W. Bateson & Co. v. Baldwin Forging & Tool Co.

84 S.E. 887, 75 W. Va. 574, 1915 W. Va. LEXIS 212
CourtWest Virginia Supreme Court
DecidedFebruary 2, 1915
StatusPublished
Cited by9 cases

This text of 84 S.E. 887 (W. Bateson & Co. v. Baldwin Forging & Tool Co.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. Bateson & Co. v. Baldwin Forging & Tool Co., 84 S.E. 887, 75 W. Va. 574, 1915 W. Va. LEXIS 212 (W. Va. 1915).

Opinion

MiddeR, Judge:

Plaintiffs, principal contractors, sued defendant, to enforce against its property their alleged lien for labor performed and material furnished in the execution of a contract to construct a factory building in accordance with the plans and specifications covered by the contract, impleading also numerous subcontractors who are alleged to have performed labor and furnished material in the execution of said contract.

Answers and cross-answers, were filed by the Baldwin Forging & Tool Company, and by several of the subcontractors, and answers to said cross-answers of the subcontractors -were also filed by the Baldwin Forging & Tool Company.

[576]*576After issues were joined on these pleadings the canse was referred to a master, to report the property of defendant company, and the several liens thereon, and the priorities thereof, and from the decree on that report and the several exceptions thereto, the Baldwin Forging & Tool Company has appealed, and Bateson & Company, without themselves applying for or obtaining an appeal from the decree against them in favor of appellant on its cross-answer, for $22,893.15, and as found by the commissioner, have attempted to cross assign error, on appellant’s appeal from the decree against it in favor of other appellees, and adjudicating large sums against its property in their favor, and enforcing the liens therefor.

We will first ■ consider and dispose of the errors assigned and relied on in the decree respecting the

Lien of C. E. Shailuck, Special Receiver.

The first point of error raised by demurrer to the cross-answer, and by exceptions to the commissioner’s report, overruled, is that the account served on appellant and recorded, and exhibited with the bill, is not such an itemized account as is required by the statute to constitute a good and valid lien on appellant’s property. In support of this proposition it is said, and the fact is, that the account begins with an item on September 1, 1910, and then continues with numerous intervening items down to and including two items of November 26, 1910, the first for 11,900 bricks, by L. S. & M. S. Car No. 31797, the second, 4,500 bricks, hauled by wagon, all totaling 526,100 bricks, at $7.50 per thousand, or $3,945.75. And that following these items and footings is an item under August-, 1910, 295,716 bricks, $2,217.87, and after them the credit item, October 4, 1910, $2,217.87; and then the following credit under date 1910, month and day not indicated, “Brick used by W. Bateson & Co., elsewhere than in Baldwin Forging & Tool Company plant and building 187 (meaning 187,000) brick at 7.50 per M. $1402.50. To balance $2543.25.”

The contention is that as the credit item, 187,000 bricks, is not itemized, and the account on its face does not show what items on the debit side are covered by this credit item, so as to identify and enable the owner to definitely trace the same, [577]*577it is not an itemized account within the meaning of section 3, chapter 75, serial section 3844, Code 1913, and is therefore void on its face, and that the demurrer to the cross bill answer, and appellant’s exceptions to the commissioner’s report, allowing the same, should have been sustained, and relief denied.

If on its face .the lien is void, as contended, the demurrer and exceptions to the commissioner’s report properly presented the question. Hill Clutch Co. v. Independent Steel Co. of America, 74 W. Va. 353, 82 S. E. 223. The statute, section 3, chapter 75, serial section 3844, requires an itemized account, and section 4, serial section 3845, of the same chapter, requires that within sixty days after ceasing to labor on, or furnish material, the person desiring to avail himself of the lien provided by the statute, must file with the clerk of the county court, “a just and true account of the amount due him, after allowing all credits, together with a description of the property”, &c. Lumping items, or lumping estimates, at least on the debit side, will not do. Niswander & Co. v. Black, 50 W. Va. 188. In the case last cited, while the lien was held bad as to the lumping estimate therein, it was held good as to all items properly itemized. So, an account containing items furnished beyond the period of nine months from the date of the notice to the owner, contrary to said section 3, of chapter 75, was held good as to the items furnished within that period. Huntington Plumbing & Supply Co. v. McGuffin, 75 W. Va. 78, 83 S. E. 194. The lump credit of 187,000 bricks in the account now under consideration, however, shows that of the whole number of bricks, itemized on the other side of the account, that number, whether furnished for the purpose’of constructing the defendant’s plant, or not, did not in fact go into that construction, for they are credited back, and a lien is not claimed for them. The question recurs, is the account void on its face for this reason ?

True, as argued, the demurrer, if they be well pleaded, admits the facts alleged, but if the exhibit vouched therefor contradicts or conflicts with the allegations we take the exhibit as showing the facts and not the allegations of the pleading. Richardson v. Ebert, 61 W. Va. 523; Board of Education v. Berry, 62 W. Va. 433, 436; Lunsford v. Wren, 64 W. Va. 458, 466; Lumber Co. v. Railway Co., 69 W. Va. 682, 688; [578]*578Plaster v. Harmon, 70 W. Va. 634, 636. And in a suit to enforce a mechanic’s lien, if the hill and exhibits read together, show all the facts necessary to be alleged, the bill is sufficient in law, and the demurrer should be overruled. Grant v. Cumberland Valley Cement Co., 58 W. Va. 162. By these authorities either party may look to the exhibit on demurrer, and neither is bound by any of the allegations in conflict or inconsistent therewith. Is this lien void then on its face, regardless of what is said about it in the other -part of the pleading ?

It will be observed that the statute requires an itemized account of the labor done and material furnished by a subcontractor “for the construction, alteration, * * * * of any house or other structure.” The account in this case complies .literally with this requirement, and is verified by the oath of the claimant, as being a just and true account. But the statute does not, in terms at least, require that the credits be itemized. What is required is an itemized account of the labor done or material furnished, and the affidavit prescribed by section three requires that affiant shall swear that a certain sum is owing on the account after allowing all just and true credits made thereon; and section four requires the account to state the “amount due him, after allowing all credits.” Neither section requires the credits to be itemized. In Grant v. Cumberland Valley Cement Co., supra, we decided, point 2 of the syllabus, with respect to both debits and credits that itemization in form was unnecessary, if it appear in substance and effect. In that case the account in question contained a credit, “By aggregate of all payments made to said James Grant on account of salary up to this date, $4,000.00”, and it was held good, the reasons for so holding being set out in the opinion, with citation of authorities.

So we are disposed to hold this account valid on its face.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gooch v. West Virginia Department of Public Safety
465 S.E.2d 628 (West Virginia Supreme Court, 1995)
Gamble v. Main
300 S.E.2d 110 (West Virginia Supreme Court, 1983)
Thacker v. Tyree
297 S.E.2d 885 (West Virginia Supreme Court, 1982)
Rural Plumbing & Heating, Inc. v. Hope Dale Realty, Inc.
140 S.E.2d 330 (Supreme Court of North Carolina, 1965)
Northern Virginia Savings & Loan Ass'n v. J. B. Kendall Co.
135 S.E.2d 178 (Supreme Court of Virginia, 1964)
Looney v. Leeper
1930 OK 455 (Supreme Court of Oklahoma, 1930)
Hough v. Watson
112 S.E. 303 (West Virginia Supreme Court, 1922)
Pittsburgh Steel Product Co. v. Huntington Masonic Temple Ass'n
94 S.E. 127 (West Virginia Supreme Court, 1917)
Gist v. Virginian Railway Co.
90 S.E. 554 (West Virginia Supreme Court, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
84 S.E. 887, 75 W. Va. 574, 1915 W. Va. LEXIS 212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-bateson-co-v-baldwin-forging-tool-co-wva-1915.