Sarnoff v. De Graf Brothers, Inc.

554 N.E.2d 335, 196 Ill. App. 3d 535, 143 Ill. Dec. 400, 1990 Ill. App. LEXIS 386
CourtAppellate Court of Illinois
DecidedMarch 28, 1990
Docket1-88-3810
StatusPublished
Cited by3 cases

This text of 554 N.E.2d 335 (Sarnoff v. De Graf Brothers, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sarnoff v. De Graf Brothers, Inc., 554 N.E.2d 335, 196 Ill. App. 3d 535, 143 Ill. Dec. 400, 1990 Ill. App. LEXIS 386 (Ill. Ct. App. 1990).

Opinion

PRESIDING JUSTICE CERDA

delivered the opinion of the court:

Defendant, De Graf Brothers, Inc., appeals from the entry of summary judgment in the favor of plaintiff, Norton Sarnoff, in an action for damages caused because of defendant’s defective concrete construction work in plaintiff’s building. Defendant argues that the trial court erred in entering summary judgment because there were disputed issues of fact concerning the amount of damages and the bias of the decision by the architect and third-party defendant, Jerome Soltan, who found defendant responsible for the defective work. Defendant also argues that the trial court erred in striking that portion of a counteraffidavit it filed in which the affiant gave his opinion that, rather than defendant, the architect was responsible for the defective work.

Plaintiff alleged that he entered into a written contract with defendant to provide concrete work and that defendant warranted that the work would be free of defects. The work was completed around March 1984. Plaintiff alleged that he observed that the concrete floor was emitting dust, spalling, flaking and deteriorating within the first year. Plaintiff hired an engineer to inspect the floor; the cost of testing was $2,670. The test report stated that the concrete work had been improperly performed. Plaintiff alleged that the contract provided that defendant was responsible for the cost of testing if the tests revealed a failure in workmanship.

It was further alleged that on January 8, 1987, the architect made a decision finding defendant responsible for the defective work. Plaintiff demanded that defendant repair the defects but defendant refused. Under the contract, if a demand for arbitration was not made within 30 days of the architect’s decision, the decision was final and binding. Defendant did not demand arbitration, and plaintiff alleged that defendant was thereby bound by the architect’s decision and was liable for the repair. Plaintiff also requested damages of $15,000 for the repairs.

Plaintiff and defendant entered into AIA Document A101, “Standard Form of Agreement Between Owner and Contractor.” Incorporated into the contract was AIA Document A201, “General Conditions of the Contract for Construction.” The following terms were included in this latter document. Nothing in the documents was to create any contractual relationship between the architect and the contractor. The architect was the owner’s representative during construction and until final payment. Claims, disputes and other matters in question between the contractor and the owner relating to the execution or progress of the work or the interpretation of the contract documents were to be referred initially to the architect for decision which was to be rendered in writing within a reasonable time. In the architect’s capacity as interpreter and judge, he was to exercise his best efforts to ensure faithful performance by both the owner and the contractor and was not to show partiality to either.

Any claim, dispute or other matter referred to the architect (with certain exceptions not applicable here) was subject to arbitration upon the written demand of either party. If an architect’s decision was made in writing and stated that it was final but subject to appeal, a demand for arbitration was to be made within 30 days after the decision was received. The failure to demand arbitration within this period resulted in the architect’s decision becoming final and binding upon the owner and contractor.

The contract also provided that the architect was not responsible for the acts or omissions of the contractor or any other persons performing any of the work. The contractor warranted to the owner and architect that all work was of good quality, free from faults and defects, and in conformance with the contract documents. A claim of damage to property was to be made in writing to the party claimed to be responsible within a reasonable time after the first observance of the damage. The making of final payment was not to constitute a waiver of claims arising from faulty or defective work appearing after substantial completion. The architect had the authority to require special inspection or testing of the work even when completed if his opinion was that it was necessary or advisable to ensure the proper implementation of the intent of the contract documents. If special inspection or testing was deemed necessary by the architect after the commencement of work and revealed a failure of the work to comply with the contract requirements, the contractor was to bear all costs.

The contractor was to promptly correct all work rejected by the architect as defective or failing to conform to the contract documents whether observed before or after substantial completion and whether or not fabricated, installed or completed. The contractor was to bear all cost of correcting such rejected work. If within one year after the date of substantial completion or within such longer period as may be prescribed by law any of the work was found to be defective, the contractor was to correct it promptly after receipt of written notice. If the contractor failed to correct defective work, the owner could correct it.

Attached to the complaint was a letter dated January 8, 1987, from the architect to plaintiff and defendant which stated that after reviewing a report from a material and concrete consultant firm, his final decision was that a portion of the concrete floor had been wearing at a relatively rapid rate and that the problem was due to improper finishing of the cement contractor.

Defendant admitted in its answer to a request to admit facts that it never demanded arbitration, that it knew the concrete floor was emitting dust, and that it received a copy of the architect’s decision.

Plaintiff filed a motion for summary judgment in which he argued that the failure of defendant to demand arbitration after receipt of the architect’s final decision rendered it binding upon the parties under the contract. Plaintiff quoted from the contract’s provisions that: the contractor warranted that all work was to be of good quality and free from faults and defects; the contractor was to bear costs of special testing after the commencement of the work if the architect determined that it was required; and that the contractor was to correct defective work.

Plaintiff filed a “certification in lieu of affidavit” which stated: that defendant was paid the full amount of the contract price for the installation of the concrete floor; that during the first year following completion he noticed the floor was emitting dust, flaking and deteriorating; that during the first year defendant was notified of the conditions and undertook some remedial steps to correct the defect; that defendant agreed to engage engineers to test the floor to determine the cause of the problem; and that he paid $2,670 for testing and $31,900 to correct the defective condition.

The architect’s certification was also filed and stated that on numerous occasions he requested that defendant repair the deteriorating condition of the concrete floor.

Defendant was granted permission to file a third-party complaint against the architect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jetz Service Co., Inc. v. Jay & Harry Corp.
2025 IL App (1st) 242446-U (Appellate Court of Illinois, 2025)
Drinane v. State Farm Mutual Automobile Insurance
584 N.E.2d 410 (Appellate Court of Illinois, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
554 N.E.2d 335, 196 Ill. App. 3d 535, 143 Ill. Dec. 400, 1990 Ill. App. LEXIS 386, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sarnoff-v-de-graf-brothers-inc-illappct-1990.