Lunsford & Withrow & Co. v. Wren

63 S.E. 308, 64 W. Va. 458, 1908 W. Va. LEXIS 67
CourtWest Virginia Supreme Court
DecidedDecember 9, 1908
StatusPublished
Cited by14 cases

This text of 63 S.E. 308 (Lunsford & Withrow & Co. v. Wren) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lunsford & Withrow & Co. v. Wren, 63 S.E. 308, 64 W. Va. 458, 1908 W. Va. LEXIS 67 (W. Va. 1908).

Opinion

Miller, Judge:

J. K. Lunsford, July 2, 1906, entered into a contract with “The Institutional Baptist Church, a corporation,” so styled therein, whereby in consideration of four dollars per cubic yard for stone work in the wall, he agreed to furnish all necessary labor, material, etc., and to build and complete, according to the drawings and specifications of Babenstein & Warne, Architects, the foundation walls for a church edifice, in the city of Huntington, payments to be made from time to time upon the certificates of the architects, when work to the amount of two hundred dollars had been completed and accepted by the architects. The contract also provided, [461]*461that Lunsford should prosecute the work diligently and complete the same within forty days from the time of beginning, excluding certain days in which he might be delayed, and with which he should have credit, it being stipulated in the contract that for every day’s delay due to the fault of the other party, he should have credit for two days; and that should he fail on his own account to complete the work within the time specified, then he should pay to the other party at the rate of $5.00 per day for each day the completion of the work should be delayed beyond the time provided, it being stipulated that the other party to the contract should be injured to that extent by reason of its inability to occupy the building for the period of delay.

The evidence of Lunsford, not materially contradicted, shows that lie began quarrying stone July 5, but because of delays in the excavation was unable to begin laying stone until some time in August; in one place he says he was delayed twelve or fifteen days, may be more, on this account; he was afterwards further delayed by the church authorities failing to furnish gravel footing for the foundation, and in this way, and by rainy weather, was delayed altogether about thirty-five days, and according to. his affidavit to his lien did not complete the wall until about October 31, but according to his evidence before the commissioner not until October 1st.

In the meantime, August 24, 1906, before completion of the work by Lunsford, “ The Institutional Baptist Church” by C. E. Wren, President of the Board of Trustees, entered into another contract with A. F. Withrow & Co., whereby without any reference to the Lunsford contract for building-the foundation, Withrow & Co., agreed to proceed immediately, and did proceed about August 28, to erect the church building, according to plans and specifications of said architects. Their contract ivas to purchase the necessary materials, have them delivered on the premises and placed in position in the building, and to complete the building as soon as practicable, consistent with good workmanship; the Church to reimburse them for their outlay for labor and material on or before the tenth day of each month, succeeding that in which they should be made, on vouchers approved by the [462]*462architects before they were paid, and Withrow & Co., were to be paid eight per cent on the aggregate sum expended by them for such labor and materials when the contract should be fully completed. In addition to this, the Church agreed to pay the freight and charges on all tools, derricks and other equipments, but no salary was to be allowed any member of the firm, the Church, however, was to pay the expenses of a foreman, engineer, and for fuel and water. Other provisions of the contract are immaterial in the present controversy.

After the contract with Withrow & Co., the further work of building the foundation seems to have been proceeded with by Lunsford under the supervision of J. S. Higgs, Superintendent for Withrow & Có., and although Lunsford and Withrow & Co., deny that the latter assumed the contract of Lunsford, yet Lunsford seems to have looked to and received payment from Withrow & Co., for all work and materials furnished. Wren, the pastor of the church and president of the Board of Trustees, claims that Withrow & Co., at the time of the contract, assumed the contract of Lunsford; and it is shown that, of the $919.60 acknowledged as received by Lunsford on account of the aggregate of his claim of $1423.60, the sum of $499.10 was paid him by Withrow & Co. The latter claim the payments by them to Lunsford were merely accommodations to the Church and to help along the work.

At all events, the work proceeded under Lunsford’s contract until October 31, when he claims to have completed it; and under the Withrow & Co. contract until about November 13, when they claim they ceased work, and at which time they had expended for labor and material, including $138.75 advanced for gravel furnished, $499.10 paid Luns-ford, and $235.28, 8 per cent commissions, claimed by them on disbursements, the sum of $3176.30, and there has been paid them in sums at from $5.00 to $200.00, only $658.18.

The reason assigned by Withrow & Co. for not proceeding further with their contract, was the failure of the church to make payments as provided in the contract.

About November 27, 1906, Lunsford made up and filed in the county clerk’s office, his mechanic’s lien, claiming a [463]*463balance of $516.00 against the church building and lots; and Withrow & Co., January 14, 1907, made up and filed their lien against the same property for the balance of their claim, amounting to $2,583.95.

Lunsford, March 6, 1907, and Withrow & Co., May 27, 1907, instituted in the circuit court of Cabell county, the present suits to enforce payment of their respective liens. C. E. Wren, W. H. Ball, W. A, Ripley, J. W. Perry and Emma Mills, Trustees of Institutional Baptist Church, and The Huntington Land Company, a corporation, were the only parties made defendants to these suits, except that Lunsford, the plaintiff in the first suit, was made defendant in the suit of Withrow & Co.

April 1, 1907, Wren and the other trustees filed their general demurrer to the bill of Lunsford; and July 1, following, they and Lunsford filed their demurrer to the bill of Withrow & Co., and on the same day, both causes being brought on to be heard together, the demurrer in each case was overruled and leave given the defendants to answer. But without awaiting the answers, both causes were on the same day referred to a commissioner, who was by the order of reference, directed to report as follows: First, whether or not the plaintiff in either of said suits is entitled to maintain a • lien against said church property; second, the amounts of said liens; third, what other liens, if any, exist against said property, and the priorities thereof; and fourth, any other matter required by either of the parties in writing, or deemed pertinent by the commissioner.

Pending proceedings before said commissioner, August 10, 1907, Wren and .others, trustees, filed with the commissioner answers to each of said bills; and the Huntington Land Company also lodged in the papers an answer to the bill of Lunsford; but these answers were never filed in court until the final decree appealed from, pronounced December 13, 1907, and there were never any replications thereto.

The final decree adjudged the plaintiffs entitled to enforce their respective liens as reported by the commissioner, and overruling the several exceptions of defendants thereto, further adjudged there was due Lunsford on his lien $261.29, to Withrow & Co. on their lien $2655.09, and that there was [464]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Sheet Metal Corp. v. Continental-Diamond Springs Associates
10 Va. Cir. 451 (Virginia Beach County Circuit Court, 1988)
James T. Bush Construction Co. v. Patel
10 Va. Cir. 323 (Richmond County Circuit Court, 1987)
Walt Robbins, Inc. v. Damon Corporation
348 S.E.2d 223 (Supreme Court of Virginia, 1986)
Osnes v. Morris
298 S.E.2d 803 (West Virginia Supreme Court, 1982)
Brady v. Reiner
198 S.E.2d 812 (West Virginia Supreme Court, 1973)
Gaymont Fuel Co. v. Price
65 S.E.2d 393 (West Virginia Supreme Court, 1951)
Forsberg v. Zehm
143 S.E. 284 (Court of Appeals of Virginia, 1928)
Pfaff & Smith Builders Supply Co. v. Mason
137 S.E. 356 (West Virginia Supreme Court, 1927)
W. Bateson & Co. v. Baldwin Forging & Tool Co.
84 S.E. 887 (West Virginia Supreme Court, 1915)
Atlantic Terra Cotta Co. v. Moore Construction Co.
80 S.E. 924 (West Virginia Supreme Court, 1914)
Houston Lumber Co. v. Wetzel & Tyler Railway Co.
72 S.E. 786 (West Virginia Supreme Court, 1911)
Caldwell & Drake v. Schmulbach
175 F. 429 (N.D. West Virginia, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
63 S.E. 308, 64 W. Va. 458, 1908 W. Va. LEXIS 67, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lunsford-withrow-co-v-wren-wva-1908.