McKinney Drilling Co. v. MacH I Ltd. Partnership

359 A.2d 100, 32 Md. App. 205, 1976 Md. App. LEXIS 417
CourtCourt of Special Appeals of Maryland
DecidedJune 30, 1976
Docket1219, September Term, 1975
StatusPublished
Cited by17 cases

This text of 359 A.2d 100 (McKinney Drilling Co. v. MacH I Ltd. Partnership) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKinney Drilling Co. v. MacH I Ltd. Partnership, 359 A.2d 100, 32 Md. App. 205, 1976 Md. App. LEXIS 417 (Md. Ct. App. 1976).

Opinion

* Gilbert, J.,

delivered the opinion of the Court.

The American Arbitration Association explains that *206 “[arbitration is the voluntary submission of a dispute to a disinterested person or persons for final determination.” 1 This appeal has resulted from an arbitration award which was vacated by Judge Joseph M. Mathias in the Circuit Court for Montgomery County. In order to determine whether the circuit court action was proper, we must set out a brief recitation of the circumstances underlying this appeal.

McKinney Drilling Company (McKinney), appellant, contracted with Mach I Limited Partnership (Mach), appellee, to supply materials and construct concrete caissons for an office building being constructed by Mach in Maryland. Mach refused to pay McKinney the approximately $51,000 contract balance for the work performed, asserting that the concrete did not meet the strength specifications required by Mach. The contract between the parties provided for resolving such disputes. Under the terms of the contract, disputes initially were to be submitted to the architects of the project. After they had made their determination, if either party was dissatisfied, it could demand that the dispute be submitted to the American Arbitration Association whose decision shall be final and enforceable under the law of the project situs.

In this case, the architects considered the dispute and, on November 1, 1973, notified McKinney that testing results indicated that the concrete did not meet the contract strength specifications. McKinney demanded arbitration of the dispute, and Mach counterclaimed in the arbitration proceeding for a minimum of $75,000 damages which it averred resulted from delays and additional construction costs arising out of the concrete’s weaknesses. The parties selected an arbitrator from a list supplied by the Association, and hearings were held.

In addition to the parties to the dispute, Maloney Concrete Company, the concrete supplier to McKinney, was permitted *207 to participate indirectly. 2 On May 28, 1974, the arbitrator found in favor of McKinney by awarding it $51,107.80 plus six percent interest from November 28, 1973. There were no findings of fact made. The counterclaim of Mach was not decided. The only statement made by the arbitrator, besides the amount of the award, was that “[t]his award is in full settlement of all claims submitted to this arbitration.”

On June 18, 1974, McKinney filed a petition in the Circuit Court for Montgomery County, pursuant to Md. Ann. Code, Courts and Judicial Proceedings Art. § 3-227, seeking confirmation of the arbitration award inasmuch as Mach had not yet paid the amount awarded. Mach answered and both parties moved for summary judgment. 3 The motions were denied, according to McKinney, because the pleadings and arguments of counsel left doubt in the judge’s mind as to how Mach’s counterclaim had been treated by the arbitrator. McKinney then sought to reopen the arbitration for the purpose of clarifying the award. On June 27, 1975, the court granted the motion and ordered the parties to exchange questions and agree upon those to be asked of the arbitrator.

Prior to the inquisition of the arbitrator by the parties, the arbitrator notified the American Arbitration Association that his construction company, subsequent to the arbitration award in this case, submitted a bid to *208 develop a building on property owned by Maloney Concrete Company. The parties were also notified, and Mach immediately objected to the arbitrator’s continuing to act in this dispute. When Mach’s objection was overruled by the Association, Mach then moved that the court strike its order reopening the arbitration. The motion was denied, but the court issued a supplemental order permitting the parties to ask questions of the arbitrator concerning his prior relationship with Maloney Concrete Company.

Pursuant to that order, a hearing was held on August 13, 1975, in which McKinney and Mach inquired of the arbitrator as to his relationship with Maloney. The arbitrator explained that he bought concrete from Maloney to use in his company’s construction projects. The record indicates that the relationship was ongoing at the time the arbitrator considered the McKinney-Mach dispute, although the amount of concrete bought in recent years had been extremely small. When questioned about his treatment of Mach’s counterclaim, the arbitrator stated “... I neither granted it [the counterclaim] or denied it. I did not consider it because it was outside the scope of the arbitration.” The arbitrator further said that he had issued no findings of fact or conclusions of law because neither is required by the Association’s rules.

Subsequent to the arbitrator inquiry hearing, Mach, on September 11,1975, filed an amended answer to the petition for confirmation in which Mach asserted that the arbitration award should be vacated because (1) not all the claims were adjudicated; (2) Maloney participated in the arbitration hearings even though Mach had no agreement with Maloney; and (3) the arbitrator did not disclose his own relationship with Maloney. Both McKinney and Mach again moved for summary judgment. McKinney’s motion was denied, but summary judgment was granted for Mach, and Judge Mathias ordered that the arbitration award be vacated.

No transcript of the hearing or findings of fact, if any, or conclusions of law reached by the judge are included in the record. While McKinney’s brief and argument advance a *209 number of issues for our review, 4 we think the only question is whether the hearing judge erred in granting Mach’s motion for summary judgment.

The duties of an appellate court, when reviewing a motion for summary judgment, are extensively discussed in Lynx, Inc. v. Ordinance Products, Inc., 273 Md. 1, 327 A. 2d 502 (1974):

“In reviewing the propriety of the grant of a summary judgment we are concerned primarily with deciding whether a factual issue which was material to the resolution of the controversy existed and whether the trial judge was legally correct.... Where the record shows that there was no such genuine dispute as to any material fact necessary to resolve the controversy as a matter of law, and it is shown that the movant is entitled to judgment, the entry of summary judgment is proper.” 273 Md. at 8. (Citations omitted).

This is the test we shall apply in this case.

McKinney does not dispute the material facts that the arbitrator never expressly ruled on Mach’s counterclaim even though it was properly before him, did not disclose his ongoing relationship with Maloney Concrete, and allowed *210 Maloney, indirectly, to participate in the arbitration hearing through its counsel and vice-president although it had no agreement with Mach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Venners v. Goldberg
758 A.2d 567 (Court of Special Appeals of Maryland, 2000)
Beebe Medical Center, Inc. v. InSight Health Services Corp.
751 A.2d 426 (Court of Chancery of Delaware, 1999)
Parks v. Sombke
732 A.2d 907 (Court of Special Appeals of Maryland, 1999)
Casias v. Dairyland Insurance
1999 NMCA 046 (New Mexico Court of Appeals, 1999)
Wills v. Baltimore County
707 A.2d 108 (Court of Special Appeals of Maryland, 1998)
Robb v. Wancowicz
705 A.2d 125 (Court of Special Appeals of Maryland, 1998)
Hott v. Mazzocco
916 F. Supp. 510 (D. Maryland, 1996)
Baltimore Teachers Union v. Mayor and City Council of Baltimore
671 A.2d 80 (Court of Special Appeals of Maryland, 1996)
Marsh v. Loffler Housing Corp.
648 A.2d 1081 (Court of Special Appeals of Maryland, 1994)
Atlantic Aviation, Inc. v. EBM Group, Inc.
11 F.3d 1276 (Fifth Circuit, 1994)
King v. Sentry Claims Service
595 N.E.2d 380 (Ohio Court of Appeals, 1991)
Snyder v. BERLINER CONSTRUCTION CO.
555 A.2d 523 (Court of Special Appeals of Maryland, 1989)
Gerl Construction Co. v. Medina County Board of Commissioners
493 N.E.2d 270 (Ohio Court of Appeals, 1985)
Hartman v. Cooper
474 A.2d 959 (Court of Special Appeals of Maryland, 1984)
Tyson v. Masten Lumber & Supply, Inc.
408 A.2d 1051 (Court of Special Appeals of Maryland, 1979)
Freeport Construction Co. v. Star Forge, Inc.
378 N.E.2d 558 (Appellate Court of Illinois, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
359 A.2d 100, 32 Md. App. 205, 1976 Md. App. LEXIS 417, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckinney-drilling-co-v-mach-i-ltd-partnership-mdctspecapp-1976.