defendants from a judgment for $425 entered by the court for the plaintiff. The action by the plaintiff was to recover $575 alleged to be due the plaintiff for the furnishing of certain labor and material. The cause was submitted.to the court, and upon a hearing of the evidence the court allowed the defendants $150 on their counterclaim, which was filed in the action.

The defendants, Adelyne Sehwill, and her now deceased husband, Julius Sehwill, entered into a contract on July 19, 1937, with A. N. Rebori, an architect, for the construction of a $50,000 house at Barrington, Illinois, the architect to prepare the plans and specifications and perform all the duties of an architect as by the contract provided.

The general contractor for the construction of this home was R. E. Herlihy Construction Company, Inc., who let the contract to the plaintiff for the labor and material for sheet metal work, tile roofing, tar and gravel roofing, quarry tile, to be done according to the plans and specifications prepared by A.' N. Rebori.

On August 17, 1937, the plaintiff entered into a contract with R. E. Herlihy Construction Company, Inc., the general contractor. By the terms of the contract he agreed to furnish the labor and material and other items before stated which were required to be performed by the terms of his contract according to the plans and specifications prepared by A. N. Rebori, architect, for $1,695. According to the evidence in the record he performed certain work and received on account of the contract $1,260, and on February 4, 1938, there was due him the sum of $575.

It is contended by the defendants herein that the plaintiff should have presented an architect’s certificate, as provided for by the contract of R. E. Herlihy Construction Company, Inc., which was not presented to or received by the defendants as provided by the Herlihy contract.

The defendants, Adelyne Sehwill, individually, and Adelyne Sehwill as executrix of the estate of Julius, deceased, pursuant to rule of court, filed an amended answer and counterclaim admitting the contract and that the sum paid to the plaintiff was $1,260, and further in her answer stated: “that plaintiff’s work was rejected by the architect as well as by the defendant, of which rejection plaintiff was notified. That the contract provides that the decision of the architect in such case is final unless plaintiff within time specified demands arbitration. That arbitration or a demand therefor in such case is a condition precedent to the bringing of any action. That the time within which arbitration under the contract expired prior to the bringing of this suit. Wherefore, the decision of the architect as aforesaid is final.”

In support of the defendants’ counterclaim it is alleged :

“Defendant says by way of counter-claim that the plaintiff in performing and attempting to perform the work required of him under the contract, performed the same in such an unskillful, unworkmanlike and improper manner, using improper materials and applying the same in an unskillful and unworkmanlike manner and not in accordance with the plans or specifications of the contract. That by reason thereof the defendant was required to and did remove the materials so supplied by the plaintiff and was required to and did expend in that behalf and in having the work and materials done properly and in compliance with the plans and specifications, a sum in excess of $1,000 which sum she claims as a counter-claim against plaintiff, together with a further sum of $5,000 as damages suffered by defendant by reason of work and materials furnished by plaintiff and wrought into the structure which defects cannot be remedied or repaired except at great cost and expense as aforesaid.”

It was upon the issues which were presented to the court upon the trial of the matter that the judgment appealed from was entered.

This is an action by the plaintiff against the defendants based upon a contract to perform certain work, entered into by the plaintiff with B. E. Herlihy Construction Co. the general contractor for the construction of the residence at Barrington, Illinois. This contract is as follows:

“R. E. Herlihy Construction Co.

144 W. 47th Street

Chicago, Illinois

“Gentlemen:

“Re: Residence for Mrs. J. Schwill, Barrington, Illinois.

“We propose to furnish labor and material for Sheet Metal Work, Tile Roofing, Tar and Gravel Roofing and Quarry Tile, according to plans and specifications prepared by A. N. Rebori, Architect, for the sum of Sixteen Hundred Fifty and 00/100 Dollars ($1650.00).

“The above price is quoted with the understanding that we will furnish you with a Twenty year guarantee for Flat roof.

“If fire door from kitchen porch to garage is wanted add the sum of Forty Five and' 00/100 dollars ($45.00).”

Subsequently, during the progress of the work on the residence of the defendants, a further agreement ivas entered into, which is as follows:

“Mr. A. N. Rebori

29th Floor Tribune Tower

“Re: Schwill Residence

Barrington, Illinois

Job # 410

“Change on rear sleeping porch tile roofing, sheet metal gutters, flashings ^according to details for the sum of $115.00 (One Hundred Fifteen and No/100).

“Change on Kitchen Porch Tile Roofing, sheet metal gutters, flashings, etc. similar to above — Add the sum of $25.00.

“F. C. Cody Company

F. C. Cody Co.

By Per Bertha O’Brien (Signed)

“The above extra work (in the total amount of $140.00, One Hundred Forty and no/100 Dollars) is to be paid for by the Owner and deducted from the Architect’s Fee.

“Signed Andrew N. Bebori.”

The defense to this action is based upon two points. First, that the plaintiff failed to produce a certificate of the architect in compliance with the contract entered into with the B. E. Herlihy Construction Co. We might note at this time that the contract of the plaintiff is not subject to the terms and conditions of a building contract such as was entered into by the B. E. Herlihy Company and the defendants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vermont Street M. E. Church v. Brose
104 Ill. 206 (Illinois Supreme Court, 1882)
Foster v. McKeown
61 N.E. 514 (Illinois Supreme Court, 1901)
Evans v. Howell
71 N.E. 854 (Illinois Supreme Court, 1904)
Haunroth v. Peters
50 Ill. App. 366 (Appellate Court of Illinois, 1893)
Kleinschnittger v. Dorsey
152 Ill. App. 598 (Appellate Court of Illinois, 1910)
Connelly v. Wallin
181 Ill. App. 212 (Appellate Court of Illinois, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
23 N.E.2d 223, 301 Ill. App. 560, 1939 Ill. App. LEXIS 653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cody-v-schwill-illappct-1939.