Davidson, J.,
delivered the opinion of the Court.
Bel Pre Medical Center, Inc., appeals from an order of the Circuit Court for Montgomery County which, on the motion of Frederick Contractors, Inc., directed the parties to stay the arbitration of a dispute arising out of a construction contract between them. The facts are essentially undisputed.
On 4 August 1971 the parties entered into a contract entitled “Standard Form of Agreement Between Owner and Contractor” which included as a part of the contract a document entitled “General Conditions of the Contract for Construction.”
By the terms of this contract the appellee, Frederick Contractors, Inc. (hereinafter referred to as the contractor), agreed, for a stipulated sum, to build for the appellant, Bel Pre Medical Center, Inc. (hereinafter referred
to as the owner), a two-story addition to the owner’s nursing home in Montgomery County.
The relevant portions of the contract, in the order of their importance, provide as follows:
“7.10.1 [General Conditions]. All claims, disputes and other matters in question arising out of, or relating to, this Contract or the breach thereof, except as set forth in Subparagraph 2.2.9 with respect to the Architect’s decisions on matters relating to artistic effect, and except for claims which have been waived by the making or acceptance of final payment as provided by Subparagraphs 9.7.5 and 9.7.6, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. This agreement so to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.
“7.10.2 [General Conditions]. Notice of the demand for arbitration shall be filed in writing with the other party to the Contract and with the American Arbitration Association, and a copy shall be filed with the Architect. The demand for arbitration shall be made within the time limits specified in Subparagraphs 2.2.10 and 2.2.11 where applicable, and in all other cases within a reasonable time after the claim, dispute or other matter in question has arisen, and in no event shall it be made after institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations.
“2.2.7 [General Conditions]. Claims, disputes and
other matters in question between the Contractor and tne Owner relating to the execution or progress of the Work or the interpretation of the Contract Documents shall be referred initially to the Architect for decision which he will render in writing within a reasonable time.
“2.2.9 [General Conditions]. The Architect’s decisions in matters relating to artistic effect will be final if consistent with the intent of the Contract Documents.
“2.2.10 [General Conditions], Any claim, dispute or other matter that has been referred to the Architect, except those relating to artistic effect as provided in Subparagraph 2.2.9 and except any which have been waived by the making or acceptance of final payment as provided in Subparagraphs 9.7.5 and 9.7.6, shall be subject to arbitration upon the written demand of either party. However, no demand for arbitration of any such claim, dispute or other matter may be made until the earlier of: .1 the date on which the Architect has rendered his decision, or .2 the tenth day after the parties have presented their evidence to the Architect or have been given a reasonable opportunity to do so, if the Architect has not rendered his written decision by that date.
“2.2.11 [General Conditions], If a decision of the Architect is made in writing and states that it is final but subject to appeal, no demand for arbitration of a claim, dispute or other matter covered by such decision may be made later than thirty days after the date on which the party making the demand received the decision. The failure to demand arbitration within said thirty days’ period will result in the Architect’s decision becoming final and binding upon the Owner and the Contractor. If the Architect renders a decision after arbitration proceedings have been initiated, such decision may be entered as evidence but will not
supersede any arbitration proceedings except where the decision is acceptable to the parties concerned.”
On 12 January 1973 the architect and representatives of the owner and the contractor met to inspect the premises and to determine what items remained to be completed by the contractor. On 16 January 1973 the architect wrote a letter to the owner which stated as follows:
“We hereby certify that to the best of our knowledge, information and belief, and on the basis of our observation and inspection the Work has been completed In accordance with the terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor, except as noted below is due and payable.
We have attached herewith a copy of our final “Punch List” dated 12 January 1973. We feel an equitable sum of $5,000.00 should be withheld from final payment of retainage until this “Punch List” is complete.”
The “punch list” contains 58 separate minor items remaining to be done. On or about 16 January 1973, the contractor submitted written requisitions for payment. On 27 January 1973 a meeting took place between the owner and the contractor at which a dispute arose whieh was not then resolved.
Final payment has not been made by the owner.
On 22 March 1973 the contractor recorded a mechanic’s lien on the subject property and on 30 April 1973 filed a bill in equity to foreclose on the lien. On 22 May 1973 the owner made a demand upon the contractor for arbitration in which he charged that the contractor:
1) failed to construct the building according to specifications;
2) failed to recognize the architect as an employee of the owner;
3) interfered with the contractual relationship between the architect and the owner; and
4) failed to obtain certificates of payment signed by the architect.
On 8 June 1973 the contractor refused to participate in the arbitration proceedings “unless ordered by the Circuit Court for Montgomery County to do so.”
On 24 May 1973 the owner moved to strike the mechanic’s lien on the grounds that arbitration was the sole and exclusive remedy which the contractor could utilize to enforce his rights. On 12 June 1973 this motion was denied. On 19 June the owner filed his answer to the contractor’s bill of complaint. He admitted all of the contractor’s allegations except the amounts in dispute, and averred that the contractor had waived his right to file a mechanic’s lien by failure to demand arbitration. On 27 June 1974 the contractor applied for an ex parte injunction to stay the arbitration demanded by the owner on the ground that the owner had failed to demand arbitration within thirty days of the receipt of the architect’s letter. The ex parte injunction was granted.
On 12 July a hearing was held to determine whether a permanent injunction enjoining the arbitration proceeding should issue. Judge Philip M. Fairbanks found that the question presented was “whether the provisions [¶¶ 2.2.10 and 2.2.11 of the General Conditions] requiring demand for arbitration to be made within thirty days of the architect’s decision apply or whether the provisions [¶ 7.10.2 of the General Conditions] requiring demands for arbitration to be made within a reasonable time after claim or within the statute of limitations apply.” Judge Fairbanks determined that the architect’s letter of 16 January 1973 constituted “his decision that the work was completed and that the contractor was entitled to be paid;” that under the contract the owner was required to demand arbitration “within thirty days of the architect’s letter, or at most within thirty days of January 27, 1973;” and that the owner, therefore, had sought arbitration too late. The judge further found that
“even were the provisions of 2.2.10 and 2.2.11 not applicable, the owner’s demand for arbitration comes not within a reasonable time, having been delayed until nearly a month after the filing of the mechanic’s lien.” An order permanently enjoining the parties from proceeding with arbitration was entered on 3 August 1973. It is this order from which the owner appeals.
The question before us concerns the effect of an arbitration clause agreed to by the owner and the contractor. Appellant-owner contends here, as he did below, that the agreement of the parties to arbitrate “all claims, disputes, and other matters in question arising out of, or relating to this contract or the breach thereof’ is binding upon the parties and precludes a court from determining the amount of money due for labor and materials furnished by the contractor to the owner. He insists that by agreement of the parties this issue must be determined by the arbitrator. Appellee-contractor does not dispute the fact that the issue of the amount of money due and owing for labor and materials is arbitrable under the terms of the agreement but contends that the owner waived his right to arbitration by failing to file a timely demand for arbitration. In support of this position the contractor argues, in the alternative, either that the architect’s letter of 16 January 1973 constituted an “architect’s decision” within the meaning of Paragraph 2.2.10 of the agreement so that under Paragraph 2.2.11 a demand for arbitration was required to be filed within 30 days, or that a dispute arose at the meeting of 27 January 1973 so that under Paragraph 7.10.2 a demand for arbitration had to be filed within a reasonable time. The contractor asserts that in either event the demand for arbitration, made on 22 May 1973, was too late. The owner asserts that the architect’s letter of 16 January 1973 is not
an “architect’s decision” so that he was not under an obligation to demand arbitration within 30 days; that his demand for arbitration was filed well within the period of limitations established by Paragraph 7.10.2 of the agreement and was therefore filed within a reasonable time; and, most importantly, that under the broad language of Paragraph 7.10.1 the very question of whether there was compliance on his part with the procedural requirements of the contract for the initiation of arbitration proceedings is to be determined by the arbitrator and not by the court.
“Since time immemorial, governments have provided means, either in the person of the Sovereign himself, or in the form of courts, for settlement of disputes between subjects.” Mullen, “Arbitration under Maryland Law,” 2
Md. L. Rev.
326 (1938). Arbitration is the process whereby parties voluntarily agree to substitute a private tribunal for the public tribunal otherwise available to them. The arbitration process provides a speedy, informal, relatively inexpensive, and private procedure for resolving controversies arising out of commercial transactions, as well as a tribunal uniquely qualified to resolve such disputes.
Schreiber v. Pac. Coast Fire Ins. Co.,
195 Md. 639, 647, 75 A. 2d 108, 111-12 (1950);
Dominion Marble Co. v. Morrow,
130 Md. 255, 260, 100 A. 292, 293 (1917);
California Law Revision Comm’n, A Study Relating to Arbitration
G-25 (1960);
M. Domke, The Law and Practice of Commercial Arbitration,
§ 2.01 at 10 (1968); Aksen, “Resolving Construction Contract Disputes Through Arbitration,” 23
Arb. J.
141, 158 (1968); Cushman, “Arbitration and State Law,” 23
Arb. J.
162 (1968). The arbitrator is not a public official imposed upon the parties by a superior authority, and he is not required to administer justice for a community which transcends the parties. Rather, he is a part of the system of self-government created by and confined to the parties and designed to serve their specialized needs. The arbitrator is usually chosen because of the parties’ confidence in his knowledge of the practices of the industry which enables him to employ considerations in fashioning his judgments which may be foreign to the expertise of the courts. The
parties expect that the arbitrator’s competence and skill, based on his specialized knowledge and experience, will produce a judgment which is founded not only upon the literal meaning of the words appearing in the contract document itself, but also on their meaning in the context of the practices and customs associated with their use.
Schreiber v. Pac. Coast Fire Ins. Co., supra;
Phillips, “A Lawyer’s Approach to Commercial Arbitration,” 44
Yale L. J.
31, 40-41 (1934);
see
Shulman, “Reason, Contract, and Law in Labor Relations,” 68
Harv. L. Rev.
999, 1016-18 (1955).
The view of courts toward the arbitration process has been somewhat ambivalent. The common law, recognizing the value of arbitration, permitted parties to agree voluntarily that they would submit to arbitration their existing or possible future disputes. If the agreement to arbitrate was performed by the parties and an arbitrator’s award obtained, the award would be enforced by the courts.
Nelley v. Baltimore City,
224 Md. 1, 8-9, 166 A. 2d 234, 237 (1960);
Mayor and City Council of Baltimore v. Clark,
128 Md. 291, 309, 97 A. 911, 917 (1916). Indeed, suits to enforce an arbitrator’s award were described as “favored” actions,
Parr Construction Co. v. Pomer,
217 Md. 539, 543, 144 A. 2d 69, 72 (1958);
Dominion Marble Co. v. Morrow, supra; Lewis v. Burgess,
5 Gill. 129, 131 (1847);
Caton v. McTavish,
10 G. & J. 192, 216-17 (1838); and the awards of arbitrators would not be set aside by the courts unless the arbitrator was guilty of fraud, misconduct or prejudice, had exceeded his authority, or had made a mistake in law or fact appearing on the face of the award.
Chillum v. Button
&
Goode,
242 Md. 509, 517, 219 A. 2d 801, 806 (1966);
Parr Construction Co. v. Pomer, supra,
217 Md. at 543-44; 144 A. 2d at 72;
Witz v. Tregallas,
82 Md. 351, 369-70, 33 A. 718, 721-22 (1896);
Roloson v. Carson,
8 Md. 208, 220-22 (1855). But at common law it was also the general rule that, in the absence of legislative direction to the contrary, an executory agreement for arbitration of the ultimate rights of the parties, such as an agreement to arbitrate all future disputes that might thereafter arise, even though resort to arbitration was specified to be a condition precedent to court action, was not
enforceable and could not constitute a bar to legal or equitable redress in the courts. Courts and commentators reasoned that such a contract, which ousted the jurisdiction of the courts, was against public policy and illegal; or that such an agreement affected only the remedies available to the parties and not their substantive rights; or that such an agreement was revocable at will.
Eisel v. Howell,
220 Md. 584, 587-588, 155 A. 2d 509, 511 (1959);
Tomlinson v. Dille,
147 Md. 161, 167, 127 A. 746, 748 (1925). Thus, while suits to enforce an arbitration award were viewed as “favored” actions, executory agreements for arbitration were consigned to an “unfavored” status and suits to compel arbitration or to stay court proceedings pending arbitration could not be brought.
In Maryland arbitration was governed by the common law rules until 1965, the year in which the Maryland Uniform Arbitration Act, Code (1957), Art. 7, was enacted by the General Assembly.
The Uniform Arbitration Act is the
product of the National Conference of Commissioners on Üniform State Laws and was approved in 1956. It has now been adopted by seventeen states, including Maryland.
The Maryland Act provides, in pertinent part:
“§ 1. A written agreement to submit any existing controversy to arbitration or a provision in a written contract to submit to arbitration any controversy thereafter arising between the parties is valid, enforceable and irrevocable, save upon such grounds as exist at law or in equity for the revocation of any contract. This article does not apply to an arbitration agreement between employers and employees or between their respective representatives unless it is expressly provided in such agreement that this article shall apply.
“§ 2. (a)
When court to order arbitration; expeditious hearing to determine issue; ordering arbitration or denial of application.
— On application of a party showing an agreement described in § 1, and the opposing party’s refusal to arbitrate, the court shall order the parties to proceed with arbitration, but if the opposing party denies the existence of the agreement to arbitrate, the court shall proceed expeditiously to the determination of the issues so raised and sh9.ll order arbitration if found for the moving party, otherwise, the application shall be denied.
“(b)
Staying arbitration. —
On application, the court may stay an arbitration proceeding commenced or threatened on a showing that there is no agreement to arbitrate as described in § 1. Such an issue, when in substantial and bona fide dispute, shall be forthwith tried and the stay ordered if found for the moving party. If found for the opposing party, the court shall order the parties to proceed to arbitration.
“(c)
Courts in which application may he made.
— If an issue referable to arbitration under the alleged agreement is involved in an action or proceeding pending in a court having jurisdiction to hear applications under subsection (a) of this section, the application shall be made therein. Otherwise and subject to § 17, the application may be made in any court of competent jurisdiction.
“(d)
Stay of proceedings when order of arbitration or application therefor made; when order to include stay.
— Any action or proceeding involving an issue subject to arbitration shall be stayed if an order for arbitration or an application therefor has been made under this section or, if the issue is severable, the stay may be with respect thereto only. When the application is made in such action or proceeding, the order for arbitration shall include such stay.
“(e)
When order not to he refused.
— An order for arbitration shall not be refused or an arbitration proceeding stayed on the ground that the claim in issue lacks merit or bona fides or because a valid basis for the claim sought to be arbitrated has not been shown.”
The Uniform Arbitration Act constitutes a radical
departure from the common law. Executory agreements to arbitrate are to be deemed “valid, irrevocable and enforceable,” and suits to compel arbitration or to stay the action of a court pending arbitration may now be brought. The prime purpose of these provisions is to discourage litigation and to foster voluntary resolution of disputes in a forum created, controlled and administered according to the parties’ agreement to arbitrate.
Maietta v. Greenfield,
267 Md. 287, 291, 297 A. 2d 244, 246 (1972);
Accord, School District No. 46 v. Del Bianco,
68 Ill. App. 2d 145, 215 N.E.2d 25, 31 (1966);
Layne-Minnesota Co. v. Regents of Univ. of Minn.,
266 Minn. 284, 123 N.W.2d 371, 374-75 (1963). Thus, by its enactment, the General Assembly established a policy in favor of the settlement of disputes through the arbitration process and ended the ambivalence of courts under the common law. Not only suits to enforce an arbitrator’s award, but also suits to compel arbitration and suits to stay court action pending arbitration, are now to be viewed as “favored” actions.
In accord with the legislative policy in favor of the enforcement of executory agreements to arbitrate, the Act strictly confines the function of the court in suits to compel arbitration to the resolution of a single issue: is there an agreement to arbitrate the subject matter of the dispute. What is sought in such suits is the enforcement of an agreement to arbitrate. Whether one is seeking a court order directing the parties to proceed to arbitration under § 2 (a), resisting a demand for arbitration and seeking an order staying it under § 2 (b), or seeking to stay a court action and obtain an order directing arbitration under § 2 (d), the question is always the same: is there an agreement to arbitrate?
Where the language of the arbitration provisions is clear and precise, there is no problem for the court. If it is plain that the dispute sought to be arbitrated falls within the scope of the arbitration clause, arbitration should be compelled. If it is apparent, on the other hand, that the issue sought to be arbitrated lies beyond the scope of the arbitration clause, the opposing party should not be compelled to submit to arbitration, since there is no agreement to arbitrate. Where there is a broad arbitration clause, calling for the arbitration of any and all disputes arising out of the contract, all issues are arbitrable
unless expressly and specifically excluded.
McCandliss v. Ward W. Ross, Inc.,
45 Mich. App. 342, 206 N.W.2d 455, 457 (1973);
Michigan Mutual Liability Co. v. Graham,
44 Mich. App. 406, 205 N.W.2d 289, 291 (1973);
Maryland Casualty Co. v. McGee,
32 Mich. App. 539, 189 N.W.2d 44, 48 (1971);
Grover-Diamond Ass’n v. American Arbitration Ass’n,
Minn., 211 N.W.2d 787, 790 (1973).
A problem is created for the court when the language of the arbitration provision is unclear as to whether the subject matter of the dispute falls within the scope of the arbitration agreement. In such circumstances the legislative policy in favor of the enforcement of agreements to arbitrate dictates that the question should be left to the decision of the arbitrator. Whether the party seeking arbitration is right or wrong is a question of contract application and interpretation for the arbitrator, not the court, Code (1957), Art. 7, § 2 (e), and the court should not deprive the party seeking arbitration of the arbitrator’s skilled judgment by
attempting to resolve the ambiguity.
Under such circumstances arbitration should be compelled.
Here the parties agreed to submit to arbitration “all claims, disputes and other matters in question arising out of or relating to the contract or the breach thereof.” Without first seeking arbitration the contractor filed suit to enforce a mechanic’s lien for money allegedly due and owing under the agreement. Thereafter the owner made a demand for arbitration of issues concerning the amount of money, if any, that was due and owing. The contractor refused to arbitrate and sought to stay the arbitration proceeding, not because the arbitrability of the substantive issues was questioned but rather because of a dispute as to whether the demand for arbitration had been timely made. Thus the question of substantive arbitrability is not before us. The
precise issue which we must resolve is whether the question of compliance with the procedural prerequisite of a timely demand growing out of the arbitrable dispute should be determined by the arbitrator or a court.
Neither Maryland nor any other state which has adopted the Uniform Arbitration Act has decided this issue.
However, the identical question has been resolved by the United States Supreme Court in a suit brought by a labor organization to compel arbitration under § 301 of the Labor Management Relations Act.
In
John Wiley & Sons, Inc. v. Livingston,
376 U. S. 543, 84 S. Ct. 909 (1964), the company
alleged that it had no duty to arbitrate a dispute found by the court to be arbitrable because the Union had failed to comply with certain of the procedural prerequisites to arbitration required by the governing collective bargaining agreement, including a requirement for a timely filing of the demand for arbitration.
There the Court said:
“We think that labor disputes of the kind involved here cannot be broken down so easily into their ‘substantive’ and ‘procedural’ aspects. Questions concerning the procedural prerequisites to arbitration do not arise in a vacuum; they develop in the context of an actual dispute about the rights of the parties to the contract or those covered by it. . . .
“Doubt whether grievance procedures or some part of them apply to a particular dispute, whether such procedures have been followed or excused, or whether the unexcused failure to follow them avoids the duty to arbitrate cannot ordinarily be answered without consideration of the merits of the dispute which is presented for arbitration....
It would be a curious rule which required that intertwined issues of ‘substance’ and ‘procedure’ growing out of a single dispute and raising the same questions on the same facts had to be carved up between two different forums, one deciding after the other. Neither logic nor considerations of policy compel such a result.
“Once it is determined, as we have, that the parties are obligated to submit the subject matter of a dispute to arbitration, ‘procedural’ questions
which grow out of the dispute and bear on its final disposition should be left to the arbitrator. Even under a contrary rule, a court could deny arbitration only if it could confidently be said not only that a claim was strictly ‘procedural,’ and therefore within the purview of the court, but also that it should operate to bar arbitration altogether, and not merely limit or qualify an arbitral award. In view of the policies favoring arbitration and the parties’ adoption of arbitration as the preferred means of settling disputes, such cases are likely to be rare indeed. In all other cases, those in which arbitration goes forward, the arbitrator would ordinarily remain free to reconsider the ground covered by the court insofar as it bore on the merits of the dispute, using the flexible approaches familiar to arbitration. Reservation of ‘procedural’ issues for the courts would thus not only create the difficult task of separating related issues, but would also produce frequent duplication of effort.
“In addition, the opportunities for deliberate delay and the possibility of well-intentioned but no less serious delay created by separation of the ‘procedural’ and ‘substantive’ elements of a dispute are clear. While the courts have the task of determining ‘substantive arbitrability,’ there will be cases in which arbitrability of the subject matter is unquestioned but a dispute arises over the procedures to be followed. In all of such cases, acceptance of Wiley’s position would produce the delay attendant upon judicial proceedings preliminary to arbitration. As this case, commenced in January 1962 and not yet committed to arbitration, well illustrates, such delay may entirely eliminate the prospect of a speedy arbitrated settlement of the dispute, to the disadvantage of the parties (who, in addition, will have to bear increased costs) and contrary to the aims of national labor policy.
“No justification for such a generally undesirable result is to be found in a presumed intention of the parties. Refusal to order arbitration of subjects which the parties have not agreed to arbitrate does not entail the fractionating of disputes about subjects which the parties do wish to have submitted. Although a party may resist arbitration once a grievance has arisen, as does Wiley here, we think it best accords with the usual purposes of an arbitration clause and with the policy behind federal labor law to regard procedural disagreements not as separate disputes but as aspects of the dispute which called the grievance procedures into play.” 376 U. S. at 556-59, 84 S. Ct. at 918-19.
This rule has been consistently followed and applied by federal courts.
While the principles enunciated in
Wiley
do not flow from an interpretation of the Uniform Arbitration Act, the Congressional policy favoring the enforcement of agreements to arbitrate which led the Supreme Court to its resolution of this issue under § 301 are parallel to the
policies underlying the Uniform Arbitration Act. Under § 301 the function of the court is strictly confined to ascertaining whether the parties agreed to arbitrate the subject matter of the dispute.
When the parties have agreed to submit any and all controversies arising out of the contract to an arbitrator, all issues other than those expressly and specifically excluded must be submitted to arbitration.
All doubts concerning the arbitrability of the
subject matter of the dispute are to be resolved in favor of arbitration.
Once it is determined that an arbitrable issue
exists the parties are not to be deprived by the courts of the benefits of arbitration for which they bargained — speed in the resolution of the dispute and the employment of the specialized knowledge and competence of the arbitrator.
Wiley v. Livingston, supra,
376 U. S. at 557-58, 84 S. Ct. 918-19.
We are convinced that the rule enunicated in the
Wiley
case, applicable to arbitration under collective bargaining agreements in suits brought under § 301 of the Labor Management Relations Act, is sound and totally consistent with the intent and purposes of the Uniform Arbitration Act. The rule promotes the benefits of arbitration. It removes the “difficult task of separating related issues” from the courts and avoids duplication of effort and unjustifiable delay. We believe that the application of
Wiley
to commercial arbitration would properly effectuate the legislative policy in favor of the enforcement of executory agreements to arbitrate which the Uniform Arbitration Act expresses.
The application of
Wiley
to the instant case produces a clear result. Here the substantive arbitrability of the dispute is unquestioned and the only area of conflict relates to compliance with the procedural prerequisite of timeliness of the demand for arbitration. We can find no justification for the fractionating of a dispute which the parties agree to submit to arbitration. Accordingly we now hold that under an arbitration clause such as is present in this case, when parties are obligated to submit the subject matter of their dispute to arbitration, “procedural” questions which grow out of the dispute and bear on its final disposition should be left to the arbitrator.
The trial court erred in ordering a stay of arbitration. Accordingly, we shall reverse and remand for the entry of an order to compel arbitration and to stay further proceedings in the Circuit Court for Montgomery County.
Order reversed.
Case remanded for further proceedings in accordance with this opinion.
Costs to be paid by appellee.