Vermont Street M. E. Church v. Brose

104 Ill. 206, 1882 Ill. LEXIS 286
Illinois Supreme Court·Decided September 28, 1882·Published·Cited by 34 cases

Opinion

Mr. Chief Justice Scott

delivered the opinion of the Court:

The petition in this case was brought by John G. Brose, against the Trustees of the Vermont Street M. E. Church, to establish a mechanic’s lien on the property belonging to the defendant corporation. Under a written contract between the parties, petitioner undertook to erect for defendants a church edifice, according to plans and specifications referred to and made a part of the contract. That part of the work which petitioner was to do was not completed by the time mentioned in the contract. It is alleged it was on account of the fault of defendants the delay occurred. The case is not defended on the ground the work was not finished within the time limited by the contract. It is sufficiently shown, both by the averments of the petition and the evidence, the time for doing the work was extended by mutual agreement.

In two particulars there is some ambiguity in the contract,—first, who was to furnish the “stone for the front and the footing;” and second, to whose “full and complete satisfaction” was the work to be “finished and completed;” but it is thought it readily admits of a construction consistent with the acts of the parties. By ascertaining the meaning of the contract in these respects the case will be relieved of much difficulty. Considering the questions in the order stated, it will be seen that in one part of the contract it is provided the work shall be completed by. a day fixed, “weather permitting, and stone for front and footing being furnished. ” Standing alone, this clause would be readily understood to obligate defendants to furnish “stone for front and footing,” because petitioner was not. bound to finish the work unless the wreather would permit, and the “stone for front and footing” was furnished. The difficulty arises out of a clause in the covenanting part of the contract on the part of the defendants, wherein they agree to pay petitioner a certain sum of money in consideration he will furnish “all materials, and fully and faithfully execute the work to the full and complete satisfaction of the architect, ” and at the time mentioned. Following, as this does, the former provision cited, it may well be understood to bind petitioner only to furnish “all the materials” necessary to complete the work which defendants had not previously contracted to furnish. It will be seen the subsequent conduct of the parties renders this construction of the contract reasonably certain. It is allowable always to look to the interpretation the contracting parties place on their agreement, either contemporaneously or in its performance, for assistance in ascertaining its true meaning. No extrinsic aid can be more valuable. In their original answer defendants admitted the allegation of the petition they were to furnish the “stone for front and footing, ” but in their answer to an amended petition that admission was withdrawn. Without attaching much importance. to what the answers contained, as neither of them was under oath, it is of much more importance to ascertain what the parties did in the performance of the contract. In that respect their acts are the result of their understanding of their agreement, and afford valuable® aid in ascertaining its meaning. Looking at what was done, it is seen defendants from first to last, while the work wras in progress, recognized their obligation to furnish “stone for front and footing,” and did in fact furnish that which was used in the building. Both parties so understood the agreement, in this respect, while it was being performed, and their conduct is consistent with a reasonable construction of the contract.

As respects the second inquiry, it is provided the work is to be done by petitioner in a skillful and workmanlike manner, to the “full and complete satisfaction of Geo. H. Bdbroke, architect, or his assistant superintendent, John Crockett. ” Under this clause of the agreement, if the work was done to the satisfaction of either party named it would seem it would be in conformity with the contract. It is not agreed that both of them shall be satisfied with the work. Should either of them approve the work it would be sufficient. It is true, in a subsequent clause of the agreement it is said the work shall be done to the “full and complete satisfaction of Geo. H. Edbroke, architect. ” Here again the conduct of the parties renders valuable aid in ascertaining the true construction of the agreement in this respect. It is evident it was not intended that Edbroke, who drew the plans and specifications, was to have the immediate and personal superintendence óf the work. He says himself he did not see the work from the time of its commencement till he was called to inspect it in February, 1877, and that John Crockett was appointed by him local superintendent. What he did in this respect conforms to a true understanding of the contract. The work was to be done under the supervision of Crockett, and if satisfactory to him, that would be a compliance with the contract. Both by the terms of the agreement and the appointment of the principal architect, the local superintendent had the supervision' of the work as it was being done, and it would be most unreasonable if, after the work had been done under the immediate direction of the local superintendent, that Edbroke should be permitted afterwards to say it was not done to his “satisfaction,” and reject all that petitioner had done in the erection of the building. This would be most unreasonable, as well as unjust, and esj>ecially so when Edbroke had not seen the work as it progressed, and had absented himself, and left it all to the supervision of Crockett, the local superintendent. Such a result could not have been in the contemplation of the parties, nor will the contract bear any such construction.

Having ascertained the meaning of the contract, so far as relates to the principal matters in contention, but few words of illustration will be necessary to dispose of the objections taken to the decree of the circuit court. As has been seen, the time for completing the work was extended by mutual agreement, and there is no just ground for complaint on • that score. The delay, arose principally out of the neglect of defendants to furnish stone, as was their duty under the contract. But the most serious complaint is made as to the manner in which the stone was laid on the Eighth street front of the building. Two objections are insisted upon: First, the stone are not set far enough in the wall to give it sufficient strength; and, second, they are set on edge, when skillful workmanship would require they should be laid as in their “natural bed.” As respects the point made the face stone is not laid far enough in the wall to give it the requisite strength to'support the superstructure that was proposed to be erected thereon, it may be said the evidence is conflicting. On this question a good deal of testimony was taken. That given by petitioner, and witnesses introduced on his behalf, seems entitled to most weight. All the witnesses skilled in that kind of labor say it is quite difficult, if not impracticable, to ascertain how far face stone extends into the wall, after it is finished, without tearing it down. Very unsatisfactory are all outside measurements. Witnesses that did the work, of course had the best opportunity to know how far the stone extended into the wall, and relying on the testimony given by that class of witnesses, as the court was warranted in doing, its conclusion was justified the work was reasonably well done in that regard.

Free access — add to your briefcase to read the full text and ask questions with AI

Vermont Street M. E. Church v. Brose, 104 Ill. 206, 1882 Ill. LEXIS 286 (Ill. 1882).

104 Ill. 206 (Vermont Street M. E. Church v. Brose) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Corbetta Construction Co. v. Lake County Public Building Commission
381 N.E.2d 758 (Appellate Court of Illinois, 1978)
Castle v. Hulcher
312 N.E.2d 836 (Appellate Court of Illinois, 1974)
Cody v. Schwill
23 N.E.2d 223 (Appellate Court of Illinois, 1939)
Sumner v. Smysor
273 Ill. App. 588 (Appellate Court of Illinois, 1933)
Edward Edinger Co. v. Willis
260 Ill. App. 106 (Appellate Court of Illinois, 1931)
Granette Products Co. v. Arthur H. Neumann & Co.
221 N.W. 197 (Supreme Court of Iowa, 1928)
Chicago Title & Trust Co. v. Merchants Loan & Trust Co.
244 Ill. App. 302 (Appellate Court of Illinois, 1927)
Lowe v. Condit
227 Ill. App. 11 (Appellate Court of Illinois, 1922)
Hatcher v. Ferguson
198 P. 680 (Idaho Supreme Court, 1921)
Sholl Bros. v. Peoria & Pekin Union Railway Co.
114 N.E. 529 (Illinois Supreme Court, 1916)
Breen v. Cameron
157 N.W. 500 (Supreme Court of Minnesota, 1916)
Connelly v. Wallin
181 Ill. App. 212 (Appellate Court of Illinois, 1913)
Elgin, Joliet & Eastern Railway Co. v. Northwestern National Bank
165 Ill. App. 35 (Appellate Court of Illinois, 1911)
Swanson v. James L. Lederer & George B. Levee Amusement Co.
163 Ill. App. 69 (Appellate Court of Illinois, 1911)
Burgin v. . Smith
66 S.E. 607 (Supreme Court of North Carolina, 1909)
Lunsford & Withrow & Co. v. Wren
63 S.E. 308 (West Virginia Supreme Court, 1908)
Evans v. Ross Construction Co.
142 Ill. App. 375 (Appellate Court of Illinois, 1908)
David Bradley Manufacturing Co. v. Tedford
127 Ill. App. 1 (Appellate Court of Illinois, 1906)
Coulter v. B. F. Thompson Lumber Co.
142 F. 706 (Sixth Circuit, 1906)
Walker v. Illinois Central Railroad
74 N.E. 812 (Illinois Supreme Court, 1905)