Edward Edinger Co. v. Willis

260 Ill. App. 106, 1931 Ill. App. LEXIS 1157
CourtAppellate Court of Illinois
DecidedJanuary 26, 1931
DocketGen. No. 8,427
StatusPublished
Cited by16 cases

This text of 260 Ill. App. 106 (Edward Edinger Co. v. Willis) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward Edinger Co. v. Willis, 260 Ill. App. 106, 1931 Ill. App. LEXIS 1157 (Ill. Ct. App. 1931).

Opinion

Mr. Presiding Justice Shurtleff

delivered the opinion of the court.

This appeal is brought to review a decree of the circuit court of Macon county in two cases brought to foreclose mechanics’ liens on the property of The First Baptist Church, a corporation, of Decatur, which arose out of a contract to build a new church for that corporation, one Ernest Widmer being the general contractor.

The first case designated in the records was instituted by Edward Edinger Company as a corporation by bill filed September 11, 1925, to foreclose a-lien for cut stone furnished as subcontractor, naming as parties defendant J. E. Willis et al., trustees of The First Baptist Church, Margaret Widmer, administratrix of the estate of Ernest Widmer, deceased (the contractor), and Columbia Casualty Company, a corporation (the surety), but the summons was served only upon the trustees. On* February 8, 1926, The First Baptist Church of Decatur, a corporation, was made defendant, entered its appearance and filed answer. The suit was dismissed as to Columbia Casualty Company without service of summons or notice. The trustees also filed their answer to the amended bill. Both answers are substantially alike and admit the making of the contract between the church corporation and Ernest Widmer in his lifetime for construction of a new church building in Decatur; that he died on July 24, 1925, without completing the job, and that the Columbia Casualty Company, his surety, entered upon the completion of the contract; denies any right to lien of the complainant Edinger, and further alleges that no notice of lien was given to the owner within 60 days after final- delivery of any materials by complainant Edinger, and further denies that any foreclosure proceeding was instituted by Edinger Company against said First Baptist Church within four months thereafter. Subsequently thereto it developed that Edward Edinger Company was a partnership and by leave of the court the copartners were substituted as complainants in lieu of the corporation.

While this suit was still pending and undetermined, the general contract was completed by the Columbia Casualty Company, and being unable to arrive at a settlement with the owner, the Columbia Casualty Company, appellant, filed its bill of foreclosure in the circuit court of Macon county, the proceedings being instituted on April 30, 1926.

The bill sets forth that on July 30, 1924, the defendant, The First Baptist Church of Decatur, Illinois, a corporation, was the owner of lots one and two in block eight of Western Addition to the City of Decatur, and that on that date it entered into a contract in writing with one Ernest Widmer for the construction of a church building, copy of the contract and specifications being attached to the bill of complaint. The bill further sets forth the death of Widmer during the construction and before completion; that the complainant surety company entered upon the construction of the work and completed same, and that the building was tendered to the owner on March 11, 1926, and was accepted on March 13, 1926. The bill further alleged that payment became due by the terms of the contract on April 12, 1926, but that payment was refused. It appeared by the construction contract made a part of the bill of complaint that the time of completion was originally fixed as of July 1, 1925, but the bill alleged that an extension of time had been given, extending the time to September 1, 1925.

By amendment to the bill of complaint it was further alleged that the owner did not give possession of the premises on or before September 1, 1924, as the contract between the defendant and The First Baptist Church, and the said Ernest Widmer required, but on the contrary did not give possession thereof until some time during the month of November, 1924.

A written contract was entered into between appellee and Widmer, doing business as the Widmer Construction Company, on July 30, 1924, in and by which contract Widmer agreed, for the sum of $144,-000, to erect for appellee a church building according to the plans and specifications of the architect. All of the rights and liabilities of the parties arise out of this contract, which is the basis of this case.

Among the other provisions this contract provides:

Art. I. That Widmer was to furnish the material and build the building according to the specifications of the architect. He was also to receive a commission of two per cent for supervising the removal of the brick building already on the lot to the rear of the lot. (This building was incorporated into the new building, as a part thereof.)

Art. III. Which reserved to the appellee the right to make alterations in the plans and specifications; but such changes could only be made upon the written order of the architect.

Art. V. Provided that if the contractor did not show proper diligence in prosecuting the work the appellee could furnish labor and materials upon giving the contractor five days’ notice in writing (this at the expense of the contractor). If the architect certified the neglect of the contractor this was sufficient grounds therefor, and the appellee could take over the work and complete it at the cost of the contractor; and the architect’s certificate should be final as to such costs.

Art. VI. Provided for the completion of the building by July 1, 1925, provided the contractor got possession of the premises by September 1, 1924. This article also provides for a forfeit of $50 per day for every day the building remained uncompleted after that date or the date to which extended, by the architect, as liquidated damages.

Art. VII. Provided that should the work be delayed by any act or failure of the appellee or the architect to do anything, the time for the completion of the building should be extended for a period equivalent to the time lost by reason of the conduct of appellee or the architect. Provided, that no allowance could thus be made for such extension of time unless a written claim was made to the architect asking for an extension, within 24 hours after the occurrence of such delay.

Art. IX. Provided that any controversy arising between the contractor and the appellee should be settled by the architect, whose decision should be final (except certain matters might be arbitrated); but no request for arbitration was ever asked by either party under this clause and, therefore, it is not in question.

Art. X. Provided that while $144,000 was the contract price, the list of changes attached to the contract formed a part of it, and that the appellee might accept any or all of such changes at any time before the work was actually started on them; and provided the amount set opposite each change should be deducted from the contract price.

This article also provided the manner of making-payments by appellee as follows: “that such sum shall be paid in current funds by the owner to the contractor in instalments, upon written certificates of the architect that payments have become due. Each certificate shall represent 85 per cent of the architect’s estimate of the value of the labor incorporated in the building and material delivered on the site sincé the preceding- certificate was issued. The 15 per cent reserved shall be payable when the final certificate is issued.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Benford v. Everett Commons, LLC.
2014 IL App (1st) 131231 (Appellate Court of Illinois, 2014)
Sarnoff v. De Graf Brothers, Inc.
554 N.E.2d 335 (Appellate Court of Illinois, 1990)
Roy Strom Excavating & Grading Co. v. Miller-Davis Co.
509 N.E.2d 105 (Appellate Court of Illinois, 1986)
Allied Contracting Co. v. Bennett
442 N.E.2d 326 (Appellate Court of Illinois, 1982)
Fedco Electric Co. v. Stunkel
395 N.E.2d 1116 (Appellate Court of Illinois, 1979)
Fischer v. McHenry State Bank
392 N.E.2d 995 (Appellate Court of Illinois, 1979)
Pathman Construction Co. v. Hi-Way Electric Co.
382 N.E.2d 453 (Appellate Court of Illinois, 1978)
Wiebe Construction Co. v. School District of Millard
255 N.W.2d 413 (Nebraska Supreme Court, 1977)
Gamm Construction Co. v. Townsend
336 N.E.2d 592 (Appellate Court of Illinois, 1975)
Royal Ornamental Iron, Inc. v. Devon Bank
336 N.E.2d 105 (Appellate Court of Illinois, 1975)
Roosevelt University v. Mayfair Construction Co.
331 N.E.2d 835 (Appellate Court of Illinois, 1975)
Ahmer v. Peters
149 N.E.2d 503 (Appellate Court of Illinois, 1958)
Clement, Et Ux. v. Pensacola Builders Supply Co.
189 So. 852 (Supreme Court of Florida, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
260 Ill. App. 106, 1931 Ill. App. LEXIS 1157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-edinger-co-v-willis-illappct-1931.