Freeport Construction Co. v. Star Forge, Inc.

378 N.E.2d 558, 61 Ill. App. 3d 999, 19 Ill. Dec. 57, 1978 Ill. App. LEXIS 3123
CourtAppellate Court of Illinois
DecidedJune 29, 1978
Docket77-184
StatusPublished
Cited by21 cases

This text of 378 N.E.2d 558 (Freeport Construction Co. v. Star Forge, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Freeport Construction Co. v. Star Forge, Inc., 378 N.E.2d 558, 61 Ill. App. 3d 999, 19 Ill. Dec. 57, 1978 Ill. App. LEXIS 3123 (Ill. Ct. App. 1978).

Opinion

Mr. PRESIDING JUSTICE SEIDENFELD

delivered the opinion of the court:

This appeal raises a preliminary question as to the jurisdiction of courts to review a determination by the American Arbitration Association that an arbitrator should not be removed for alleged “evident partiality.” (Ill. Rev. Stat. 1975, ch. 10, par. 112(a) (2.) There is the further question whether the award should be vacated or whether the cause should be remanded for the taking of further evidence.

I

The claim that one of the panel of three arbitrators was not impartial was made to the American Arbitration Association during the pendency of the hearing before the arbitrators. Freeport Construction Company suggests that the determination of the American Arbitration Association, after an investigation of the claim that there was no bias or partiality, is binding on the court. We conclude, however, that the trial court and on appeal the reviewing court have the power to decide whether the arbitrator was subject to removal for partiality or bias even though the American Arbitration Association has investigated the matter and reached a conclusion on the issue.

The submission to arbitration was made under the terms of a construction contract and involved generally a dispute between Freeport Construction Company, the general contractor (Freeport), and the owner, Star Forge, Inc., arising out of the building of a new manufacturing facility. The arbitration clause of the construction contract specifically incorporated the Construction Industry Arbitration Rules of the American Arbitration Association, which state in pertinent part:

“No person appointed as a neutral arbitrator shall serve if he has any financial or personal interest in the result of the arbitration, unless the parties, in writing, waive such disqualification.
# # #
A person appointed as a neutral arbitrator shall disclose any circumstances likely to create a presumption of bias or which might disqualify him as a neutral arbitrator. * * * Upon receipt of such information from any source, the AAA shall immediately communicate it to the parties. If a party challenges an arbitrator, he shall be replaced, unless the AAA determines that the circumstances do not disqualify the arbitrator from serving as a neutral.” (American Arbitration Association, Construction Industry Arbitration Rules §§11 and 18 (1974).)

The rules themselves do not expressly provide that a determination of the association shall be binding. And the Uniform Arbitration Act authorizes resort to the court in the provision that:

“(a) Upon application of a party, the court shall vacate an award where:
* # #
(2) There was evident partiality by an arbitrator appointed as a neutral or corruption in any one of the arbitrators or misconduct prejudicing the rights of any party;” (Ill. Rev. Stat. 1975, ch. 10, par. 112(a)(2).)

We conclude that the determination of the association is not binding upon the court. See, e.g., McKinney Drilling Co. v. Mach I Ltd. Partnership, 32 Md. App. 205, 359 A.2d 100, 102 (1976); cf. St. Paul Insurance Companies v. Lusis, 6 Wash. App. 205, 492 P.2d 575, 581 (1971).

II

Our disposition of the remaining issues requires a review of the record which includes the complaint of Star Forge to vacate or modify the award of the arbitrators supported by various documents, and the responsive pleadings of Freeport Construction. In substance Star Forge alleges in count I of its complaint that the original contract price was *514,136 with undisputed extras totaling *26,878, resulting in an adjusted contract price of *541,014; that the contract stated that the work would be completed by November 15, 1975, with time stated to be of the essence; that although the deadline was extended to November 30, 1975, the work was still substantially incomplete on that date with the major problem being Freeport Construction’s electrical subcontractor, Miller Engineering, which was not performing its work; that because of this on December 3, 1975, Star Forge removed both Freeport Construction and Miller Engineering from the project and employed another electrical contractor to complete the unfinished electrical work. The complaint further states that Freeport Construction responded by filing an arbitration demand with the American Arbitration Association pursuant to the construction contract. At the same time Miller Engineering filed a law suit against both Star Forge and Freeport Construction claiming a mechanic’s lien against the real estate in the amount of *50,812 which remains pending awaiting trial; that a panel of three arbitrators was appointed by the arbitration association to hear the dispute and conducted five nonconsecutive days of hearings; that Star Forge has paid out *452,690.01 to Freeport Construction, its various subcontractors and suppliers and including *61,723.23 paid to the substituted electrical contractor; this, when added together with the amount of the arbitrators’ award of *147,587.37, would put Star’s total cost to obtain full performance of its contract at *600,277.38 which would be *59,263.38 in excess of the adjusted contract price; that this result is contrary to section 21 of the Illinois Mechanics’ Lien Act which in substance provides that an owner shall not be compelled to pay a greater sum for the completion of the improvement than the price stipulated in the construction contract, with exceptions not applicable here. (Ill. Rev. Stat. 1975, ch. 82, par. 21.) Under count I Star Forge seeks an order modifying the award of the arbitrators by reducing the amount due Freeport Construction to *88,323.99.

As an alternative ground for setting aside the arbitration award count II in substance makes the further allegations that while the arbitration proceedings were pending Star Forge received a report that there were repeated business dealings between Miller Engineering (Miller) and one of the arbitrators, Robert R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Britz, Inc. v. Alfa-Laval Food & Dairy Co.
34 Cal. App. 4th 1085 (California Court of Appeal, 1995)
Haynes Construction Co. v. Cascella & Son Construction, Inc.
647 A.2d 1015 (Connecticut Appellate Court, 1994)
John E. Reid & Associates, Inc. v. Wicklander-Zulawski & Associates
627 N.E.2d 348 (Appellate Court of Illinois, 1993)
Staff v. State Farm Mutual Insurance
622 N.E.2d 434 (Ohio Court of Appeals, 1993)
Edward Electric Co. v. Automation, Inc.
593 N.E.2d 833 (Appellate Court of Illinois, 1992)
Drinane v. State Farm Mutual Automobile Insurance
584 N.E.2d 410 (Appellate Court of Illinois, 1991)
Welch v. Johnson
574 N.E.2d 49 (Appellate Court of Illinois, 1991)
King v. Sentry Claims Service
595 N.E.2d 380 (Ohio Court of Appeals, 1991)
Sarnoff v. De Graf Brothers, Inc.
554 N.E.2d 335 (Appellate Court of Illinois, 1990)
Muzzy v. Chevrolet Div., GMC
571 A.2d 609 (Supreme Court of Vermont, 1989)
Gerl Construction Co. v. Medina County Board of Commissioners
493 N.E.2d 270 (Ohio Court of Appeals, 1985)
J&K Cement Construction, Inc. v. Montalbano Builders, Inc.
456 N.E.2d 889 (Appellate Court of Illinois, 1983)
Bernard v. Hemisphere Hotel Management, Inc.
450 N.E.2d 1084 (Massachusetts Appeals Court, 1983)
State Farm Mutual Automobile Insurance v. Stuckey
445 N.E.2d 791 (Appellate Court of Illinois, 1983)
Saville International, Inc. v. Galanti Group, Inc.
438 N.E.2d 509 (Appellate Court of Illinois, 1982)
Beverly Bank v. Alsip Bank
436 N.E.2d 598 (Appellate Court of Illinois, 1982)
Indianapolis Public Transportation Corp. v. Amalgamated Transit Union
414 N.E.2d 966 (Indiana Court of Appeals, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
378 N.E.2d 558, 61 Ill. App. 3d 999, 19 Ill. Dec. 57, 1978 Ill. App. LEXIS 3123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/freeport-construction-co-v-star-forge-inc-illappct-1978.